Cabinet received the Part 1 report on the Council’s arboriculture contract. Decision taken Cabinet agreed to: a) Award the following contracts for an initial three year period (with an optional one year extension) commencing on 1st January 2025: · Lot 2 (Maintenance of Young Trees) is awarded to: Maydencroft Limited · Lot 3 (Maintenance of Woodland trees) is awarded to Maydencroft Limited b) Extend the current contract with Maydencroft Limited for a period of three months for maintenance of urban trees (Lot 1). c) That new procedurement can commence for Urban Tree Maintaenance (Lot 1) and be evaluated 50% on price and 50% on quality Reason for decision The Council is responsible for the maintenance of 30,000 trees across the Borough and manage this responsibility through a contract that includes lots for a) b) c) Maintenance of Urban Trees Maintenance of Young Trees Maintenance of Woodland Trees The current contract expires at the end of December 2024 and following approval by the Executive Member, a new procurement was undertaken.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
1.1The current contract for Arboriculture Services expires at the end of December 2024 and this report considers its replacement.
2 Recommendation(s)
2.1That Cabinet agrees to award the following contracts for an initial three year period (with an optional one year extension) commencing on 1 st January 2025:
Lot 2 (Maintenance of Young Trees) is awarded to: Maydencroft Limited
Lot 3 (Maintenance of Woodland trees) is awarded to Maydencroft Limited
2.2That in accordance with clause 31.2g (Alternative procedures in prescribed circumstances), Cabinet agree to extend the current contract with Maydencroft Limited for a period of three months for maintenance of urban trees (Lot 1).
2.3That Cabinet agree a new procurement can commence for Urban Tree Maintenance (lot 1) and be evaluated 50% on price and 50% on quality.
3 Explanation
3.1The council is responsible for the maintenance of 30,000 trees across the Borough and manage this responsibility through a contract that includes lots for
a) Maintenance of Urban Trees
b) Maintenance of Young Trees
c) Maintenance of Woodland Trees
3.2The current contract expires at the end of December 2024 and following approval by the Executive Member, a new procurement has been undertaken. The procurement was undertaken on the basis of the three lots as above, but for lot 1, two contractors will be appointed with the work split between them on a geographical basis. The contract has provision that if one contractor underperforms, more work can be given to the other contractor.
3.3The results of the tender process and pricing is included in the Part 2 report.
Implications
-1- 4 Legal Implication(s)
4.1The procurement process was carried out in accordance with the Public Contracts Regulations and the council’s Contract Procedure Rules. In relation to Lot 1 the council has a discretion not to award a contract. Further details are contained with the part 2 report
5 Financial Implication(s)
5.1Further details are contained with the part 2 report
6 Risk Management Implications
6.1As with any procurement of this nature there is a risk of challenge from unsuccessful tenderers.
7 Security and Terrorism Implication(s)
7.1None directly associated with this recommendation
8 Procurement Implication(s)
8.1The Procurement has been undertaken in accordance with the Public Contracts Regulations 2015
9 Climate Change Implication(s)
9.1Part of the tender evaluation was allocated to climate change initiatives. Responses from the winning bidders included:
main office is equipped with solar panels. We have a number of electric vehicles and the entire vehicle fleet is no less than Euro 6 and compliant with the new ULEZ standards. Prevent pollution, reduce waste and ensure that, wherever practical, measures are implemented to protect and preserve natural habitats, flora and fauna. Promote good environmental practices to minimise our impact on the environment and where at all possible, make a positive contribution to enhancing biodiversity. Investment in electric hand tools such as hedge cutters, pumps, strimmers, chainsaws Recycling of green waste including wood chippings for power stations
10 Human Resources Implication(s)
10.1None directly associated with this recommendation
11 Health and Wellbeing Implication(s)
11.1None directly associated with this recommendation
12 Communication and Engagement Implication(s)
12.1None directly associated with this recommendation -2- 13 Link to Corporate Priorities
13.1The subject of this report is linked to the Council’s Corporate Priority ‘To run an effective council and make financial decisions to deliver efficient and quality services
14 Equality and Diversity
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.