AI summaryWaverley Executive approves £11,897,864 of Strategic CIL for 22 infrastructure projects and will ask Council to add £2,080,000 for Cranleigh Leisure Centre. Four bids ruled invalid, seven declined.
Written from the decision and the officer reportPDF Pro
OutcomeNotedPlus £2.08m Cranleigh bid recommended to Council
Money£13,977,864.00 total recommended£11,897,864.00 under threshold; £2,080,000.00 above
What happens nextFunding agreements and final checksDelegated to Joint Assistant Director Planning
Who it affectsWaverley Borough residents, schools, NHSInfrastructure projects across the borough
What was decided
The Executive approved Strategic CIL allocations for 22 projects totalling £11,897,864.00, all below the £2.5 million upper limit for Executive approval. Report P8, 6.22, P65
Four submitted bids were noted as invalid because they would not support development and aimed to remedy pre-existing deficiencies not made more severe by new development. Report P7, 6.17, P47, P49
The Executive will recommend to Full Council an additional £2,080,000.00 for the Cranleigh Leisure Centre project, which exceeds the £2.5 million threshold. Report P14, 6.23, P68
Why
To ensure robust and effective expenditure in line with the CIL Regulations 2010 (as amended) and the Council's approved Strategic CIL governance arrangements. Report 3.1, P15
The cross-party CIL Spend Executive Working Group assessed 31 valid bids against agreed scoring criteria over three meetings in January and February 2026. Report 6.18, 6.19, 6.20
Each project must meet mandatory criteria, including supporting development rather than remedying pre-existing infrastructure deficiencies. Report 6.3, 6.16, P111
What happens next
The Cranleigh Leisure Centre additional bid will be presented to Full Council for approval because it exceeds the £2.5 million Executive threshold. Report 4.1, 1.1, 6.7
The Joint Assistant Director for Planning Development, with the Portfolio Holder for Finance, Assets and Property, will complete final checks and negotiate funding agreements. Report P9, 4.2
The CIL Spend Executive Working Group will meet again to review and reflect on the 2025/26 cycle and consider any governance process changes. Report 4.3, 6.6
£950,000.00 Combe Common Pavillion/Youth Hub, Chiddingfold Report P60
just over £14.5 million Strategic CIL available after proposed Neighbourhood CIL cap ringfencing Report 6.11, 6.21
Options considered
Rejected: Members come to their own view on each submitted bid and decide whether to approve or decline Strategic CIL funding. Officers said this approach would not be recommended; reasons for departing from the EWG would need to be clearly articulated and evidenced Report 11.1, P102, P103
Chosen: Approve the recommendations of the cross-party CIL Spend Executive Working Group as set out in the report. Officers and the EWG gave thorough consideration to each bid; approach recommended Report 11.2, P105, P106
Implications
Financial: CIL amounts proposed have been received and are on the balance sheet; no impact on Waverley's revenue budget. Report P108, 6.12
Legal: Each allocation must comply with CIL Regulations 2010 and the Subsidy Control Act 2022; Legal Services will advise, particularly on Cranleigh Cricket Club. Report P110, P116, P118
Equalities: An Equalities Comprehensive Impact Assessment found no disproportionately adverse impact; the Public Sector Equality Duty has been considered. Report P124, P126, P127
Climate: Strategic CIL scoring includes a component on the Council's Climate Emergency aims; many recommended bids have positive environmental impacts. Report P130
Risk: The Council will complete final relevant checks on all funded projects and address risks through funding agreements and conditional allocations. Report 10.1, P99, 6.26
Other: Strategic CIL cannot retrospectively fund infrastructure; allocations may be reduced at funding agreement stage to ensure regulatory compliance; payments are made after project completion against verifiable invoices. Report 6.25, 6.26, P72, P73
Who and where
Residents and businesses across Waverley Borough benefitting from new or improved local infrastructure Report P124, 7.1, 7.2
Successful applicants including Surrey County Council, Waverley Borough Council, Royal Surrey County Hospital, parish councils, schools, Surrey Police, the Wey & Arun Canal Trust and community groups Report P58, P60, P62, P68
Unsuccessful applicants whose bids were either ruled invalid or not recommended for funding Report P47, P49, P78, P80, P82, P84, P86
Timeline
19th March 2019: Council approved CIL governance arrangements for Strategic CIL allocation Report 6.4, 1.1
1st January 2026: Strategic CIL available was just over £15.5million Report 6.10
20th, 21st January and 3rd February 2026: Cross-party CIL Spend Executive Working Group met to consider valid bids Report 6.20
25th February 2026: Council meeting due to consider Neighbourhood CIL cap issue, which may reduce available Strategic CIL to just over £14.5 million Report 6.11
10th March 2026: Executive considered and approved the 2025/26 Strategic CIL Bidding Cycle recommendations
December 2026: Annual Infrastructure Funding Statement to be published reporting on Strategic CIL use Report 6.27
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge on new development used to fund infrastructure
Strategic CIL: The 70 to 80 per cent share of CIL retained by the charging authority for strategic infrastructure, rather than passed to town and parish councils
EWG: Cross-party CIL Spend Executive Working Group that assesses bids and recommends allocations
LCWIP: Local Cycling and Walking Infrastructure Plan
ANPR: Automatic Number Plate Recognition cameras used for traffic enforcement
ICB: Integrated Care Board, the NHS body responsible for commissioning local health services
RSCH: Royal Surrey County Hospital
IFS: Infrastructure Funding Statement, the annual public report on CIL receipts and spending
EVCP: Electric Vehicle Charging Point
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 51/25
Resolved
Resolved that Four of the submitted Strategic CIL bids were invalid for the reasons set out in the Table at paragraph 6.17 of the agenda report be noted. The allocation of Strategic CIL for each of the projects set out in the Table at paragraph 6.22 of the agenda report ... EXE 51/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1As per the approved CIL governance arrangements (Council on 19th March 2019), the Executive is delegated to approve bids for the allocation of Strategic CIL Funding, on the recommendation of the cross-party CIL Spend Executive Working Group (EWG), subject to an upper limit of £2.5m per individual award, above which approval reverts to Full Council.
1.2This report does not cover Neighbourhood CIL expenditure.
1.3This report invites the Executive to consider the allocation of Strategic CIL funding to the projects recommended (for the projects below the £2.5m award threshold) for funding by the CIL EWG in relation to the Strategic CIL Bidding Cycle 2025/26.
1.4For the projects above the £2.5m award threshold, the report invites a recommendation from Executive to Council for the allocation of Strategic CIL funding, as recommended by the cross-party CIL Spend EWG in relation to the Strategic CIL Bidding Cycle 2025/26.
1.5Members may reach alternative conclusions to those recommended by the cross-party CIL Spend EWG but their reasons for doing so will need to be clearly articulated and evidenced where possible.
Recommendations
2.1That the Executive resolves to:
2.1.1 Note that four of the submitted Strategic CIL bids were invalid for the reasons set out in the Table at paragraph 6.17 of this report.
2.1.2 Approve the allocation of Strategic CIL for each of the projects set out in the Table at paragraph 6.22 of this report (inclusive of the caveats and amounts set out in such table).
2.1.3 Delegate authority to the Joint Assistant Director – Planning Development, in consultation with the Portfolio Holder for Finance, Assets and Property, to undertake and complete any final relevant checks, and to negotiate and complete a funding agreement for each approved project.
2 Strategic Community Infrastructure Levy (CIL) Bidding Cycle 2025/2026
2.1.4 Decline Strategic CIL funding for the bids submitted for the projects set out in the Table at paragraph 6.29 of this report.
2.1.5 Approve amendments to two projects approved in the 2024/2025 Strategic CIL Bidding Cycle, as set out in the Table at paragraph 6.30 of this report.
2.2That the Executive recommends that Council resolves to:
2.2.1 Approve the allocation of Strategic CIL funding for the project (and amount) as set out in the table at paragraph 6.23 of this report.
3. Reason(s) for recommendation:
3.1In order to ensure robust and effective expenditure in line with the CIL Regulations 2010 (as amended), and in accordance with the Council’s approved Strategic CIL governance arrangements, which include detailed eligibility and assessment criteria.
4. Next steps
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.