Resolved
RESOLVED that: The opening of the new Macroeconomic Volatility risk (SR13), with a score of Moderate (3) and Possible (3), resulting in a rating of AMBER be agreed.
AI summaryWaverley Executive approves a new Macroeconomic Volatility risk (SR13) on the Strategic Risk Register with an AMBER rating, and notes the updated Q4 2025/26 risk registers.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that: The opening of the new Macroeconomic Volatility risk (SR13), with a score of Moderate (3) and Possible (3), resulting in a rating of AMBER be agreed.
1.1This report provides an update on the Strategic risk register. The Strategic risk register has been reviewed and refreshed for Q4 2025/26 to include detailed mitigations and risk scorings and can be found in Appendix 1.
2.1Executive: Note and approve the opening of the new Macroeconomic Volatility risk (SR13), scored Moderate (3) and Possible (3) which is a rating of AMBER.
2.2That the Audit and Risk Committee and the Executive note the updated Strategic and Operational risk registers and make any observations on its contents.
3 Reason(s) for recommendation:
3.1Executive: To enable the Executive to ensure that risks threatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy.
3.2Audit and Risk Committee: To support the Committee’s constitutional role in respect of risk management.
3.3The Risk Management Framework states the Audit and Risk Committee and the Executive will monitor and review the strategic risk register quarterly, ensuring that the Council operates and maintains a robust and effective risk management process.
4 Next steps
4.1There are no further steps for this report.
5 Exemption from publication
2 Q4 2025/26 Strategic risk register
5.1No part of this report is exempt from publication.
6 Background and Proposal
Role of the Audit & Risk Committee
6.1The purpose of the Committee is to provide independent assurance to councillors of the adequacy of the risk management framework and the internal control environment. It provides independent review of the authority’s governance, risk management and control frameworks.
Strategic and operational risks
6.2The Council’s risk management strategy defines corporate risks as risks ‘that reside outside the usual course of management and require a wider corporate response or awareness …’.
6.3Corporate risks are split into two categories: strategic and operational risks.
6.4Strategic risks (shown at Appendix 1) are risks that could impact the Council’s medium to long term priorities and objectives as set out in the Corporate Strategy or other corporate level policies and strategies, including the Medium-Term Financial Plan (MTFP).
6.5Operational risks are risks that are encountered in the delivery of services and which affect service objectives, as defined in service plans. Operational risks are usually managed as part of the usual course of management by services. However, where an operational risk cannot be managed within the service or if it is outside of the Council’s risk appetite, then it should be considered for inclusion on the operational risk register.
6.6Red rated operational risks (shown at Appendix 2) are reported to the Audit and Risk Committee and the Executive.
Changes to the risk registers since the last report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Waverley Q4 2025-26 Strategic Risk Register: Finalised 31/25Appendix 1 | 1.1 MB | Download |
PDF |
Waverley Q4 2025-26 Operational Risk Register: Finalised 31/25Appendix 2 | 489 KB | Download |
PDF |
Middle East Conflict Impacts: Briefing 31/25Appendix 3 | 500 KB | Download |
PDF |
Q4 2025/26 Strategic risk registerReport | 790 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.