Resolved
RESOLVED (Unanimous) That the 2021/2022 Internal Audit Progress Report recommendations be noted.
Audit Committee noted this item on Monday 27 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (Unanimous) That the 2021/2022 Internal Audit Progress Report recommendations be noted.
A Progress against the 2021/22 Audit Plan
B 2021/22 Audit Plan Start Dates Agreed with Management
C Implementation Status of High Priority Recommendations as at 6 September 2021
D Implementation Status of Outstanding Medium Priority Recommendations as at 6 September 2021
E Assurance and Finding Definitions 2021/22
Page 2 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2021/22 as at 10 September 2021. b) Proposed amendments to the 2021/22 Annual Audit Plan report. c) The implementation status of previously agreed audit recommendations. d) An update on performance management information as at 10 September 2021.
1.2The 2021/22 Annual Audit Plan was approved by the Audit Committee at its meeting on 17 March 2021.
1.3The Audit Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the second report on the delivery of the 2021/22 Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed Annual Audit Plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 10 September 2021, 30% of the 2021/22 Audit Plan days had been delivered.
2.2The following final reports have been issued since 11 June 2021 (cut-off date for the SIAS Update Report for 28 June 2021 Audit Committee):
Audit Title Date of Issue Assurance Number of Level Recommendations Housing Land Supply June 2021 Reasonable 2 Medium, 1 Low 20/21
Housing Maintenance Not June 2021 1 Medium Contract – Part 1 Assessed
Page 3 2.3 To help the Committee assess progress in delivering the 2021/22 Audit Plan, Appendix B details agreed start dates. These dates were agreed with management and resources allocated accordingly. This schedule was designed to facilitate smoother delivery of the audit plan through the year.
Proposed Amendments to Audit Plan
2.4As agreed with management, the Voids Management audit (10 days) has been cancelled as a result of limited officer availability within this service area to support this audit. As a previous audit of this area was completed in April 2019, SIAS have agreed to cancel this project and agree whether a future audit is required as part of the 2022/23 annual audit planning cycle.
2.5As a result of the above change, the contingency budget is now 16.5 days. SIAS will continue to work with management to identify suitable projects for these days to be assigned to. Any further changes will be communicated to the Audit Committee at future meetings.
High Priority Recommendations
2.6Members will be aware that a Final Audit Report is issued when it has been agreed by management. This includes an agreement to implement the recommendations that have been made. It is Internal Audit’s responsibility to bring to Members’ attention the non-implementation of high priority recommendations. It is the responsibility of officers to implement the recommendations by the agreed date.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
WHBC SHARED INTERNAL AUDIT SERVICE (SIAS) PROGRESS REPORTReport | 571 KB | DownloadRead as text |
Follow Audit Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. | Noted | Open |
| 2 Sep 2026 | Rebuilding assurance updateTo note the Rebuilding Assurance Update. | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. | Noted | Open |
| 2 Sep 2026 | Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.