FORMER SHREDDED WHEAT FACTORY WELWYN GARDEN CITY AL8 6UN - 6/2019/1330/FULL - ALTERATIONS AND AMENDMENTS TO PLANNING PERMISSION 6/2018/0171/MAJ, FOR THE ERECTION OF A FIVE-STOREY COMMUNITY BRIDGE BUILDING (1,257M2) FOR FLEXIBLE USE (B1/D1/D
RefusedCommittee1 paper
Development Management Committee refused this item on Thursday 5 December 2019. Below is the council's own wording, with the papers it was decided on.
(12 voting in favour, 1 abstaining) That the recommendation be overturned and REFUSED. Reasons for refusal; 1. The proposed development, by virtue of the loss of the skate park, would result in there being a lack of provision for older children and teenagers to ‘hang out’ within the wider strategic site, contrary to Policy EMP3 of the Welwyn Hatfield District Plan, the Broadwater Road West Supplementary Planning Document and the National Planning Policy Framework. 2. The proposed development provides no parking, which would result in dispersing onto nearby highway creating an adverse highway impact, contrary to Policies D1 and M14, the Supplementary Planning Document on Parking and the National Planning Policy Framework.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1Members will recall that this planning application was presented at last month’s Development Management Committee (14 November). The application was deferred and it was agreed to be brought back to this month’s committee.
1.2There are no alterations to the report, except at paragraph 10.15, which alters the incorrect reference of condition 47 to condition 52 and paragraph 10.36 which substitutes the western elevation for the eastern elevation. Condition 4 is also altered to reflect the western elevation of the building. Additionally the table at paragraph 3.3 is altered to incorporate the minimum of 338sqm D2 use class and a maximum flexible use of 937sq m.
2 Site Description
2.1The site lies within the Wheat Quarter redevelopment site, in Welwyn Garden City. The strategic site occupies a central position, to the east of the main railway line bounded by Broadwater Road, Bridge Road and Hyde Way and land adjoining the railway.
2.2The site is adjacent to the raised pedestrian footbridge which provides access to Welwyn Garden City train station, beyond to Howard Centre shopping mall and then serving as a gateway to the town centre.
2.3The site is currently accessed from Bridge Road, or via a pedestrian access off of Hydeway.
2.4The area of land, which the proposed development would be located, has planning permission (6/2018/0171/MAJ) for the erection of a two storey building
for the use of a train operating company (TOC) and the development of a skate park.
2.5The TOC building would deliver 360m2 of B1 use floor space, designed to align with the quantum of space required by Network Rail. The skate park would deliver 338m2 of informal play provision, which falls under a class D2 use.
3 The Proposal
3.1The applicant seeks planning permission for the erection of a 5-storey Community Bridge Building (1,257m²) for flexible use (B1/D1/D2) Use Classes incorporating a minimum of 338 square metres of D2 Use Class Floor space and the removal of the skate park.
3.2The floor area of the building comprises of a ground floor that is 168m² (Gross Internal Area [GIA]). At first, second and third floor levels the units are 224m² (GIA) and are accessible via stairs/lift from the ground floor. The fourth floor allows for 79m² (GIA) and there is also access to a roof terrace, with access via the main stair/lift core.
3.3The table below provides a comparison between the approved building, with the skate park, and the proposed community bridge building:
Component Approved Scheme Proposed Scheme with (GEA) a minimum 338sq m of D2 use (GEA) B1(a) Use Class Floor 360m² (TOC building) 937 sqm (max) space D1 Use Class Floor N/A 937 sqm (max) space D2 Use Class Floor 338m² (Skate Park) 1257 sqm (max) space
3.4This application has been submitted, as Network Rail have informed the applicant that they no longer require the building. The approved building is a bespoke product, one that was designed with a specific user and operator in mind, it is no longer considered to be an appropriate market product.
3.5The applicant therefore proposes that the Local Planning Authority reconsider the use and potential of this building and ensure that it maximises the potential for regeneration and provides the necessary commercial and community floor space to serve the town.
4 Reason for Committee Consideration
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
FORMER SHREDDED WHEAT FACTORY WELWYN GARDEN CITY AL8 6UN: 6/2019/1330/FULL: ALTERATIONS AND AMENDMENTS TO PLANNING PERMISSION 6/2018/0171/MAJ, FOR THE ERECTION OF A FIVE-STOREY COMMUNITY BRIDGE BUILDING (1,257M2) FOR FLEXIBLE USE (B1/D1/D2 USE CLASSES) INCORPORATING A MINIMUM OF 338 SQUARE METRESReport
76FORMER SHREDDED WHEAT FACTORY WELWYN GARDEN CITY AL8 6UN - 6/2019/1330/FULL - ALTERATIONS AND AMENDMENTS TO PLANNING PERMISSION 6/2018/0171/MAJ, FOR THE ERECTION OF A FIVE-STOREY COMMUNITY BRIDGE BUILDING (1,257M2) FOR FLEXIBLE USE (B1/D1/DThis decision
FORMER SHREDDED WHEAT FACTORY WELWYN GARDEN CITY AL8 6UN - 6/2019/1330/FULL - ALTERATIONS AND AMENDMENTS TO PLANNING PERMISSION 6/2018/0171/MAJ, FOR THE ERECTION OF A FIVE-STOREY COMMUNITY BRIDGE BUILDING (1,257M2) FOR FLEXIBLE USE (B1/D1/DThis decision
Follow Development Management Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.