Community Infrastructure Levy (CIL) Exceptional Circumstances Relief
DecidedCommittee3 papers
AI summaryWaverley Borough Council adopts CIL Exceptional Circumstances Relief Policy, enabling reduced levy payments for unviable developments from 1 April 2026.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedPolicy adopted and relief made available
MoneyNot stated
What happens nextClaims accepted from 1 April 2026Statement to be issued at least 14 days before
Who it affectsDevelopers with Section 106 agreementsWhere CIL payment would render development unviable
What was decided
The Council made CIL relief for exceptional circumstances available in its area under Regulations 55 to 57 of the CIL Regulations 2010 (as amended). Report P6, 6.5, 6.6
The Council adopted the Waverley Borough Council CIL Exceptional Circumstances Relief Policy set out in Appendix 1. Report P8
Authority to determine claims was delegated to the Joint Assistant Director for Planning, in line with the policy, the CIL Regulations 2010 and the Subsidy Control Act 2022. Report P9, 6.19
Why
The relief is intended to avoid rendering sites with specific and exceptional cost burdens unviable, providing a mechanism to enable growth where exceptional circumstances arise. Report 3.1, 6.7, 6.16, 7.2
Adopting the policy and delegating decisions allows robust, transparent and effective implementation of the relief in line with the CIL Regulations. Report 6.19
Waverley's CIL rates were set using viability evidence that considered Section 106 obligations and Local Plan policies, so claims are expected to be rare. Report 6.3
What happens next
At least 14 days before 1 April 2026, the Council will issue a statement giving notice that exceptional circumstances relief is available and stating the start date for claims. Report 5.1, P17
The statement will be published on the Council's website and made available for inspection under the CIL Regulations. Report 5.2
Each claim will be assessed case by case, and any relief granted must also comply with the Subsidy Control Act 2022. Report 6.9
Options considered
Rejected: Option 1: Do not make CIL Exceptional Circumstances Relief available and do not adopt the policy. Would leave the Council with no mechanism to avoid rendering sites with exceptional cost burdens unviable. Report 11.1, P50
Chosen: Option 2: Make CIL Exceptional Circumstances Relief available and adopt the Waverley Borough Council CIL Exceptional Circumstances Relief Policy. Provides a mechanism to enable growth and deliver development where exceptional circumstances arise. Report P51
Implications
Financial: Granting exceptional circumstances relief will reduce CIL income available to fund infrastructure, though the number of qualifying developments is expected to be very small. Report P53, P54
Legal: The policy and procedures comply with Regulations 55 to 57 of the CIL Regulations 2010 and Part 2 of the Subsidy Control Act 2022; Legal Services will support ongoing compliance. Report P57, P59, P60, P61
Equalities: The Equalities Comprehensive Impact Assessment found no disproportionately adverse impact on people with any protected characteristic. Report P68, P69
Climate: There are no climate change or sustainability implications arising from the report. Report 12.5, P71
Risk: Risk that multiple developments seek reduced CIL payments is mitigated by the requirement for 'truly exceptional circumstances' and case-by-case discretion. Report 10.1, 10.2
Who and where
Developers with planning permissions subject to Section 106 agreements where CIL payment would render the development unviable Report 6.8, 6.11, 6.13
The Council as CIL Charging Authority, which will administer claims and assess viability Report 6.4, 6.19
Infrastructure delivery funded by CIL, which may see reduced income where relief is granted Report 7.1, P53
Timeline
31 October 2018: Waverley Borough Council CIL Charging Schedule adopted
1 March 2019: CIL Charging Schedule implemented
October and November 2025: Cross-party CIL Review and Reform Temporary Executive Working Group met to discuss Exceptional Circumstances Relief
3 March 2026: Council meeting at which the decision was made
At least 14 days prior to 1st April 2026: Council will issue a statement that exceptional circumstances relief is available Report 5.1, P16
1st April 2026: Date on which the Council will begin accepting claims for CIL Exceptional Circumstances Relief Report 5.1, P17
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge local authorities can levy on new development to help fund supporting infrastructure.
CIL Exceptional Circumstances Relief: A mechanism under Regulations 55 to 57 of the CIL Regulations 2010 allowing a charging authority to reduce or waive CIL where payment would make a development unviable.
Section 106 agreement: A planning obligation under section 106 of the Town and Country Planning Act 1990 requiring a developer to deliver works or contributions as part of a planning permission.
Subsidy Control Act 2022: UK legislation requiring that public financial support, including CIL relief, is provided in a way that does not distort competition.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCNL4/25
Resolved
RESOLVED that: 1. The CIL relief for exceptional circumstances in its area in accordance with Regulation 55-57 of the Community Infrastructure Levy Regulations 2010 (as amended) be made available, 2. The Waverley Borough Council CIL Exceptional Circumstances Relief Policy, as provided in Appendix 1 ... view the full minutes text for item CNL4/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
2.1That the Executive recommends that Council resolves to:
2.1.1 Make the CIL relief for exceptional circumstances available in its area in accordance with Regulation 55-57 of the Community Infrastructure Levy Regulations 2010 (as amended).
2.1.2 Adopt the Waverley Borough Council CIL Exceptional Circumstances Relief Policy, as provided in Appendix 1 to this report.
2.1.3 Delegate authority to the Joint Assistant Director for Planning to determine claims for CIL Exceptional Circumstances Relief in accordance with the Waverley Borough Council CIL Exceptional Circumstances Relief Policy and in compliance with the requirements of the Community Infrastructure Levy Regulations 2010 (as amended) and Subsidy Control Act 2022 (as amended).
2.2That the Council resolves to:
2.2.1 Make the CIL relief for exceptional circumstances available in its area in accordance with Regulation 55-57 of the Community Infrastructure Levy Regulations 2010 (as amended)
2 Community Infrastructure Levy (CIL) Exceptional Circumstances Relief
2.2.2 Adopt the Waverley Borough Council CIL Exceptional Circumstances Relief Policy, as provided in Appendix 1 to this report.
2.2.3 Delegate authority to the Joint Assistant Director for Planning to determine claims for CIL Exceptional Circumstances Relief in accordance with the Waverley Borough Council CIL Exceptional Circumstances Relief Policy and in compliance with the requirements of the Community Infrastructure Levy Regulations 2010 (as amended) and Subsidy Control Act 2022 (as amended).
3 Reason(s) for recommendation:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.