Council, Tuesday 21 April 2026 at 7.00pm

Strategic CIL Bidding Cycle 2025-2026

Approved Committee 3 papers

AI summaryFull Council approves £2,080,000 Strategic CIL allocation to Waverley Borough Council for the New Cranleigh Leisure Centre further bid, completing the £13,977,864 2025/2026 funding cycle.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStrategic CIL funding for project above £2.5m threshold
Money£2,080,000.00Cranleigh Leisure Centre further bid allocation
What happens nextFunding agreementFinal checks, then negotiation and completion
Who it affectsWaverley Borough infrastructureSchools, health, roads, leisure, community facilities

What was decided

Council approved £2,080,000.00 of Strategic CIL funding to Waverley Borough Council for the New Cranleigh Leisure Centre Further Bid, the single project above the £2.5m Executive threshold. Report 2.1, 6.23

The award forms part of a total £13,977,864.00 Strategic CIL recommended for the 2025/2026 bidding cycle, alongside 22 other projects totalling £11,897,864.00 already approved by the Executive on 10th March 2026. Report 6.22, 6.24, P58

Several awards carry caveats, such as submission of a valid planning application within 12 months, or withdrawal of previously allocated Strategic CIL for the Elstead Road Safety Scheme. Report P51, P53, P55, P58

Why

To ensure robust and effective expenditure in line with the CIL Regulations 2010 (as amended) and the Council's approved Strategic CIL governance arrangements. Report 3.1, P10

The cross-party CIL Spend Executive Working Group assessed the bid against the agreed Strategic CIL Bid Scoring Criteria and recommended it for funding. Report 6.5, 6.18, 6.19, 6.20

The Executive considered the bid on 10th March 2026 and recommended the Council to approve the allocation. Report 1.2, 1.4, 6.23

What happens next

If approved, final relevant checks will be undertaken, followed by negotiation and completion of a funding agreement for the project. Report 4.1, 6.26

All successful applicants must accept terms and conditions and sign a funding agreement; payments are made after project completion against verifiable invoices. Report 6.26, P66

The cross-party CIL Spend EWG will meet again to review and reflect on the 2025/2026 cycle, including any governance or process changes. Report 4.2

The money

  • £2,080,000.00 New Cranleigh Leisure Centre Further Bid (project 23, above £2.5m threshold) Report 6.23, P61
  • £13,977,864.00 Total Strategic CIL recommended for allocation across the 2025/2026 cycle Report 6.24
  • £11,897,864.00 Total of 22 projects below £2.5m threshold approved by Executive on 10th March 2026 Report P58
  • just over £14.5 million Strategic CIL available as of 1st January 2026 after Neighbourhood CIL cap adjustment Report 6.11, 6.21
  • just over £15.5million Strategic CIL available as of 1st January 2026 before Neighbourhood CIL cap Report 6.10
  • just under £19.3 million Total CIL requested across all 35 bid submissions Report 6.15
  • just over £128 million Total value of all 35 projects submitted Report 6.15
  • just under £18.3 million Total CIL requested across the 31 valid bid submissions Report 6.18

Options considered

  • Rejected: Option 1: Council to form its own view on the bid above the £2.5m threshold and decide to approve or decline. Not recommended; officers, the EWG and the Executive have already given thorough consideration Report 11.1, P90, P91
  • Chosen: Option 2: Approve the recommendations of the cross-party CIL Spend EWG and Executive as set out in the report. Recommended; based on detailed EWG assessment and Executive endorsement on 10th March 2026 Report 11.2, P93, P94

Implications

  • Financial: CIL amounts proposed for allocation have been received and are on the balance sheet; no impact on Waverley's budget from these proposals. Report P97
  • Legal: Each allocation will be assessed under the UK Subsidy Control regime (Subsidy Control Act 2022) before funding is provided; funding agreements will be prepared by Legal Services. Report P98, P105, P106
  • Equalities: Equalities Comprehensive Impact Assessment concluded the proposals will not have a disproportionately adverse impact on any protected characteristic group. Report P114
  • Climate: The Strategic CIL Scoring Criteria include a component assessing how bids support the Council's Climate Emergency aims; many recommended bids have positive environmental impacts. Report P118
  • Risk: Council will complete final relevant checks on all funded projects and ensure funding agreements address all relevant matters to keep expenditure within the CIL Regulations 2010. Report 10.1, P87

Who and where

  • Waverley Borough Council (applicant for the Cranleigh Leisure Centre further bid and other projects) Report 6.23, P61
  • Surrey County Council (applicant for multiple road safety, cycling and school projects) Report P51, P53, P55, P58
  • Royal Surrey County Hospital (applicant for cancer, chemotherapy and aseptic unit projects) Report P57, P58
  • Town and parish councils and community organisations in the borough (applicants and beneficiaries) Report P51, P53, P55, P57, P58
  • Residents and businesses across Waverley borough benefiting from infrastructure improvements Report P113

Timeline

  • 1st January 2026: Strategic CIL available stood at just over £15.5million before the Neighbourhood CIL cap adjustment Report 6.10
  • 20th, 21st January and 3rd February 2026: Cross-party CIL Spend Executive Working Group met to consider valid bids Report 6.20
  • 25th February 2026: Council resolved that Strategic CIL be ringfenced to 'Uplifted Capped Parish CIL' funds, reducing available Strategic CIL to just over £14.5 million Report 6.11
  • 10th March 2026: Executive approved 22 projects below the £2.5m threshold and recommended the Cranleigh Leisure Centre further bid to Council Report 1.2, 1.4, 6.22
  • 21st April 2026: Full Council considered and approved the Cranleigh Leisure Centre further bid

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on new development used to fund infrastructure
  • Strategic CIL: The portion of CIL receipts used for strategic infrastructure to support development of the area
  • EWG: CIL Spend Executive Working Group, a cross-party group that recommends Strategic CIL allocations
  • IFS: Infrastructure Funding Statement, published annually in December
  • LCWIP: Local Cycling and Walking Infrastructure Plan
  • ANPR: Automatic Number Plate Recognition
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCNL18/25

Resolved

that the allocation of Strategic CIL funding for the project (and amount) as set out in the table at paragraph 6.23 of the agenda report, be approved.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Council

Executive summary

1.1As per the approved CIL governance arrangements (Council on 19th March 2019), the Executive is delegated to approve bids for the allocation of Strategic CIL Funding, on the recommendation of the cross-party CIL Spend Executive Working Group (EWG), subject to an upper limit of £2.5m per individual award, above which approval reverts to Full Council.

1.2On 10th March 2026, the Executive considered the allocation of Strategic CIL funding to the projects recommended (for the projects below the £2.5m award threshold) for funding by the CIL EWG in relation to the Strategic CIL Bidding Cycle 2025/26.

1.3For the project above the £2.5m award threshold, this report invites Council to consider the recommendation from Executive to Council, and consider the allocation of Strategic CIL funding, as recommended by the cross-party CIL Spend EWG in relation to the Strategic CIL Bidding Cycle 2025/26.

1.4It should be noted, that at the 10th March 2026 meeting the Executive recommended that the Council resolves to approve the allocation of Strategic CIL funding for the project (and amount) as set out in the table at paragraph 6.22 of this report.

1.5Members may reach alternative conclusions to those recommended by the cross-party CIL Spend EWG but their reasons for doing so will need to be clearly articulated and evidenced where possible.

Recommendations

2.1That the Council resolves to:

2.1.1 Approve the allocation of Strategic CIL funding for the project (and amount) as set out in the table at paragraph 6.23 of this report.

3. Reason(s) for recommendation:

3.1In order to ensure robust and effective expenditure in line with the CIL Regulations 2010 (as amended), and in accordance with the 2 Strategic Community Infrastructure Levy (CIL) Bidding Cycle 2025/2026

Council’s approved Strategic CIL governance arrangements, which include detailed eligibility and assessment criteria.

4. Next steps

4.1If the relevant recommendation is approved by Council, in accordance with the approved Executive delegation, where Strategic CIL funding has been approved final relevant checks will be undertaken, and then the negotiation and completion of a funding agreement for the approved project.

4.2The cross-party CIL Spend EWG will meet again to review and reflect on the 2025/2026 Strategic CIL Bidding Cycle, including considering any review of process for Strategic CIL governance and expenditure.

5. Exemption from publication

5.1This report is not exempt from publication.

6. Background and Proposal

6.1In accordance with the CIL Regulations 2010 (as amended) Strategic CIL must be spent on “the provision, improvement, replacement, operation or maintenance of infrastructure to support the development of its area”.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic CIL Bid Scoring Criteria /25Appendix 1 492 KB Download
PDF
Equalities Impact Assessment /25Appendix 2 211 KB Download
PDF
Strategic CIL Bidding Cycle 2025-2026Report 855 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

39 of 50 attended
PR
Councillor Penny RiversMayor, present
DM
Councillor David MunroDeputy Mayor, present
LA
Councillor Lauren AtkinsCommittee Member, absent
JA
Councillor Jane AustinCommittee Member, apologies
ZB
Councillor Zoe Barker-LomaxCommittee Member, present
DB
Councillor David BeamanCommittee Member, present
DB
Councillor Dave BusbyCommittee Member, present
LC
Councillor Laura CavaliereCommittee Member, present
PC
Councillor Peter ClarkCommittee Member, apologies
CC
Councillor Carole Cockburn BEMCommittee Member, present
JC
Councillor Janet CroweCommittee Member, present
JD
Councillor Jerome DavidsonCommittee Member, present

All 50 on the meeting page

On this subject at Waverley

Search all
  1. Strategic CIL Bidding Cycle 2025-2026This decision
  2. Strategic CIL Bidding Cycle 2025/26Noted
  3. Community Infrastructure Levy (CIL) Strategic Bidding Cycle 2024/25Approved

More from Waverley Council

All decisions
MeetingDecisionOutcome
29 Jul 2026 Annual Standards Report 2025-26RESOLVED that the Annual Report 2025-26 of the Joint Standards Committee be deferred to a future meeting. Deferred Open
29 Jul 2026 Member Questions at MeetingsThat 1. The amended Council Procedure Rule 12 as set out in Appendix 2 to this report, be adopted 2. The Monitoring O... Approved Open
30 Jun 2026 Amended Redundancy Policy - Pension Strain CostsThat 1. the amendment to the redundancy policy to remove the deduction of pension strain costs from redundancy paymen... Approved Open
30 Jun 2026 Councillor Connor Relleen - Approval of Reason for Non-attendance at meetingsThat 1. the reason for Councillor Connor Relleen’s failure to attend any meeting of the Council or any of its committ... Agreed Open
30 Jun 2026 Waverley Householder CIL - Lack of ProgressRESOLVED that the motion as set out in agenda report be supported. The Chamber adjourned for a 10 minute comfort brea... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies