RESOLVED (9 for and 2 abstentions) 1. That the Panel agrees the proposed response to the Hertfordshire Mineral Local Plan Consultation (2019) as set out in Appendix A to the report and; 2. The Panel agrees that the final response be confirmed by the Head of Planning in consultation with the ... view the full minutes text for item 132.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1Hertfordshire County Council (HCC) has published its Proposed Submission version of the Hertfordshire Minerals Local Plan (MLP) for consultation which closes on 22 March 2019. Once adopted this Plan will replace the policies contained within its existing Minerals Local Plan (adopted in 2007) that covered the period between 2002- 2016. https://www.hertfordshire.gov.uk/about-the- council/consultations/environment/proposed-submission-minerals-local-plan- consultation.aspx
1.2The County Council have previously undertaken a number of consultations on what should be contained within the Mineral Local Plan and the site selection methodology. The last consultation was considered by Members of this Panel on 8th February 2018 and this Council raised the following concerns:
The potential for cumulative impacts arising from the scale of mineral extraction concentrated in three allocations to the west of Hatfield, concern particularly relates to HGV movements;
The lack of assessment in the site selection process and the sustainability appraisal of the cumulative impacts from the combination of sites;
Concern that the scale of mineral extraction identified in the document could prejudice the delivery of housing in north west Hatfield within the Welwyn Hatfield Local Plan period;
the extent of the areas identified as minerals consultation areas on the draft Policies Map which includes residential areas in the urban areas and the lack of clarity on what is a minerals safeguarding area;
Concern that the County Council would not be able to resource advising on whether or not a minerals resources assessment would be required for the number of applications it would relate to.
1.3This latest consultation is the formal regulation 19 consultation stage and the Council’s response will need to focus on any soundness or cross boundary strategic issues relating to the Duty to Cooperate.
1.4The main body of the report highlights the key issues whilst the proposed Council’s response has been included in Appendix A to this report.
-1- 2. Recommendation(s)
2.1That the Panel agrees the proposed response to the Hertfordshire Mineral Local Plan Consultation (2019) as set out in Appendix A to this report.
2.2That the Panel agrees that the final response be confirmed by the Head of Planning in consultation with the Executive Member for Planning.
Background
3.1Hertfordshire County Council, as the mineral planning authority, has a statutory duty to prepare a Minerals Local Plan, in line with NPPF. This identifies the locations where future minerals will be extracted (via allocations) and seeks to safeguard potential mineral sites from sterilisation by other uses (if necessary). It also includes a set of development management policies that will be used to determine planning applications for proposals for mineral extraction or other associated uses. When the MLP is adopted, it will form part of the Development Plan for the county.
3.2It is important to have regard to the Memorandum of Understanding (MOU) between WHBC and HCC, which was signed in August 2017 by the Councils’ then respective executive members for Planning. This document identifies the strategic issues affecting WHBC and HCC relating to minerals and waste; and the delivery of housing and jobs. It agrees the approach to future plan reviews and includes a commitment that both authorities will continue to work together consistent with the requirements of the NPPF and the Planning and Compulsory Purchase Act 2004, as amended by the Localism Act 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet Planning and Parking Panel at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
2026 - 28 Parking Works ProgrammeUnanimous That Cabinet Planning and Parking Committee: a) Recommends to Cabinet that the proposed PSWP, as outlined i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.