What was decided
The Executive approved using the existing budget of up to £250,000 for a consultancy contract covering only RIBA stages 1 and 2 of the Broadwater Park redevelopment. Report 2.1, P2
Authority was delegated to the Strategic Director of Economy, Planning and Place to award the contract in line with procurement rules and the approved budget. Report P3
The Executive still regards Broadwater Park as a strategic priority and wants to appoint the preferred bidder to begin the work. Report 3.1, P6, P7
Why
Tenders received for work up to RIBA stage 3 came in over the agreed £250,000 budget. Report P15
Officers said stage 3 is hard to price reliably until stages 1 and 2 are complete, and the council is facing continued high inflation in consultant fees. Report 6.4, 6.5
Under the original April 2025 decision, the full outcomes could not be delivered within the approved budget, so a reduced scope now needs Executive sign-off. Report P46
What happens next
Officers will progress the procurement and appoint the preferred bidder, then formalise the contract under delegated authority. Report 4.1, P8
A separate budget request to support a planning application will go to the annual budgeting cycle; the unspent balance from stages 1 and 2 can be carried into stage 3 or released. Report P8, P44
The council will engage the Surrey County Council Waste and Minerals team and share learning with Guildford Borough Council on a similar former landfill project. Report 8.1, 8.3, P30
The money
£250,000 Existing approved budget for the Broadwater Park project, to be used for RIBA stages 1 and 2 only Report 2.1, P2, P42
£136,000 Virement of unspent budget from the Central Godalming Regeneration project to Broadwater Park Report 6.1, P19
£114,000 Supplementary budget estimate funded from the capital contingency reserve Report 6.1, P19
Options considered
Chosen: Proceed with the project using existing funding for feasibility and design concepts only (RIBA stages 1 and 2). Allows the project to continue, lets detailed surveys refine the full scope, and avoids delay; further funding to be sought through the capital budgeting process for 2026 Report 11.1, P40
Rejected: Do not proceed with the project at this stage. Full planning application is not affordable within the current budget; would require a further report to seek extra funding and cause a delay of several months during which legal obligations could otherwise be progressed Report P40
Implications
Financial: The £250,000 budget is unchanged but will now only cover stages 1 and 2; a business case for further stage 3 funding has been submitted to the council's budget-setting process. Report P42, P43
Risk: Planning permission is required before any works and cannot be submitted until landfill monitoring is complete, with a risk the application is refused; mitigated by an experienced design team and a pre-application approach. Report 10.1, P36
Legal: The council has time-sensitive obligations to the former golf club tenant under a settlement agreement. Report 10.2, P36
Legal: The Executive's April 2025 decision assumed certain outcomes for £250,000; market testing has shown those outcomes are not affordable, so Executive approval is needed for a reduced set of outcomes. Report P46
Equalities: Officers concluded there are no equality and diversity implications arising directly from this report. Report P52
Climate: Officers concluded there are no climate change or sustainability implications arising directly from the recommendations. Report P56
Other: Under local government reorganisation, property interests may transfer to a successor unitary authority; the council will protect its existing interests in the meantime. Report 8.2, P30
Who and where
Residents and visitors to the borough who use Broadwater Park's natural greenspaces Report P24, P26
Local businesses potentially involved in delivering leisure activities on the site Report P27
Residents' health and leisure use, both informal and formal, of the area Report P28
The former golf club tenant, under a time-sensitive settlement agreement Report 10.2, P36
Any successor unitary authority under local government reorganisation Report 8.2, P30
Timeline
1 April 2025: Previous Executive decision approved updated project objectives and the £250,000 total project budget Report 6.1, P17, P18, P19
20 October 2025: Paper discussed at Executive Briefing Report 9.1, P35
4 November 2025: Executive agreed the updated scope Report 2.1
January 2026: Exempt tender pricing and scoring information may be released for public inspection on completion of the contract Report 5.3, P15
Q1 2026/7: Update on progress to be considered by the Overview and Scrutiny Committee Report 14.1, P60
Plain English for the jargon
RIBA stages: The Royal Institute of British Architects' standard work stages covering design and construction of a building or landscape project, from preparation (stage 1) through to construction and use (stage 7)
Virement: Transfer of budget from one spending heading to another within the council's accounts
Pre-app: A pre-application discussion with the local planning authority before a formal planning application is submitted
Options Appraisal: A structured assessment of different ways the site could be used or developed
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 96/25
Resolved
RESOLVED that: 1. A change in contract scope to be delivered using the allocated budget of up to £250,000 for the Broadwater Park redevelopment project consultancy contract to be used for RIBA stages 1 and 2 only be approved. 2. Authority be delegated to the Strategic Director of Economy, Planning ... EXE 96/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
2.1.1 Approves a change in contract scope to be delivered using the allocated budget of up to £250,000 for the Broadwater Park redevelopment project consultancy contract to be used for RIBA stages 1 and 2 only.
2.1.2 Delegates to the Strategic Director of Economy, Planning and Place the authority to enter into the consultancy contract with the winning tenderer, in compliance with Procurement Procedure Rules, the Council’s Constitution and within the approved budget.
3 Reason(s) for recommendation:
3.1The Executive still considers the Broadwater Park project to be a strategic priority of considerable potential value to residents. 3.2 The resetting of this work will still enable the Council to appoint the preferred bidder for the multi-disciplinary consultancy
2 Broadwater Park – updated scope of work
contract and initiate work pursuant to the Executive decision of April 2025, which seeks to identify a long-term solution for the landfill and assess redevelopment opportunities at Broadwater Park.
4 Next steps
4.1Subject to the approval of the recommendations set out in this report, Officers will progress the procurement process, leading to an appointment, and formalise the contract with the preferred bidder, in line with the relevant delegated authorities. 4.2 A budget request to support the development and submission of a planning application will be submitted for consideration as part of the annual budgeting cycle.
5 Exemption from publication
5.1Part of this report is exempt from publication.
5.2The content of the Appendix 1 is to be treated as exempt for the purposes of the Council’s Access to Information Procedure Rules because it contains pricing and scoring of tenders and is therefore exempt by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act as follows:
Information relating to the financial or business affairs of any particular person (including the authority holding that information).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.