That the framework contracts for minor building works be extended for a period of one year to 31 March 2018. (Note: Councillor M.Perkins declared a non-pecuniary interest in this item because she had requested a quote for private work from one of the companies in the framework and did not participate in the discussion).
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1On 4 March 2014, Cabinet agreed to award framework contracts for Minor Building works to the following companies:
D Smith Builders (Welwyn) Limited
Purdy Contracts Limited
RCP Contractors Limited
1.2The contracts started on 31/3/2014 and the initial term was for three years until 31/3/2017 with an optional one year extension. This report considers the benefit of extending the contract
2 Recommendation(s)
2.1That the framework contracts are extended for a period of one year to 31/03/2018
3 Explanation
3.1The Minor Building Works contract is for responsive repairs and minor new works to the council corporate property portfolio.
3.2The main benefit of the contract is that the officers can instruct contractors to carry out works, at pre agreed rates without the delay of a procurement process. This enables work to be undertaken without unnecessary delay and is especially beneficial for emergency works.
3.3The contract is based on continual monitoring of contractors to ensure that quality of work is maintained and value for money is achieved.
3.4The Contractors on the framework have performed exceedingly well and enabled a number of high profile projects to be achieved on time. To enable this service to continue it is recommended that the frameworks continue in their current format and a new procurement commences in mid 2017 for a replacement contract to commence on 01/04/2018. Implications
4 Legal Implication(s)
4.1The original procurement was let in accordance with the European Procurement Directives and there was provision in the contract notice for a one year extension.
5 Financial Implication(s)
The spend on the framework is approximately £400,000 per annum and is met from various budgets. The rates on the framework will remain the same for the proposed extension period,
6 Risk Management Implications
6.1There are very little risks of using a framework of this nature, as there are other contractors on the framework, if one of the contractors fails to perform.
7 Security & Terrorism Implication(s)
7.1None relating to this report.
8 Procurement Implication(s)
8.1This proposal is in accordance with the Contract Procedure Rules and European Procurement Directives
9 Climate Change Implication(s)
9.1None relating to this report.
10 Link to Corporate Priorities
10.1The subject of this report is linked to the Council’s Corporate Priority 4 - Help build a strong local economy, by maintaining and enhancing council assets.
11 Equality and Diversity
11.1An Equality Impact Assessment (EIA) has not been carried out in connection with the proposals that are set out in this report as there are no changes to service delivery.
Name of author Mike Storey Title Corporate Property Manager Date 1st August 2016
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.