Q2 PERFORMANCE, KPI AND RISK REPORT

Noted Executive 2 papers

AI summaryWelwyn Hatfield Cabinet noted the Q2 2025-26 performance report, which shows 87% of projects on track and 78% of key performance indicators met or within tolerance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the report and its appendix
MoneyNot stated
What happens nextQuarterly monitoring continuesNext quarterly report expected in Q3 cycle
Who it affectsAll wardsCovers whole council, all corporate priorities

What was decided

Cabinet noted the contents of the Q2 performance, KPI and risk report and Appendix 1. Report P5

Why

The report is part of the council's performance management framework, with performance monitored monthly by the Chief Executive, Directors and Assistant Directors. Report P4, P6

Working with Directors and Assistant Directors on the report ensures accountability for performance within the officer structure and provides detailed information to council leadership. Report P6

What happens next

Continue monthly monitoring of key performance indicators, projects and risks, with the next quarterly report presented to Cabinet after Q3. Report P6

Use the updated targets for KPIs 130 and 131 (now aligned to contractor performance targets) for ongoing monitoring. Report 3.4

Implications

  • Risk: The risk assessment of the performance management framework is reviewed quarterly on the council's strategic risk register. Report P11
  • Financial: Failure to deliver corporate projects and KPIs may have a financial impact; any such cases are referenced in Appendix 1. Report P10
  • Legal: No direct legal implications arise from the report. Report P9
  • Legal: No procurement implications arise from the report. Report P12
  • Climate: No direct climate change implications arise from the report. Report P13
  • Other: No health and wellbeing, communication and engagement, or human resources implications arise from the report. Report P14, P15, P16
  • Equalities: No Equality Impact Assessment was completed because the report does not propose changes to existing service-related policies or new service-related policies. Report P18

Who and where

  • All wards and all council services, since the report covers corporate priorities council-wide Report P1, P17

Timeline

  • 1 July 2025 to 30 September 2025: Reporting period covered (Q2 of 2025-26) Report P4
  • October 2025: Report authored by Assistant Director (Customer Service & Transformation) Report P19, P20
  • 4 November 2025: Cabinet noted the report Report P2

Plain English for the jargon

  • KPI: Key Performance Indicator, a measurable target used to track council performance.
  • Q2 2025-26: The second quarter of the 2025-26 financial year, covering 1 July to 30 September 2025.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item499

Resolved

Cabinet noted the content of the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: 0 Main author: Kirsten Roberts Executive Member: Cllr Max Holloway All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET 4 NOVEMBER 2025 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)

PERFORMANCE, KPI AND RISK REPORT – QUARTER 2 (2025-26)

1 Executive Summary 1.1 This report summarises the council’s corporate quarterly performance data following the monitoring and review of performance reports by the Chief Executive, Directors, and Assistant Directors. This report covers the period 1 July 2025 to 30 September 2025 (Q2). 1.2 All corporate projects, key performance indicators and risks are reported in Appendix 1.

2 Recommendation 2.1 That Cabinet note the contents of this report and Appendix 1.

3. Explanation 3.1 All performance relating to key performance indicators, projects and risks are monitored monthly and reported to Cabinet on a quarterly basis as part of the council’s performance management framework. 3.2 By working with Directors and Assistant Directors in the production of this report, it ensures accountability for performance within the officer structure. This allows for a flow of detailed information to and from the council’s leadership.

3.3By the end of Q2, 87% of projects were completed or on schedule with no risks, and 78% of KPIs have been met or are within tolerance.

3.4In Q2, the targets for KPIs 130 and 131 have been updated to mirror contractor performance targets and Q1 data has also been updated to reflect this.

4. Legal Implications 4.1 There are no direct legal implications arising from the contents of this report.

5. Financial Implications 5.1 Failure to deliver corporate projects and key performance indicators may have a financial impact for the council. Where this is the case, it will be referenced in Appendix 1, as appropriate.

6. Risk Management Implications 6.1 A risk assessment of our performance management framework is reviewed quarterly on the council’s strategic risk register. 7. Security and Terrorism Implications 7.1 There are no security and terrorism implications directly arising from the contents of this report.

8. Procurement Implications 8.1 There are no procurement implications directly arising from the contents of this report.

9. Climate Change Implications 9.1 There are no direct climate change implications directly arising from the contents of this report.

10. Health and Wellbeing Implications 10.1 There are no health and wellbeing implications directly arising from the contents of this report.

11. Communication and Engagement Implications 11.1 There are no communication and engagement implications directly arising from the contents of this report. Separate communication plans are in place for corporate projects, as required.

12. Human Resources Implications 12.1 There are no human resources implications directly arising from the contents of this report.

13. Link to Corporate Priorities 13.1 This report is linked to all the council’s corporate priorities as it shows the status of those corporate projects and performance targets associated within each priority.

14. Equality and Diversity 14.1 An Equality Impact Assessment has not been completed because this report does not propose changes to existing service-related policies or the development of new service-related policies.

Name of author Kirsten Roberts Title Assistant Director (Customer Service & Transformation)

Date October 2025

Appendix 1 Performance Report (Q2 2025-26)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_ Quarter 2 Performance ReportAppendix 1 18 MB Download
PDF
Q2 PERFORMANCE, KPI AND RISK REPORTReport 130 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
AS
Councillor Astrid ScottCommittee Member, present
BC
Bernice ComptonSecretary, expected
RM
Roxanne MisirSecretary, expected
SB
Councillor Sandreni BonfanteCommittee Member, present
MH
Councillor Max HollowayCommittee Member, apologies
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, in attendance
CC
Clare CadeSecretary, in attendance

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Q2 PERFORMANCE, KPI AND RISK REPORTThis decision
  2. Quarter 1 performance, kpi and risk reportDecided
  3. Key Performance, KPI and Risk ReportDecided
  4. Q3 performance report, kpi and risk reportNoted
  5. Quarter 1 Performance, KPI and Risk ReportNoted
  6. PERFORMANCE REPORT FOR HOUSING Q2 (KPIs)Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies