DECISION TAKEN: Cabinet approved the appropriation of land from the General Fund to the HRA at a value of £215k. REASON FOR DECISION: The redevelopment of Minister House was delivered as part of the Council's Affordable Housing Programme and had provided much needed high-quality homes in Hatfield. As part of this project, a new substation was required to be built to serve the development. The land on which the substation had been built forms part of the Council's General Fund, as that land is no longer required for its previous purpose, and will remain the site of the new substation, the land is required to be appropriated from the General Fund to the council's housing revenue accounts. The market value for this transfer has been agreed and approved by the Section 1 5 1 Officer, and this decision will ensure that lead is the land is held in the appropriate accounts.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1Minster House was approved as part of the Affordable Housing Programme for provision of specialist, over sixties residential accommodation.
1.2Part of the build construction required a new substation to supply the property. As it was not possible to site this on Housing Revenue Account (HRA) land, without otherwise compromising the number of units which could be delivered, a nearby plot of General Fund Land was identified as suitable for the siting of the substation and it is recommended that this should be appropriated to the HRA at Market Value.
2 Recommendation(s)
2.1That Cabinet approves the appropriation of land, as shown in appendix 1, from the General Fund to the HRA at a value of £215k.
3 Explanation
3.1The Affordable Housing development team has overseen the construction project and delivery of social housing for the over sixties at Minster House, Minster Close, Hatfield.
3.2Minster House makes provision for a 91-unit scheme of residential accommodation for over sixties with provision of, a large communal garden, private amenity space, sunroom, reading room, hairdressers, parking spaces, EV chargers, car share scheme, with a kitchen and staff office.
3.3Construction of the new, larger development required provision of a new substation to the site as the previous station was deemed insufficient.
3.4It was not possible to locate the new substation on existing HRA land as this would have compromised the build and number of units able to be delivered to the site.
3.5A nearby plot of General Fund land was identified as suitable for siting of the new substation and this requires formal appropriation between the two funds so that the site is held in the HRA as part of the development. The general fund land is no longer required for the purpose it was held.
3.6The appropriation should take place at Market Value and his land has been valued by external valuers at £215k.
-1- Implications
4 Legal Implication(s)
4.1Subject to the provisions of the section, the council has power under section 122 Local Government Act 1972 to appropriate - for any purpose for which it has authority to acquire land by agreement, - land which is no longer required for the purpose for which it is held immediately before the appropriation.
4.2As the relevant land is not land forming part of a common or land consisting of or forming part of an open space, there is no requirement for the council to advertise or to consult on the, proposed, appropriation.
4.3Section 120 Local Government Act 1972 gives the council power to acquire land by agreement for the purposes of any of their functions. In addition, section 111 of the Act gives the council power to do anything which is calculated to facilitate, or is conducive or incidental to, the discharge of any of the council’s functions.
4.4Appropriation at Market Value is in line with the council’s obligations to ensure best value.
5 Financial Implication(s)
5.1The council us under a duty to ensure it obtains best value when considering the appropriation of assets. An independent external valuation has been obtained to ensure that best value has been considered, and the site has been valued at £215k.
5.2The appropriation will be undertaken in line with accounting guidance, which will be an increase to the capital financing requirement for the HRA and a reduction in the capital financing requirement for the General Fund.
5.3The reduction to the capital financing requirement will be applied in line with the debt reduction strategy agreed as part of the budget for 2024/25, in turn, reducing ongoing capital financing costs on revenue.
6 Risk Management Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.