Resolved
( unanimous ) (1)The committee noted the current Risk Management Update. (2)The committee noted comments and actions in respect of the strategic and top operational risks.
Audit Committee noted this item on Monday 30 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
( unanimous ) (1)The committee noted the current Risk Management Update. (2)The committee noted comments and actions in respect of the strategic and top operational risks.
Strategic Risk Register - 2022/23 Quarter 3 Appendix A
Risk Title Risk Description Consequences Controls Risk Manager Latest Note Previous Current Score (Q2) Score Strategic - Availability Lack of suitable sites for Increased homelessness, Senior Leadership Team Executive Director The council has a Housing Delivery Strategy in place for affordable housing. There is a 18 18 of sites / land / assets affordable homes for Financial - financial penalties, Staff resource (Place) mechanism for assessing available sites. The Housing Development and Services Manager Housing Development development, either for direct Reputational damage, has made links to a number of developers and land owners to identify opportunities. provision by the council or Additional costs, Poor disposal and grant funding to partnership working We have reviewed a number of sites within the council's Housing Revenue Account, which Registered Providers at the scale could be brought forward. The council's Housing, Homelessness and Rough Sleeping that is required. Sites need to be Strategy identifies housing supply as a key target area. deliverable and suitable to attract interest Strategic - Change A new culture and direction have Inadequate service shaping, Use of consultants Chief Executive The new management structure has now been embedded, and the new transformation 32 32 Management been set by the transformation Additional costs, Communication strategy has been approved. An action plan to deliver the strategy has been developed, strategy This risk addresses the Reputational damage Chief Executive Briefings and a the approach to project and change management is under review. A new consequences of any failure to LGA Membership Transformation Board has been put in place to monitor and oversee key transformation robustly manage change. Peer Challenge and change projects. The risk management framework is under review and will form a key HR - Meetings with Trades Unions aspect of ensuring that risk are identified for programmes of changes and monitored HR - Employee Forum closely. Appraisal and one to one process Close Working Relationship with HR Strategic - Community Failure to properly consult Intervention by regulatory Corporate Strategy - Tenant Executive Director The corporate Community and Stakeholder Engagement Group, with representation from 32 32 Consultation and customers in line with legislative bodies, Legal - challenge, Involvement Strategy (Housing) (Finance and council services, meets monthly. It is responsible for coordinating and communicating all Engagement and regulatory requirements (as Reputational damage, Policy and Procedure Framework Transformation) consultation and engagement activity. It is also responsible for the delivery of the appropriate to relevant service Additional costs, Inadequate Borough Panel corporate community engagement strategy. A review of membership of this group is areas). Failure to involve service shaping Tenants’ Panel underway. The Customer Services Member Project Board has had Consultations added to communities when planning Alliance Strategy the remit of the group and will be considering the approach to the non statutory services. Community Partnership Team consultations over the coming months. engagement events New Corporate Community and Stakeholder Engagement Strategy Strategic Risk Register - 2022/23 Quarter 3 Appendix A
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
7: Q3 RisksReport | 171 KB | DownloadRead as text |
PDF |
RISK MANAGEMENT REPORTReport | 347 KB | Download |
Follow Audit Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. | Noted | Open |
| 2 Sep 2026 | Rebuilding assurance updateTo note the Rebuilding Assurance Update. | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. | Noted | Open |
| 2 Sep 2026 | Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.