CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Welwyn Hatfield Borough Council
Cabinet, Tuesday 9 July 2024 at 6.30pm

FP2063 - Howard House Refurbishment

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.

Item263

Resolved

DECISION TAKEN: Cabinet agreed that the pre-contract services agreement for the development of Howard House was awarded to Equans Regeneration Limited. REASON FOR DECISION: A tendering process took place with regard to the establishment of Howard House in Welwyn Garden City. There were 6 bidders, Howard House is a complex building in terms of ownership and responsibilities. The report asked for approval to the award for a pre-contract agreement to Equans for the design of a extensive works and to determine costings. Once a design and costings have been to determined, there will be another Cabinet report towards design and build for the refurbishments
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1Howard House requires major refurbishment works to bring the property up to current standards.

1.2This report explains the process to appoint a contractor to undertake the initial services

2 Recommendation(s)

2.1That the Pre Contract Services Agreement (PCSA) for the development of Howard House is awarded to Equans Regeneration Limited

3 Explanation

3.1Howard House is a Welwyn Garden City Town Centre block built in 1937. It has 52 purpose-built flats across 4 blocks. There are commercial units on the ground floor. Of the 52 homes 35 are tenants and 17 are leaseholders. The Council does not own the freehold to the building but has four headleases (one for each of the four blocks) which require the council to undertake maintenance on the blocks. There is a complex ownership of the freehold with parts of the building (including the commercial units) being owned by several different landlords.

3.2Works will include major improvements to the building fabric, servicing arrangements, security, access, communal spaces and internal layouts to improve liveability, energy efficiency, deal with condensation and ventilation problems and reduce on-going maintenance.

3.3Due to the complexity of the scheme it is considered appropriate for the council to engage a contractor at the early stages of the project to assist with the design of the works.

3.4These would be commissioned under a PCSA and the scope of the services include working with the council and it’s project manager to fully design and cost the scheme.

3.5Once the costing and design of the scheme is completed (and planning permission secured) a further report will be brought back to Cabinet to consider the award of a design and build contract.

3.6At this stage Cabinet will have the option to award the construction contract to Equans Regeneration Limited or not continue with this procurement.

-1- Procurement

3.7Following an application process. 6 bidders were selected to submit tenders. The results of the tender process are included in the Part 2 report.

3.8Equans Regeneration Limited scored the highest against the evaluation criteria.

Implications

4 Legal Implication(s)

4.1As part of the costs of the work will be recharged to Leaseholders, consultation is being carried out in Accordance with Section 20 of the Landlord and Tenant Act 1985.

5 Financial Implication(s)

5.1Details are included in the Part 2 report.

6 Risk Management Implications

6.1As with all procurements of this nature and value there is risk of challenge from unsuccessful bidders.

7 Security and Terrorism Implication(s)

7.1None directly related to this report.

8 Procurement Implication(s)

8.1The procurement was undertaken in accordance with the Public Contracts Regulations 2015 and the Council’s Contract Procedure Rules.

9 Climate Change Implication(s)

9.1The following criteria were included in the evaluation process:

i) Please describe how you will encourage the use of sustainable transport for onsite construction workers. ii) Please detail the initiatives that you would use during the construction process to reduce the cardon generated from the construction phase. iii) Detail the initiatives you will use to reduce the amount of waste going to landfill

10 Human Resources Implication(s)

10.1None directly related to this report.

11 Health and Wellbeing Implication(s)

11.1None directly related to this report.

12 Communication and Engagement Implication(s) -2- 12.1 Residents are being kept up to date with the scheme through regular newsletters.

13 Link to Corporate Priorities

13.1The subject of this report is linked to the Council’s Corporate Priority ‘Homes to be proud of’

14 Equality and Diversity

14.1An EqIA was not completed because this report does not propose changes to existing service-related policies or the development of new service-related policies.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FP2063: Howard House RefurbishmentReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
RM
Roxanne MisirSecretary, expected
SB
Councillor Sandreni BonfanteCommittee Member, present
JB
Councillor James BroachCommittee Member, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
SS
Sheila SaundersOfficer, expected
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, expected
CB
Chris BarnesOfficer, in attendance

All 18 on the meeting page

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies