AI summaryWelwyn Hatfield Audit Committee notes internal audit progress to 17 August 2026, approves a wording change to the Audit Charter, and is briefed on the upcoming External Quality Assessment by the Chartered IIA.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNotes audit progress, EQA briefing, recommendation status; approves charter change
Money£not statedSIAS Board set EQA procurement budget; no figure given in the report
What happens nextEQA work starts December 2026Outcomes to be reported to SIAS Board and Audit Committees in March 2027
Who it affectsInternal audit governanceAudit Committee role, data governance, CCTV evidence handling
What was decided
The Committee noted the Internal Audit Progress Report covering the period to 17 August 2026, including delivery and recommendation implementation. Report 1.1, 2.1, 2.2
The Committee noted the Global Internal Audit Standards External Quality Assessment Briefing Paper, setting out the procurement of the Chartered IIA as independent assessor. Report P135, 2.14, P149
The Committee approved an amendment to the Internal Audit Charter, replacing a paragraph on the Audit Committee's role to describe it as providing oversight and challenge rather than holding managers to account. Report 2.15, 2.16, 2.17, 2.18
Why
Delivery of the 2026/27 audit plan is behind the original schedule, with 29% of days delivered by 17 August 2026, due to officer availability over summer and rescheduling of several audits into Quarter 3. Report 2.1, 2.10, 2.11
No new high priority recommendations arose from the two final reports issued (Budgetary Control and Cash and Banking, both Substantial assurance), but a previous Data Governance recommendation remains open with a target of 31 December 2026. Report 2.2, 2.4, P19
The Global Internal Audit Standards require a five-yearly external quality assessment, and the SIAS Board approved procurement of an independent assessor. Report 2.12, P123, P135
What happens next
Internal audit delivery is to be concentrated in Quarter 3, with continued close working with management to manage dependencies, and no current risk to delivering the agreed plan. Report 2.11, 2.10
The CCTV Strategy and Governance recommendation on body worn cameras remains in progress, with the Council exploring secure storage and logging options. Report P77, P78, P79
The Chartered IIA will conduct a validated self-assessment, starting in December 2026, with the final report to be presented by the Client Audit Manager to the Audit Committee. Report P135, P137, P143, P149
The money
100 / 275 days Profile to 17 August 2026 against planned billable days Report P31
82.5 / 275 days Actual billable days completed by 17 August 2026 Report P31
285 Total plan days in the 2026/27 audit plan Report P58
Options considered
Chosen: Validated self-assessment with independent validation as the EQA approach. Provides a valuable outcome for internal audit and serves a different purpose from a full EQA; procurement resulted in appointing the Chartered IIA. Report P129, P135, P130, P131
Rejected: Defer the EQA until after local government reorganisation in two years. Capacity is available in Q3/4 2026 and a recent EQA outcome supports SIAS tendering for new business. Report P127, P128
Rejected: Alternative EQA assessors (CIPFA, peer review through Audit Together, two SME consultancies and one large accountancy firm, or LACAN). After due diligence and competitive quotation, the Chartered IIA were awarded the contract. Report P111, P112, P113, P114, P115, P118, P119, P121, P135
Implications
Governance: The charter amendment clarifies that the Audit Committee provides oversight and challenge on risk management, internal control and governance, rather than holding operational managers to account for their effectiveness. Report 2.15, 2.16, 2.17, 2.18
Risk: A previously reported high priority Data Governance recommendation on a centralised Record of Processing Activities and retention schedule remains open, with a target implementation date of 31 December 2026. Report 2.4
Other: Several audits have been rescheduled into Quarter 3, increasing the concentration of work later in the year, although officers report no risk to delivering the agreed plan. Report 2.11, 2.10, P40, P41, P42
Staffing: 16 of 18 SIAS staff are either qualified or studying for a relevant professional qualification, meeting the 90% target. Report P31
Who and where
Welwyn Hatfield Borough Council, as a SIAS partner authority Report 1.2, 2.1, P54
The Audit Committee, in its role overseeing internal audit Report 2.15, 2.16, 2.17, 2.18
SIAS officers and BDO as co-source partner delivering audits Report P54, P55, P56, P59
Council management, responsible for implementing audit recommendations Report 2.3, 2.4, 2.5, P77
Timeline
17 March 2026: 2026/27 Internal Audit Plan approved by the Audit Committee Report 1.2
17 August 2026: Progress reported in this report (29% of plan days delivered) Report 2.1, P31
31 August 2026: Revised target for outstanding medium priority CCTV / Body Worn Cameras recommendation on officer guidance Report P77
December 2026: Commencement of the EQA by the Chartered IIA Report P149, P127
31 December 2026: Target implementation date for the open Data Governance high priority recommendation Report 2.4
March 2027: EQA outcomes to be reported to the SIAS Board and Audit Committees if possible Report P149, P143
Plain English for the jargon
SIAS: Shared Internal Audit Service, the partnership arrangement that delivers internal audit for Welwyn Hatfield Borough Council and other partner authorities.
EQA: External Quality Assessment, an independent evaluation of an internal audit function's conformance with professional standards, required at least every five years.
GIAS: Global Internal Audit Standards, the professional standards for internal audit practice.
CRA: Key Financial Systems cycle of audits covering areas such as Cash and Banking, Council Tax, Business Rates, Treasury Management and Housing Benefits.
RoPA: Record of Processing Activities, a centralised record required under data protection requirements.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item141
Resolved
To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status of internal audit recommendations and the management update; c) Note the Global Internal Audit Standards External Quality Assessment Briefing Paper; and d) Approve the amendment to the Audit Charter.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Members are recommended to: • Note the Internal Audit Progress Report for the period to 17 August 2026 • Note the implementation status of internal audit recommendations and the management update. • Note the Global Internal Audit Standards External Quality Assessment Briefing Paper • Approve the amendment to the Audit Charter
Page 1 Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 High Priority Recommendations 2.5 Medium Priority Recommendations 2.6 Proposed Amendments 2.7 Performance Management 2.10 Summary of Current Performance Against KPI’s 2.12 Global Internal Audit Standards – Commissioning of SIAS External Quality Assessment 2.15 Amendment to the Internal Audit Charter
Appendices
A Progress against the 2026/27 Audit Plan
B 2026/27 Audit Plan Start Dates Agreed with Management
C Implementation Status of Outstanding Medium Priority Recommendations
D Assurance and Findings Definitions 2026/27
E Briefing Paper – Global Internal Audit Standards – Domain III
Page 2 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Internal Audit Plan for 2026/27 as at 17 August 2026. b) In-Year Audit Plan review and proposed plan amendments. c) The implementation status of previously agreed audit recommendations. d) An update on performance indicators as at 17 August 2026. e) Commissioning of SIAS External Quality Assessment. f) Amendment to Internal Audit Charter.
Background
1.2The 2026/27 Internal Audit Plan was approved by the Audit Committee on 17 March 2026.
1.3The Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the second report giving an update on the delivery of the 2026/27 Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 17 August 2026, 29% of the 2026/27 Audit Plan days had been delivered.
2.2There have been two final audit reports issued since the previous progress report:
Audit Title Assurance Opinion Recommendations Budgetary Control Substantial None CRA Cash and Banking Substantial 1 Advisory CRA
Page 3 High Priority Recommendations
2.3Members will be aware that a Final Audit Report is issued when it has been agreed by management; this includes an agreement to implement the recommendations that have been made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of high priority recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.
2.4No new high priority recommendations have been raised as a result of the work completed and reported in the table at paragraph 2.2. However, one previously reported high-priority recommendation remains open in relation to Data Governance, concerning the establishment and maintenance of a centralised Record of Processing Activities (RoPA) and retention schedule. This recommendation has an agreed target implementation date of 31 December 2026.
Medium Priority Recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.