AI summaryWaverley Council approves £4,862,292 extra budget for Cranleigh Leisure Centre new build, funded by £2.65m CIL and £2.21m borrowing, on a 33-6 vote.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSupplementary estimate for new leisure centre
Money£4,862,292CIL plus internal borrowing
What happens nextBuild contract signingFollowing Council approval
Who it affectsCranleigh residents and visitorsNew leisure centre replacing 1969 building
What was decided
Council approved a supplementary estimate of £4,862,292 to fund Option 1 of the Cranleigh Leisure Centre new build, comprising £2,651,900 of CIL funding and £2,210,392 of internal borrowing. Report P12
The vote was carried 33 in favour and 6 against, with a recorded vote requested by Cllr Townsend.
Authority was delegated to the Joint Strategic Director of Finance and Resources to enter into the build contract and related agreements, subject to Procurement Procedure Rules. Report P10
Why
The current 1969 leisure centre is 56 years old, beyond its expected 40-year life, with high risk of further plant and structural failure, and keeping the existing building open would cost around £7.3m over five years with no improvements. Report 3.1, 6.3, 6.4
Project costs have risen by £4,862,292 since the October 2023 approval of £31,137,252, driven by inflation over five extra quarters, market rate increases in structure, services and finishes, and design development, plus £358,000 to retain 100 car parking spaces during construction. Report 6.11, 3.6
Option 1 is recommended as the most strategically aligned, retaining Passivhaus certification and the agreed facility mix, and turning a current £26,000 a year deficit asset into an average £450,000 a year revenue generator. Report 3.3, 11.3
What happens next
Officers will progress executing the main works build contract with the preferred contractor, Willmott Dixon, subject to final costs being within budget. Report 4.2
Indicative programme: detailed design completes Spring 2026, construction starts Summer 2026, new centre built by Winter 2027, old centre demolished Spring 2028. Report 6.16, P71
Officers will continue to bid for additional CIL and external funding that could replace some borrowing, and undertake value engineering with the contractor to review costs without compromising design intent. Report 1.5, 6.13
The money
£4,862,292 Supplementary estimate approved, total increase in project budget Report P12, 6.11
£2,651,900 CIL funding allocation toward the build and infrastructure Report 1.3, P12
£2,210,392 Internal borrowing to cover remaining shortfall Report 1.4, P12
£35,999,544 Reviewed total project cost plan Report 1.1, P123
£31,137,252 Capital budget approved by full Council in October 2023 Report 6.14
£14.8m Total borrowing for the project, including earlier borrowing and additional sum for S106 shortfall Report P174
£1,188,292 General inflation element of the £4,862,292 cost increase
£480,000 Market rate increase in frame and additional fire protection
£554,000 Market rate increase in roof structure
£672,000 Design development and market rates for stone cladding and masonry
£478,000 Design development and market rates for wall and floor finishes
£248,000 Design development and market rates for furniture, fittings and equipment
£464,000 Market rate increase in space heating and air conditioning
£268,000 Market rate increase in electrical installations
£152,000 Market rate increase in heat source installations
£358,000 Addition of time and cost to retain 100 public car parking spaces on site throughout construction Report 3.6
£1,722,000 Previous projected S106 funding figure, reduced to £286,960 after internal review
£286,960 Revised S106 funding following internal audit of S106 agreements
£7.3m Predicted cost over next 5 years to keep existing building open, with no improvements Report 6.4
£26,000 p.a. Current annual deficit payment to operate the existing centre Report 6.2
£450,000 Average projected annual revenue generated under Option 1 Report 11.3
Options considered
Chosen: Option 1: Progress the existing proposal as per the planning application, achieving Passivhaus certification and the full agreed facility mix. Retains Council-approved scheme, turns a £26,000 a year deficit into an average £450,000 a year revenue, supports net zero and health and wellbeing priorities Report 11.3, P8
Rejected: Option 2: Remove the Passivhaus design certification standard. Loses guaranteed energy savings, higher energy costs, programme delay of 3-12 months, planning re-submission, payback period of about 59 years Report 11.4, P185
Rejected: Option 3: Redesign the centre to keep within current budget. Loss of about 750m² of floor space, removes leisure services, programme delay of at least 12 months, new planning application, payback of about 60 years Report 11.5
Rejected: Option 4: Do nothing, cease the new build project and manage closure of the current site. Loss of leisure provision for the community, penalty under the Leisure Operating Contract with Everyone Active, loss of annual return to the General Fund Report 11.6
Implications
Financial: Project payback period extends from 44 to 50 years for the Council's direct investment, or 52 years including CIL and S106 funds, due to higher costs and the S106 funding reduction.
Financial: Overall borrowing for the project rises to £14.8m after the S106 funding reduction from £1,722,000 to £286,960 is replaced by additional borrowing. Report P174
Financial: The scheme is expected to generate an average £450,000 a year net revenue benefit to the General Fund, turning a £26,000 a year deficit into a positive return. Report 11.3, 6.2
Legal: Procurement complied with the Procurement Act 2023 and the Council's Contract Procedure Rules via the Procure Partnerships Framework; value is below Schedule 1 thresholds.
Legal: Because the additional budget exceeds £250,000, full Council approval is required under clause 6.3 of the Finance Procedure Rules. Report P137
Equalities: The Impact Assessment finds no disproportionately adverse impact on people with protected characteristics from the recommendations, but notes that if Option 1 is not approved there would be such an impact. Report P143, P146
Climate: Passivhaus design is expected to use 60 to 70 percent less energy than a typical modern leisure centre, potentially reducing Cranleigh Leisure Centre's share of council emissions from 8.5 percent (263 tCO2e) significantly, with solar panels providing up to 25 percent of energy demand. Report P74, P149
Risk: Risk of the £2m CIL offer lapsing if works do not start within 18 months; permission has been obtained to extend the construction start date. Report P112
Risk: Construction-period car parking loss is mitigated by the contractor's commitment to maintain at least 100 spaces throughout the build, at an additional cost of £358,000 and a 9-week programme extension. Report 3.6, P113
Staffing: A dedicated specialist project manager is in place, supported by a Project Working Group covering Leisure, Finance, Legal, Sustainability, Procurement, Property, Car Parks and Corporate Projects, with an Employers Agent and Clerk of Works to be appointed for the build stages. Report P147
Who and where
Cranleigh residents and visitors using the leisure centre Report 11.6
Everyone Active, the leisure operator under the Leisure Operating Contract Report P43
Local businesses and residents around the Village Way car park site Report 3.6, 9.5
Cranleigh Amateur Swimming Club and Surrey Coalition of Disabled People Report 9.10
Future successor authority for the Waverley area, which will receive the asset Report 8.2
Timeline
September 2021: Feasibility Update Report commissioned from The Sport, Leisure and Culture Consultancy Report P41
December 2021: Full Council allocated capital budget for a low carbon new-build leisure centre to Passivhaus standard on Village Way car park Report P42
1st July 2023: New Leisure Operating Contract commenced with Everyone Active, securing additional annual income of £596,000 Report P43
October 2023: Full Council approved revised capital budget of £31,137,252, Passivhaus certification and delegations Report P46
23 April 2024: Council confirmed £2 million CIL funding from the 2023/24 round Report P125
1 April 2025: Additional £651,900 CIL funding approved from 2024/25 round for car park extension and EV chargers Report P125
August 2025: Planning permission granted by the Local Planning Authority (application WA/2024/02091) Report P53
16 December 2025: Cranleigh Leisure Centre update report taken to Overview and Scrutiny Committee Report 13.1
25 February 2026: Council meeting considered the supplementary estimate approval Report 4.1, 2.2
3 March 2026: Council approved the £4,862,292 supplementary estimate on a 33-6 recorded vote
Spring 2026: Indicative completion of detailed design Report 6.16, P71
Summer 2026: Indicative construction start on site Report 6.16, P71
Winter 2027: Indicative new centre construction completion Report 6.16, P71
Spring 2028: Indicative old centre demolition Report 6.16, P71
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge developers pay to local authorities to fund infrastructure
Passivhaus: A rigorous energy performance standard for buildings focused on very high insulation, airtightness and controlled ventilation
Section 106 (S106): A legal agreement under section 106 of the Town and Country Planning Act 1990 used to secure developer contributions toward infrastructure
Supplementary estimate: Additional budget approval sought outside the main budget cycle to cover new or increased spending
Treasury Management: Management of the Council's cash flow, borrowing and investments
Everyone Active: The operator of Waverley's four leisure centres under the Leisure Operating Contract that started on 1 July 2023
RIBA stages: Work stages defined by the Royal Institute of British Architects that structure the design and construction process
D&B (Design and Build): A procurement route where a single contractor is responsible for both design and construction
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCNL6/25
Resolved
RESOLVED that the allocation of budget by way of a supplementary estimate totalling £4,862,292 to fund progression of Option 1 of the new build project in accordance with the revised business case set out in Exempt Appendix 2 of the agenda report, to be funded from; · 2,651,900 CIL funding allocation · £2,210,392 internal borrowing, be approved. Cllr Townsend requested a recorded vote which was duly supported by 5 Members. The vote was CARRIED by 33 votes in favour, 6 against as follows: For: Cllr David Beaman, Cllr Dave Busby, Cllr Janet Crowe, Cllr Jerome Davidson, Cllr Adam Duce, Cllr Alan Earwaker, Cllr Tony Fairclough, Cllr Paul Follows, Cllr Maxine Gale, Cllr George Hesse, Cllr Jerry Hyman, Cllr Victoria Kiehl, Cllr ... view the full minutes text for item CNL6/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1This report provides an updated project position with reviewed cost plan of £35,999,544 for the Cranleigh Leisure Centre new build project.
1.2It duly considers the options, as detailed at point 11, and makes recommendations to proceed with the existing approved proposal for the construction of the new centre. The recommended option delivers the Council approved scheme of a Passivhaus certified centre offering the agreed facility mix. It also turns a deficit asset into a positive revenue generator.
1.3The team has been awarded £2,651,900 of CIL funding to be used toward the leisure centre build and wider infrastructure works including increased car parking and electric vehicle charging. Whilst the allocation of strategic CIL has been approved, the addition of this funding to the project budget has not. This report seeks approval for the budget, using the allocated funding.
1.4To cover the remainder of the £2,210,392 budget required, the proposal is to fund this from borrowing.
1.5Officers will continue to actively explore further additional CIL funding and other external funding sources. If successful, this would replace this additional borrowing. However, the timelines unfortunately do not align, and we need to progress to adhere to the project programme and minimise the amount that costs could rise further.
1.6Since the original approval in October 2023, there has been a change to the Section 106 funding, as set out in the Financial Implications section, point 12.1.5. There is no change to the overall budget requested and therefore no requirement to seek additional budget approval. However, the change in funding source impacts the payback period of the scheme, and this has been reflected in Exempt Appendix 2.
Recommendations
2.1That the Executive resolves to:
2.1.1. Subject to full Council approving the supplementary estimate (as revised under recommendation 2.2.1 below), proceed with Option 1 of the Cranleigh Leisure Centre new build project, which is to progress the existing proposal as per the planning application, achieving both Passivhaus certification and full agreed facility mix.
2 Cranleigh Leisure Centre new build
2.1.2. Delegate to the Joint Strategic Director of Finance and Resources the authority to enter into the build contract, together with all other contracts and legal agreements connected with the Cranleigh Leisure Centre new build project as may be necessary, in compliance with Procurement Procedure Rules, the Council’s Constitution and within the approved budget (as revised under recommendation 2.2.1 below).
2.2That the Executive recommends that Council, at the meeting on 25 February 2026, resolves to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.