Decision taken Cabinet noted the capital forecast outturn position and the forecast position as of 30 June 2024 for funding of the capital programme and reserve balances as reflected in Table 2. Cabinet approved the virements set out in Section 3.2 of the report. Reason for decision At the end of the quarter, an overall underspend of around £18.1 million is anticipated. The majority of this was associated with the Housing Revenue Account. These projects are proceeding, but due to reasons set out within the report against individual projects, the timing of spend will be in next financial year. Some virements are set out in the report, to adjust budgets in relation to an adjustment between affordable housing programme schemes and the affordable housing contingency budget. Updates were included within the report, for key capital projects, which currently have no forecast variances. The capital financing had been updated to reflect the latest forecast spend, leading to an overall reduction to borrowing for the year. This borrowing will still be required in future years when the projects are completed.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr James Broach All Wards
WELWYN HATFIELD BOROUGH COUNCIL CABINET – 6 AUGUST 2024 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)
PERIOD 3 CAPITAL BUDGET MONITORING REPORT 2024-25
1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Period 3 (June 2024). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £79.371m (which includes the approved re- phasing of budgets from 2023/24) and the forecast outturn is £61.307m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.
2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 30 June 2024 for funding of the capital programme and reserve balances as reflected in Table 2.
2.3That Cabinet approve the virements set out in Section 3.2.
3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).
£
Original Budget £41.049m
Re-phasing from 2023/24 £38.322m Current Budget £79.371m
3.2It is recommended that the following virements be approved: That budget of £500k from the AHP – General budget (App A ref. 52) be vired to the Minster House Redevelopment project (App A ref. 55). This will cover the costs of the final retention payment and other minor works. 3.3 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2024/25 by Fund and Directorate
Re- Forecast Variance phasing (Under)/ Budget Outturn to of Over 2024/25 2024/25 Budget Capital Outturn Schemes
£'000 £'000 £'000 £'000 £'000
General Fund Executive Director (Finance and Transformation) 647 730 83 0 83
Executive Director (Place) 6,502 5,927 (575) 1,000 425 Executive Director (Resident Services and Climate Change) 1,972 1,539 (436) 436 0
General Fund Total 9,121 8,193 (928) 1,436 508 Housing Revenue Account Executive Director (Finance and Transformation) 35 35 0 0 0
Executive Director (Place) 19,916 7,306 (12,610) 12,660 50 Executive Director (Resident Services and Climate Change) 50,298 45,773 (4,526) 4,566 40 Housing Revenue Account Total 70,250 53,114 (17,136) 17,226 90
Grand TOTAL 79,371 61,307 (18,064) 18,662 598
3.4There is currently a requirement to rephase £18.662m split between funds as follows: General Fund £1.436m – rephase budget into 2025/26 HRA £17.226 – rephase budget into 2025/26 Total net rephasing - £18.662m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.