CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Waverley Borough Council
Executive, Tuesday 10 March 2026 at 7.00pm

Strategic CIL Bidding Cycle 2025/26

Noted Executive 3 papers

AI summaryWaverley Executive approves £11,897,864 of Strategic CIL for 22 infrastructure projects and will ask Council to add £2,080,000 for Cranleigh Leisure Centre. Four bids ruled invalid, seven declined.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlus £2.08m Cranleigh bid recommended to Council
Money£13,977,864.00 total recommended£11,897,864.00 under threshold; £2,080,000.00 above
What happens nextFunding agreements and final checksDelegated to Joint Assistant Director Planning
Who it affectsWaverley Borough residents, schools, NHSInfrastructure projects across the borough

What was decided

The Executive approved Strategic CIL allocations for 22 projects totalling £11,897,864.00, all below the £2.5 million upper limit for Executive approval. Report P8, 6.22, P65

Four submitted bids were noted as invalid because they would not support development and aimed to remedy pre-existing deficiencies not made more severe by new development. Report P7, 6.17, P47, P49

The Executive will recommend to Full Council an additional £2,080,000.00 for the Cranleigh Leisure Centre project, which exceeds the £2.5 million threshold. Report P14, 6.23, P68

Why

To ensure robust and effective expenditure in line with the CIL Regulations 2010 (as amended) and the Council's approved Strategic CIL governance arrangements. Report 3.1, P15

The cross-party CIL Spend Executive Working Group assessed 31 valid bids against agreed scoring criteria over three meetings in January and February 2026. Report 6.18, 6.19, 6.20

Each project must meet mandatory criteria, including supporting development rather than remedying pre-existing infrastructure deficiencies. Report 6.3, 6.16, P111

What happens next

The Cranleigh Leisure Centre additional bid will be presented to Full Council for approval because it exceeds the £2.5 million Executive threshold. Report 4.1, 1.1, 6.7

The Joint Assistant Director for Planning Development, with the Portfolio Holder for Finance, Assets and Property, will complete final checks and negotiate funding agreements. Report P9, 4.2

The CIL Spend Executive Working Group will meet again to review and reflect on the 2025/26 cycle and consider any governance process changes. Report 4.3, 6.6

The money

  • Total: £11,897,864.00 Strategic CIL recommended for 22 Executive-approved projects Report P65, 6.22
  • Additional Total: £2,080,000.00 Cranleigh Leisure Centre top-up, to go to Council Report P68, 6.23
  • £13,977,864.00 Total Strategic CIL recommended across the 2025/26 cycle Report 6.24
  • £1,979,582.00 New Witley and Milford Health Medical Centre Report P58
  • £1,078,000.00 Multipurpose studio at Loseley Fields Primary School, Godalming Report P62
  • £1,000,000.00 Waverley LCWIP (Programme Allocation 2) at Farnham LCWIP Report P60
  • £950,000.00 Combe Common Pavillion/Youth Hub, Chiddingfold Report P60
  • just over £14.5 million Strategic CIL available after proposed Neighbourhood CIL cap ringfencing Report 6.11, 6.21

Options considered

  • Rejected: Members come to their own view on each submitted bid and decide whether to approve or decline Strategic CIL funding. Officers said this approach would not be recommended; reasons for departing from the EWG would need to be clearly articulated and evidenced Report 11.1, P102, P103
  • Chosen: Approve the recommendations of the cross-party CIL Spend Executive Working Group as set out in the report. Officers and the EWG gave thorough consideration to each bid; approach recommended Report 11.2, P105, P106

Implications

  • Financial: CIL amounts proposed have been received and are on the balance sheet; no impact on Waverley's revenue budget. Report P108, 6.12
  • Legal: Each allocation must comply with CIL Regulations 2010 and the Subsidy Control Act 2022; Legal Services will advise, particularly on Cranleigh Cricket Club. Report P110, P116, P118
  • Equalities: An Equalities Comprehensive Impact Assessment found no disproportionately adverse impact; the Public Sector Equality Duty has been considered. Report P124, P126, P127
  • Climate: Strategic CIL scoring includes a component on the Council's Climate Emergency aims; many recommended bids have positive environmental impacts. Report P130
  • Risk: The Council will complete final relevant checks on all funded projects and address risks through funding agreements and conditional allocations. Report 10.1, P99, 6.26
  • Other: Strategic CIL cannot retrospectively fund infrastructure; allocations may be reduced at funding agreement stage to ensure regulatory compliance; payments are made after project completion against verifiable invoices. Report 6.25, 6.26, P72, P73

Who and where

  • Residents and businesses across Waverley Borough benefitting from new or improved local infrastructure Report P124, 7.1, 7.2
  • Successful applicants including Surrey County Council, Waverley Borough Council, Royal Surrey County Hospital, parish councils, schools, Surrey Police, the Wey & Arun Canal Trust and community groups Report P58, P60, P62, P68
  • Unsuccessful applicants whose bids were either ruled invalid or not recommended for funding Report P47, P49, P78, P80, P82, P84, P86

Timeline

  • 19th March 2019: Council approved CIL governance arrangements for Strategic CIL allocation Report 6.4, 1.1
  • 1st January 2026: Strategic CIL available was just over £15.5million Report 6.10
  • 20th, 21st January and 3rd February 2026: Cross-party CIL Spend Executive Working Group met to consider valid bids Report 6.20
  • 25th February 2026: Council meeting due to consider Neighbourhood CIL cap issue, which may reduce available Strategic CIL to just over £14.5 million Report 6.11
  • 10th March 2026: Executive considered and approved the 2025/26 Strategic CIL Bidding Cycle recommendations
  • December 2026: Annual Infrastructure Funding Statement to be published reporting on Strategic CIL use Report 6.27

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on new development used to fund infrastructure
  • Strategic CIL: The 70 to 80 per cent share of CIL retained by the charging authority for strategic infrastructure, rather than passed to town and parish councils
  • EWG: Cross-party CIL Spend Executive Working Group that assesses bids and recommends allocations
  • LCWIP: Local Cycling and Walking Infrastructure Plan
  • ANPR: Automatic Number Plate Recognition cameras used for traffic enforcement
  • ICB: Integrated Care Board, the NHS body responsible for commissioning local health services
  • RSCH: Royal Surrey County Hospital
  • IFS: Infrastructure Funding Statement, the annual public report on CIL receipts and spending
  • EVCP: Electric Vehicle Charging Point
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 51/25

Resolved

Resolved that Four of the submitted Strategic CIL bids were invalid for the reasons set out in the Table at paragraph 6.17 of the agenda report be noted. The allocation of Strategic CIL for each of the projects set out in the Table at paragraph 6.22 of the agenda report ... EXE 51/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1As per the approved CIL governance arrangements (Council on 19th March 2019), the Executive is delegated to approve bids for the allocation of Strategic CIL Funding, on the recommendation of the cross-party CIL Spend Executive Working Group (EWG), subject to an upper limit of £2.5m per individual award, above which approval reverts to Full Council.

1.2This report does not cover Neighbourhood CIL expenditure.

1.3This report invites the Executive to consider the allocation of Strategic CIL funding to the projects recommended (for the projects below the £2.5m award threshold) for funding by the CIL EWG in relation to the Strategic CIL Bidding Cycle 2025/26.

1.4For the projects above the £2.5m award threshold, the report invites a recommendation from Executive to Council for the allocation of Strategic CIL funding, as recommended by the cross-party CIL Spend EWG in relation to the Strategic CIL Bidding Cycle 2025/26.

1.5Members may reach alternative conclusions to those recommended by the cross-party CIL Spend EWG but their reasons for doing so will need to be clearly articulated and evidenced where possible.

Recommendations

2.1That the Executive resolves to:

2.1.1 Note that four of the submitted Strategic CIL bids were invalid for the reasons set out in the Table at paragraph 6.17 of this report.

2.1.2 Approve the allocation of Strategic CIL for each of the projects set out in the Table at paragraph 6.22 of this report (inclusive of the caveats and amounts set out in such table).

2.1.3 Delegate authority to the Joint Assistant Director – Planning Development, in consultation with the Portfolio Holder for Finance, Assets and Property, to undertake and complete any final relevant checks, and to negotiate and complete a funding agreement for each approved project.

2 Strategic Community Infrastructure Levy (CIL) Bidding Cycle 2025/2026

2.1.4 Decline Strategic CIL funding for the bids submitted for the projects set out in the Table at paragraph 6.29 of this report.

2.1.5 Approve amendments to two projects approved in the 2024/2025 Strategic CIL Bidding Cycle, as set out in the Table at paragraph 6.30 of this report.

2.2That the Executive recommends that Council resolves to:

2.2.1 Approve the allocation of Strategic CIL funding for the project (and amount) as set out in the table at paragraph 6.23 of this report.

3. Reason(s) for recommendation:

3.1In order to ensure robust and effective expenditure in line with the CIL Regulations 2010 (as amended), and in accordance with the Council’s approved Strategic CIL governance arrangements, which include detailed eligibility and assessment criteria.

4. Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic CIL Bid Scoring Criteria 51/25Appendix 1 492 KB Download
PDF
Equalities Impact Assessment 51/25Appendix 2 211 KB Download
PDF
Strategic CIL Bidding Cycle 2025/26Report 868 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, apologies
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Strategic CIL Bidding Cycle 2025/26This decision
  2. Strategic CIL Bidding Cycle 2025-2026Approved
  3. Community Infrastructure Levy (CIL) Strategic Bidding Cycle 2024/25Approved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies