(1) That the Cabinet note the overall position as at period 6 on the capital programme and the capital funding and reserves. (2) That the Cabinet note the movements of budgets between schemes agreed by the relevant Manager, Head of Service or Director, and reflected in the current budget at period 6. (3) That the Cabinet agree the forecast outturn as summarised and detailed in the report. (4) That the Cabinet agree the capital expenditure forecast as at period 6 and that any changes to the forecast be included in the current budget which would in turn be used as the basis of comparison to the forecast outturn noting that for period 6 the forecast outturn included savings of £138,000 and re-profiling of £238,000 from 2017/18 into 2018/19.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1This report presents the capital expenditure and associated capital funding for both general fund and housing services for the period to 30th September 2017. The report and appendices detail the changes to the original 2017/18 capital programme and funding plans, as a result of programme commitments and project delivery.
1.2At period 6 the current approved budget is £54.348m which includes rolled forward budgets from 2016/17 of £10.597m. The current forecast outturn is £53.973m which includes reductions for savings and re profiling of budgets. A summary by Head of Service is provided in Table 1 and a detailed breakdown by scheme is included in Appendix A.
1.3The resources available to fund the proposed capital programme are summarised in Table 2.
Recommendations
2.1Cabinet to note the overall position as at period 6 on the capital programme (Appendix A), and the capital funding and reserves (Table 2).
2.2Cabinet to note the movements of budgets between schemes agreed by the relevant manager, head of service or director, and reflected in the current budget at period 6 (detailed in Appendix A).
2.3Cabinet to agree the forecast outturn summarised in Table 1 and detailed in Appendix A.
Cabinet are asked to agree the capital expenditure forecast as at period 6, and agree that any changes to the forecast be included in the current budget. This in turn will be used as the basis of comparison to the forecast outturn. For period 6 the forecast outturn includes savings of £138k and re-profiling of £238k from 2017/18 into 2018/19. Forecast changes are summarised in Table 1 and detailed in Appendix A.
-1- 3 Explanation
3.1The capital expenditure position is summarised below in Table 1 and a detailed breakdown by capital scheme per directorate can be found in Appendix A.
Table 1: Capital Expenditure Budgets by Head of Service as at period 6
Current Approved Budget Original Roll 2017/18 Forecast (Under)/ Re- Description Budget Forwards (including Outturn Over profiling to 2017/18 from 2016/17 2017/18 Budget 2018/19 16/17 roll forwards)
£'000 £'000 £'000 £'000 £'000 £'000
Head of Planning 93 174 267 267 0 0 Head of Law and Administration 15 0 15 15 0 0 Head of Public Health and Protection 20 0 20 20 0 0 Executive Director - Public Protection, Planning and Governance 128 174 302 302 0 0
Head of Resources 8,594 1,093 9,687 9,662 0 (25)
Head of Environment 4,816 22 4,839 4,839 0 0 Head of Policy and Culture 2,893 82 3,099 2,961 (138) 0 Executive Director - Resources, Environment & Cultural Services 16,303 1,197 17,624 17,461 (138) (25) Head of Community & Housing Strategy 15,400 5,105 20,694 20,694 0 0 Head of Housing Property Services 11,795 4,005 15,612 15,515 0 (97) Head of Housing Operations 0 116 116 0 0 (116) Executive Director - Housing and Communities 27,195 9,226 36,422 36,209 0 (213)
TOTAL 43,627 10,597 54,348 53,972 (138) (238)
-2- 3.2 Capital Schemes progress to date
3.21Hatfield Town Centre (HTC) – Original budget for 2017/18 is £0.750m plus budgets for Highview redevelopment of £0.350m and Salisbury square £0.050m. The current budgets include rolled forward budgets from 2016/17 of £0.799m and in year virements giving a total current budget including Highview and Salisbury Square of £1.993m.
Phase two of the redevelopment is now being delivered including public realm costs. Other expenditure in year will be for refurbishment works to White Lion House flats, Culpitt House, HTC shop roofs, and final fit out costs for HTC flats and new units, plus associated fees. Costs are expected to continue into 2018/19 with further development of the town centre. The sale of Salisbury Square is going forward for cabinet approval in October. Remaining costs for this scheme will be legal fees on transfer.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.