Executive, Tuesday 1 September 2026 at 7.00pm

Procurement Pipeline Report – over £200k (2026-27)

Approved Executive 2 papers

AI summaryWaverley Borough Council's Executive approved the start of procurement for projects worth over £200k listed in Appendix 1, and delegated contract award authority to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApproval to begin tendering projects in Appendix 1
MoneyOver £200k thresholdPipeline covers procurements over £200k only
What happens nextTendering and award processProcurement team to go to market, then award
Who it affectsSuppliers and service areasFuture contract opportunities over £200k

What was decided

The Executive approved the start of procurement for projects listed in Appendix 1 to the report. Report 2.1

Delegated authority was given to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance, to award the contracts in Appendix 1 once a successful contractor is selected. Report 2.1

Why

The Council's Contract Procedure Rules require Executive permission before any procurement begins that may result in a Key Decision award over £200k. Report 1.1, 6.2

A planned pipeline allows strategic forward planning, ethical procurement, consideration of climate impact, social value, modern slavery risk, and best value. Report P7, P8, P9, P10, P11, P12

A single pipeline report avoids the need for multiple separate approval papers and is more agile. Report 11.1

What happens next

The Procurement team and the relevant service areas will go to market for the procurements listed in Appendix 1. Report 4.1

On conclusion of each procurement exercise, the team will run the award process and obtain relevant approvals, including any required consent from the Shadow West Surrey Council. Report 4.1

Where a contract falls within the Section 24 Direction, consent of the Shadow Authority must be obtained before the Council enters the contract.

The money

  • over £200k Estimated contract value threshold requiring Executive approval to commence procurement Report 1.1, 6.2
  • greater than £100m (inc VAT) Threshold of annual third party supplier spend that would trigger Procurement Act 2023 individual pipeline notices
  • above £100,000 Property transaction value requiring Shadow West Surrey Council consent under Section 24 Direction Report P27
  • over £1,000,000 Capital contract value requiring Shadow West Surrey Council consent under Section 24 Direction Report P28
  • above £100,000 Non-capital contract value where Shadow West Surrey Council consent is required if the contract period extends beyond a specified date Report P29

Options considered

  • Chosen: Bring a consolidated procurement pipeline to Executive at intervals. Saves officer and Executive time, reduces procurement timescales, more strategic planned approach Report 11.1
  • Rejected: Bring each individual procurement item to the Executive separately. Would take more time and cost writing individual reports Report P37

Implications

  • Legal: The Surrey (Structural Changes) Order 2026 came into effect on 10 March 2026, with Vesting Day on 1 April 2027. A Section 24 Direction (expected by 30 June 2026) requires Shadow West Surrey Council consent for property transactions over £100,000, capital contracts over £1,000,000, and certain non-capital contracts above £100,000. Report P27, P28, P29
  • Financial: No direct financial implications from this report. Financial approval will be sought prior to any procurements commencing. Report P38
  • Legal: No direct legal implications. Procurement and Legal teams will provide project-specific advice throughout the process. Report P39, P40
  • Equalities: Public Sector Equality Duty considered; no equality and diversity implications for this report. Report P45
  • Climate: No climate change or sustainability implications from this report; ethics including environmental and climate impact will be considered in individual procurements. Report P50, P11
  • Staffing: No direct HR implications. New CPRs may increase resource demand on the Procurement team and service areas. Report 10.1, 12.4
  • Risk: Without planned pipelines, risk of non-compliant spend rises as contracts may expire before re-procurement, and early market engagement opportunities are reduced. Report 10.2

Who and where

  • Suppliers, including small and medium enterprises and the voluntary, community and social enterprise sector Report 7.2
  • Waverley Borough Council service areas as subject experts for the requirements being procured Report 10.1
  • The Procurement team supporting both Guildford Borough Council and Waverley Borough Council Report 6.3
  • Shadow West Surrey Council, which must consent to certain contracts under the Section 24 Direction

Timeline

  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect
  • 2 June 2026: Previous procurement pipeline presented to Executive Report 1.2
  • 30 June 2026 (expected): Section 24 Direction expected to be issued
  • 1 April 2027: Vesting Day for transfer of functions to West Surrey Council
  • After Executive approval: Procurement team and service areas proceed to market, then run award process Report 4.1

Plain English for the jargon

  • CPRs: Contract Procedure Rules, the Council's internal rules for procurement
  • Key Decision: An Executive decision that is significant in budget or impact, including awards over £200k or those affecting two or more wards
  • Section 24 Direction: A direction under section 24 of the Local Government and Public Involvement in Health Act 2007 requiring Shadow West Surrey Council consent for certain contracts during reorganisation
  • Shadow West Surrey Council: The shadow authority preparing for the transfer of functions on Vesting Day
  • Vesting Day: The date on which the Council's functions transfer to the new West Surrey Council, set for 1 April 2027
  • VCSE: Voluntary, community and social enterprise sector
  • SME: Small and medium enterprises
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 49/26

Resolved

that 1) Commencement of the procurement process for the projects listed in Appendix 1 to this report be approved. 2) Delegated authority be given to the Joint Strategic Director for Finance and Resources, after consultation with the Lead Councillor for Finance and upon selection of a successful contractor, to ... EXE 49/26
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a Key Decision if the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 2 June 2026. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to: (1) Approve commencement of the procurement process for the projects listed in Appendix 1 to this report. (2) Delegate authority to the Joint Strategic Director for Finance and Resources, after consultation with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contracts listed in Appendix 1, subject to first obtaining any necessary consent from the Shadow West Surrey Council.

Reasons for recommendation

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may Procurement Pipeline Report – over £200k (2026-27)

result in a Key Decision prior to procurement procedures formally commencing. 3.2 Planning procurement activity ensures:

 effective stakeholder management

 effective procurement and sourcing

 compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

 there is consideration on how contract price is to be managed in contract and what contract price model will be used

 our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

 how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3.3 This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 3.4 When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_WBC Procurement Pipeline 04082026v2 49/26Appendix 1 519 KB Download
PDF
Procurement Pipeline Report: over £200k (2026-27)Report 305 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, apologies
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Procurement Pipeline Report – over £200k (2026-27)This decision
  2. Procurement Pipeline Report – over £200k (2025-2026)Approved
  3. Procurement Pipeline (March 2026 update)Approved
  4. Procurement PipelineApproved
  5. Procurement Pipeline (January update)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies