CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Welwyn Hatfield Borough Council
Overview and Scrutiny Committee, Tuesday 18 March 2025 at 7.30pm

Parking: Report and Recommendations from Task and Finish Group

Noted Scrutiny 4 papers

Overview and Scrutiny Committee noted this item on Tuesday 18 March 2025. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

RESOLVED The Committee: 1) Noted that CPPP would be considering the 2026-28 Parking Works programme during 2025 and asked it to: a) Build in flexibility to follow up consultations to take place on larger schemes within the same Parking Works programme rather than having to wait for subsequent Parking Works programmes. It was acknowledged that this could adversely impact the capacity of the work programme. b) Ensure that these do not overly impact the remainder of the Parking Works programme. These follow up consultations should only occur where the original consultation was in excess of 1,000 properties. c) See these follow up consultations should be limited in size, being no more than three roads within a consultation area and that the total number of properties reconsulted should be no more than 100. d) These follow up consultations can be triggered by a request by a minimum of two members for the relevant wards, with approval by the Executive Member for Environment; and 2) Ask CPPP to agree that prior to the review period commencing ward councillors will be informed by Parking Services, and the timetable for considering feedback from the review and implementing any changes will be confirmed once it is known.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Executive summary

1.1Parking Services are tasked by Cabinet Planning and Parking Panel with carrying out the Parking Works Programme. This is a programme of consultations carried out across the Borough with a view to seeking the views of residents and other stakeholders on the need to introduction, removal and amendment of parking restrictions. The programme is set every two years and the current Parking Works Programme is for 2024 to 2026.

1.2A Task and Finish Group was set up to review the parking consultation process and make recommendations to OSC for improvements.

1.3A number of meetings were held and the process was reviewed in detail, leading to two recommendations.

2 Recommendation(s)

2.1That the Committee notes that the Cabinet Parking and Planning Panel (CPPP) will be considering the 26-28 Parking Works Programme during 2025 and would ask CPPP to:

- Build in flexibility for follow up consultations to take place on larger schemes within the same Parking Works Programme, rather than having to wait for subsequent Parking Works Programmes. It is acknowledged this could adversely impact the capacity of the work programme.

Ensure that these do not overly impact the remainder of the Parking Works Programme these follow up consultations should only occur where the original consultation was in excess of 1,000 properties.

- That these follow up consultations should be limited in size being no more than three roads within a consultation area and that the total number of properties reconsulted should be no more than 100.

- That these follow up consultations can be triggered by a request by a minimum of two members for the relevant wards, with approval by the Executive Member for Environment.

2.2That prior to the review period commencing Ward Councillors will be informed by Parking Services and the timetable for considering feedback from the review and implementing any changes will be confirmed once it is known.

-1- 3 Explanation

3.1A Task and Finish Group was set up to review the Parking Consultations Process, three meetings were held on the 13th January, 27th January and 11th February respectively. Officers presented on the following topics:

Parking Restrictions and Legal Framework – Introduction and overview.

Parking Works Programme – Introduction and 24-26 Programme.

Parking Enforcement – Introduction and Legislation

Income and Expenditure from Parking Enforcement

Case Study of implementation

How the 24/26 Parking Works Programme was determined.

Capacity of the Parking Works Programme and potential to amend in the future.

Minutes of these meetings have been published through the Council’s normal process and are attached as appendices to this report.

3.2Members of the Task and Finish Group were keen that the 26-28 Parking Works Programme included spare capacity to allow for follow up consultations. Examples were given of roads within recent consultations which had voted against resident permits and now regretted them not being implemented following implementation in surrounding roads. Whilst all TRO’s are reviewed following implementation this does not allow for changes as substantial as those given in the example, which would require a follow up consultation.

3.3It was recognised that doing this would place an additional burden on Parking Services. It would therefore require either increasing the resources available to Parking Services, or reducing the scope of future Parking Works Programmes.

3.4Given the desire for the Parking Works Programme and Parking Enforcement as a whole to be cost neutral it was recognised that there was no scope to increase the staffing resources available to Parking Services.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 32 KB Download
PDF
Appendix 2Appendix 2 34 KB Download
PDF
Appendix 3Appendix 3 119 KB Download
PDF
Parking: Report and Recommendations from Task and Finish GroupReport 89 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 23 attended
RM
Roxanne MisirOfficer, in attendance
GM
Councillor George MichaelidesCommittee Member, apologies, sent representative
LC
Councillor Larry CroftonCommittee Member, present
TR
Councillor Tim RowseCommittee Member, present
KN
Ka NgOfficer, expected
HO
Helen O'KeeffeOfficer, expected
RB
Richard BakerOfficer, in attendance
SM
Sue McDaidOfficer, in attendance
GS
Geoff SampsonOfficer, in attendance
TM
Councillor Terry MitchinsonCommittee Member, present
LM
Councillor Lucy MuskCommittee Member, present
AN
Councillor Adrienne NixCommittee Member, present

All 23 on the meeting page

More from Welwyn Hatfield Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 Actions status reportResolved To note the report. Noted Open
22 Jul 2026 Committee work programme 2026/27To note the Overview and Scrutiny Work Programme 2026/27 Noted Open
4 Mar 2026 Final Report of the Housing Voids Task & Finish GroupThe Overview and Scrutiny Committee noted the report, and agreed the recommendations as set out in the report. Noted Open
4 Mar 2026 Final report of the Customer Communication & Case Management Task and Finish GroupThe Overview and Scrutiny Committee noted the report, and the recommendations in the report be referred to Cabinet. Noted Open
4 Mar 2026 Presentations on Crime and DisorderRecommendations from report/what was agreed. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies