WA/2026/00246 - Sports Field, Sandy Hill Road, Farnham GU9 0DU
DecidedPlanning2 papers
AI summaryWaverley Planning Committee grants permission for a pump track facility at Sandy Hill Road sports field, Farnham, with amended and extra conditions on ecology, drainage and cycle parking.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedPermission granted under Regulation 3
MoneyNot stated
What happens nextPre-commencement conditions to be dischargedConditions 3, 4 and new CEMP condition
Who it affectsFarnham sports field users and residentsPlus Thames Basin Heaths SPA ecology
What was decided
Permission granted under Regulation 3 of the 1992 General Regulations, subject to conditions, amendment to Condition 2, additional conditions, amendment to Informative 2 and additional informatives.
Two extra conditions were added: a Construction Environmental Management Plan (CEMP) before works start, and cycle parking within the fenced pump track area before the facility opens. Report P30, P33
Three extra informatives were added covering ordinary watercourse consent, Source Protection Zone infiltration and sub-ground structures and groundwater. Report P37, P38, P39
Why
Natural England raised no objection once mitigation is secured, addressing the Thames Basin Heaths Special Protection Area and the Bourley and Long Valley Site of Special Scientific Interest. Report P11, P13, P14
The 30-Year Habitat Management and Monitoring Plan was considered comprehensive and robust, with implementation secured through conditions and any later amendments agreed with Surrey Wildlife Trust or Natural England. Report P19
The County Highway Authority has asked for further changes to the Construction Management Plan, and the Lead Local Flood Authority still objects but its recommended wording matches existing Condition 3. Report P7, P8
What happens next
Pre-commencement Conditions 3 and 4 stand as recommended, and an additional CEMP condition must be discharged before any development starts. Report P8, P30, P32
Cycle parking details must be submitted and approved before the pump track is first brought into use, and retained thereafter. Report P33, P35
Options considered
Chosen: Grant permission under Regulation 3 subject to conditions, amended Condition 2, additional conditions, amended Informative 2 and additional informatives
Implications
Environment and climate: Mitigation measures required to protect Thames Basin Heaths SPA and Bourley and Long Valley SSSI, including an SPA-threshold pump track design, a Pump Track Management Plan and a CEMP. Report P13, P14, P15
Environment and climate: A 30-Year Habitat Management and Monitoring Plan governs ongoing ecological management, with potential later amendments agreed with Surrey Wildlife Trust or Natural England. Report P19
Legal: Pre-commencement conditions must be formally discharged by the Local Planning Authority before development begins. Report P8, P30
Risk: The County Highway Authority still requires further amendments to the Construction Management Plan before it can be approved. Report P7
Risk: The Lead Local Flood Authority maintains its objection, addressed through Condition 3 and new Informatives 8 to 10. Report P7, P36, P37, P38, P39
Who and where
Thames Basin Heaths Special Protection Area Report P13, P14
Bourley and Long Valley Site of Special Scientific Interest Report P13
Users of Sandy Hill Road sports field, Farnham Report P3, P6
Future cycle parkers at the pump track Report P24, P33
Timeline
8 July 2026: Waverley Area Planning Committee resolves to grant permission, subject to amended and additional conditions and informatives. Report P1, P3
Plain English for the jargon
Regulation 3 application: A planning application made by a local planning authority for development on its own land, determined under the Town and Country Planning General Regulations 1992.
Special Protection Area (SPA): A European-designated site protected for rare and migratory birds.
Site of Special Scientific Interest (SSSI): A national conservation designation for sites with notable flora, fauna or geology.
Appropriate Assessment: A Habitats Regulations check on whether a plan or project would harm a protected European site, alone or in combination with others.
CEMP: Construction Environmental Management Plan, a document setting out how construction works will avoid or reduce environmental harm.
HMMP: Habitat Management and Monitoring Plan, a long-term plan for managing and tracking habitat conditions on a site.
Lead Local Flood Authority (LLFA): The county-level authority responsible for managing local flood risk, here Surrey County Council.
County Highway Authority (CHA): The county council, here Surrey County Council, responsible for highways and transport matters.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24.2
Resolved
RESOLVED that subject to conditions, amendments to condition 2 and additional conditions, amendment to informative 2 and additional informatives , permission be GRANTED under Regulation 3 of The Town and Country Planning General Regulations 1992 (as amended)
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
The applicant has submitted a Construction Management Plan and a Drainage Calculation Report since the publication of the Committee agenda. These additional documents have been submitted in response to the pre-commencement requirements of Conditions 3 and 4 in the Committee Report.
The County Highway Authority (CHA) and Lead Local Flood Authority (LLFA) have commented on the respective submissions. The CHA has requested further amendments before the Construction Management Plan can be approved, while the LLFA has maintained its objection and recommended a condition to be included in any planning permission. This is the same condition as Condition 3 in the agenda. Additional informatives recommended by the LLFA are included below as Informatives 8 - 10.
Pre-commencement conditions 3 and 4 therefore remain as recommended in the Committee report.
Additional consultation responses:
An additional consultation response has been received from Natural England (NE) following reconsultation on the LPA’s Appropriate Assessment. Their response is as follows:
NO OBJECTION - SUBJECT TO APPROPRIATE MITIGATION BEING SECURED
Natural England have further advised that, without appropriate mitigation, the application would
1 have an adverse effect on the integrity of Thames Basin Heaths Special Protection Area (SPA); damage or destroy the interest features for which the Bourley and Long Valley Site of Special Scientific Interest has been notified.
In order to mitigate these adverse effects and make the development acceptable, the following mitigation measures are required: • Suitably designed and managed pump track-SPA threshold • Pump Track Management Plan (PTMP) • Submission of Construction Environmental Management Plan (CEMP).
The first and second bullet points are provided for in Conditions 2 and 9, and clarified in Informative 5 in the Committee report. The third point requires an additional condition, as recommended below.
Amendments to the report:
Section 14 - Effect on Thames Basin Heaths SPA, biodiversity and compliance with Habitat Regulations 2017:
The penultimate paragraph in Section 14 of the Committee report is amended by the addition of the bold italicised text as follows:
A 30-Year Habitat Management and Monitoring Plan (HMMP) was submitted and subsequently updated by the applicant during the course of the application. The Council’s ecology adviser Surrey Wildlife Trust (SWT) have identified some points regarding ecology and advised that they be addressed prior to determination of the application. However, the HMMP is considered to be comprehensive, and it is considered that its implementation including any subsequent amendments agreed with SWT and / or Natural England would be sufficiently robust to ensure that no significant impacts on the ecological values of the site would result. This is provided for in a condition as recommended below.
In addition, this paragraph was highlighted in yellow in error in the published Report. It should be noted that this was unintended, and should not be taken to mean that the highlighted text has greater significance than any other part of the report.
Amended Condition 2
Drawing no. OT-SHPT-007 rev. A is corrected to delete the revision number.
Additional Conditions
2 An additional condition is recommended as requested by Natural England. An additional condition is also recommended to provide cycle parking within the pump track area as delineated by the boundary fence shown in the landscape plan, to be provided prior to the facility being brought into use.
Revised and additional conditions
- Amended Condition 2:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
WA/2025/00805 - Ruffold Farm CranleighRESOLVED that, delegated authority is granted to the Assistant Director of Planning to GRANT outline planning permiss...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.