Capital Budget Monitoring Report Q2

Noted Executive 2 papers

Cabinet noted this item on Tuesday 5 November 2024. Below is the council's own wording, with the papers it was decided on.

Item312

Resolved

Decision taken Cabinet noted: a) The capital forecast outturn position b) The forecast position as of 30 September 2024 for funding of the capital programme and reserve balances as reflected in Table 2. c) The virements set out in Section 3.2. Reason for decision The report presented Cabinet with the forecast out turned for capital at the end of Quarter 2 2024/25.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr James Broach All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 5 NOVEMBER 2024 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)

QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2024-25

1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 2 (September 2024). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £79.371m (which includes the approved re- phasing of budgets from 2023/24) and the forecast outturn is £56.479m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.

2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 30 September 2024 for funding of the capital programme and reserve balances as reflected in Table 2.

2.3That Cabinet approve the virements set out in Section 3.2.

3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).

£ Original Budget £41.049m

Re-phasing from 2023/24 £38.322m Current Budget £79.371m

3.2It is recommended that the following virements be approved: • That budget of £17k from the AHP – General budget (App A ref. 52) be vired to AHP – The Commons budget. This will cover the costs of the final retention payment for this scheme. • That budget of £23k from the AHP – General budget (App A ref. 52) be vired to AHP – Ludwick Way budget (App A ref. 56). This will cover the costs of the final retention payment for this scheme. • That budget of £15k from the AHP – General budget (App A ref. 52) be vired to AHP – Queensway House budget (App A ref. 61). This will cover small overspends on this scheme. 3.3 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2024/25 by Fund and Directorate

Re- Forecast Variance phasing (Under)/ Budget Outturn to of Over 2024/25 2024/25 Budget Capital Outturn Schemes

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 647 675 29 0 29

Executive Director (Place) 6,700 5,168 (1,533) 1,150 (383) Executive Director (Resident Services and Climate Change) 1,774 1,310 (464) 436 (28)

General Fund Total 9,121 7,153 (1,968) 1,585 (382) Housing Revenue Account Executive Director (Place) 19,916 6,184 (13,732) 14,187 455 Executive Director (Resident Services and Climate Change) 50,334 43,142 (7,192) 5,975 (1,217) Housing Revenue Account Total 70,250 49,326 (20,924) 20,162 (762)

Grand TOTAL 79,371 56,479 (22,892) 21,748 (1,144)

3.4There is currently a requirement to rephase £21.748m split between funds as follows: General Fund £1.585m – rephase budget into 2025/26 HRA £20.162m – rephase budget into 2025/26 Total net rephasing - £21.748m 3.5 Key forecast variances are outlined below:

General Fund:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 139 KB Download
PDF
Capital Budget Monitoring Report Q2Report 202 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
RM
Roxanne MisirSecretary, expected
SB
Councillor Sandreni BonfanteCommittee Member, present
JB
Councillor James BroachCommittee Member, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, expected
RB
Richard BakerOfficer, in attendance
SS
Sheila SaundersOfficer, expected
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, expected
CC
Clare CadeSecretary, in attendance

All 18 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Capital Budget Monitoring Report Q2This decision
  2. Q3 capital budget monitoring report 2025/26Noted
  3. Capital budget monitoring report q2Noted
  4. Quarter 1 Capital Budget Monitoring ReportNoted
  5. Quarter 3 capital budget monitoring report 2024-25Noted
  6. Period 3 capital budget monitoring report 2024-25Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies