Resolved
That the overall position on capital spending, funding and reserves, together with the latest current budget to date of £47.321M, the forecast outturn and the Prudential Indicators be noted.
Cabinet noted this item on Tuesday 6 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the overall position on capital spending, funding and reserves, together with the latest current budget to date of £47.321M, the forecast outturn and the Prudential Indicators be noted.
1.1To provide information on capital budgets, spending, receipts, and forecasts.
1.2The current approved expenditure budget at period 03 is £47.321M with spend to date of £5.060M and commitments of £6.411M. The current forecast outturn is £47.321M. (See table 8.1 for breakdown of expenditure, receipts and reserves).
2 Recommendation(s)
2.1note the overall position on capital spending, funding and reserves.
2.2note the latest current budget to date £47.321M.
2.3note the forecast outturn (details in paragraph 8.4)
2.4note the Prudential Indicators.
3 Explanation
The summarised capital expenditure position is shown in Table 1 and a detailed breakdown by capital scheme per directorate can be found in Appendix A. The current budget has increased from the original budget owing to the roll forward of previous years budgets into 2016/17.
A forecast capital receipts and reserves position can be found in Table 2.
-1- Table 1: Capital Expenditure Budgets by Head of Service as at period 03 Variance % spent & to Approved Original Current committed Forecast Forecast Roll Actual to Description Budget Budget of Outturn Outturn Forwards Date 2016/17 2016/17 Forecast 2016/17 to from 15/16 Outturn Current Budget £ £ £ £ £ £
Head of Resources 1,714,500 3,940,060 5,654,560 2,201,175 39% 5,654,560 0
Head of Environment 1,453,000 59,530 1,512,530 81,770 5% 1,512,530 0 Director (Finance and Operations) 3,167,500 3,999,590 7,167,090 2,282,945 32% 7,167,090 0
Head of Planning 0 322,130 322,130 19,941 6% 322,130 0 Head of Policy and Culture 1,214,715 378,620 1,636,335 110,501 7% 1,636,335 0 Head of Housing and Community 25,589,300 12,541,320 38,195,620 9,057,686 24% 38,195,620 0 Director (Strategy and Development) 26,804,015 13,242,070 40,154,085 9,188,128 23% 40,154,085 0
TOTAL 29,971,515 17,241,660 47,321,175 11,471,073 24% 47,321,175 0
3.1Actual in year expenditure to date:
Listed below are the largest capital schemes in year
3.1.1 Hatfield Town Centre - Current Budget £3.118M. The areas of spend for this year is on phase two of the redevelopment. This includes spend on final costs for the arcade canopy works, associated fees, flat refurbishments at White Lion House, acquisition of 17c HTC, redevelopment of 1 and 3-9, and the creation of new residential units 20a and 22a. Total in year expenditure and commitment to date is £1.135M. There is an Internal borrowing requirement of £2.220M in 2016/17 to fund acquisitions and redevelopment of units. There is approximately 1 more year to run on the Hatfield Town Centre schemes.
3.1.2 Bereavement Services - Current Budget £1.000M This is for the design and development to a point of planning of the reallocation of the existing buildings at the Lawn Cemetery which will include a crematorium. The amount will be spent periodically throughout the year for different project stages. Two contractors have been procured for this project, and this project is currently on track to submit a planning application in Summer 2016. There is no spend to date.
-2- 3.1.3 Development of Splashlands Site - Current Budget £0.981M This scheme is for the redevelopment of the former Splashlands site in Stanborough Park. Consultants are preparing a Business Case and Cost Plan for consideration by the Splashlands Project Board over the summer months ahead of a decision on Phase 2 of this project. There is only a small amount spent to date on fees.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL BUDGET MONITORING AT 30 JUNE 2016 (PERIOD 3):Report | 225 KB | DownloadRead as text |
PDF |
Item 8 Capital Monitoring_2016_17_P03Report | 167 KB | Download |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.