(1) That, subject to the amendments recommended by the Cabinet Housing and Planning Panel at its meeting on 20 July 2016 in relation to the Panshanger site, to the Hatfield Fire Station site and the Welwyn Garden City Fire Station site and the timetable for public consultation, the Proposed Submission Local Plan, Policies Map, Sustainability Appraisal and Infrastructure Delivery Plan be published for public consultation under Regulation 19 of the Town and Country Planning (Local Planning) (England) Regulations 2012 as amended. (2) That the Local Development Scheme be updated and presented to a future Cabinet Housing and Planning Panel meeting and Cabinet meeting for agreement in line with the programme set out in the report of the Director (Governance) to the Panel meeting on 20 July 2016. (3) That authority be delegated to the Head of Planning, in consultation with the Executive Member for Planning, Housing and Community to make minor non-material spelling, formatting, mapping and other amendments to the consultation documents where they do not alter the intent of the plan. (4) That the content of the Stage 1 Green Corridor document, as set out at Appendix A to the report of the Director (Governance) ... view the full minutes text for item 39a
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1The purpose of this report is to present the Proposed Submission Local Plan to Members for their consideration.
1.2Appendix A comprises the draft Local Plan, Appendix B the Policies Maps, Appendix C the Sustainability Appraisal Report and Appendix D the Infrastructure Delivery Plan.
Recommendation
2.1That the Panel agrees that the Proposed Submission Local Plan, Policies Map, Sustainability Appraisal and Infrastructure Delivery Plan should be presented to Cabinet for agreement to publish for public consultation under Regulation 19 of the Town and Country Planning ((Local Planning) (England) Regulations 2012 as amended.
2.2That the Local Development Scheme be updated and presented to a future Cabinet Housing and Planning Panel and Cabinet for agreement in line with the programme set out in this report.
2.3That the Head of Planning be given delegated authority in consultation with the Executive Member for Planning to make minor non-material spelling, formatting, mapping and other amendments to the consultation documents where they do not alter the intent of the plan.
Background
3.1The purpose of the Local Plan is to set out the planning policy framework for the borough, by identifying how much and what type of development is needed and where it should or should not be accommodated. It also identifies areas which should be conserved and protected because of their special value. It has to be informed by evidence and to have gone through a process of consultation.
3.2Once the plan is submitted, it will be subject to a public examination by an independent inspector to consider whether it has met the legal tests for its preparation and whether it meets the tests of soundness.
3.3The legal tests relating to its preparation are a) accordance with the Local Development Scheme, b) whether consultation has been in accordance with the Council’s Statement of Community Involvement and national consultation regulations,
c) whether it has been subject to sustainability appraisal, and
d) whether the Duty to Cooperate has been met.
3.4The Local Development Scheme sets out the programme for the production of the Welwyn Hatfield Local Plan. The Scheme was revised in 2014 when it was first indicated that instead of preparing separate Core Strategy Site Allocations and Development Management documents the Council intended to produce a single Local Plan. The programme for its preparation was subsequently amended in 2015. This indicates that regulation 19 consultation should take place in the third quarter of 2016 and that the plan should be submitted at the end of 2016. It is now anticipated that submission will take place in early 2017 following the analysis of representations in late 2016 and the Local Development Scheme therefore needs to be updated accordingly.
3.5The Statement of Community Involvement sets out the approach to consultation, the methods of consultation that will be used during its preparations and the types of bodies that the Council will engage with.
3.6Several rounds of consultation have already taken place relating to the preparation of the Core Strategy and the Local Plan.
a) Pre-Issues and Options - informal consultation took place throughout 2007 and 2008 with the purpose of identifying the key issues the Core Strategy needs to tackle and what the options for addressing those issues are. In addition we also consulted on the implications of other key strategies and the scope of the Sustainability Appraisal. The details of the events and the results of the consultation are all summarised in the Pre-Issues and Options Consultation Statement. http://www.welhat.gov.uk/article/4142/Pre-Issues-and-Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
39aWelwyn Hatfield Draft Local Plan Submission 2016 and Green Corridor Strategic Framework - Stage 1 Report (Forward Plan Reference FP752)This decision
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.