Welwyn Hatfield Borough Council
Cabinet, Tuesday 4 November 2025 at 6.30pm

CAPITAL BUDGET MONITORING REPORT Q2

Noted Executive 2 papers

AI summaryWelwyn Hatfield Cabinet noted a forecast capital outturn of £84.702m against a £101.702m budget and approved virements, including £2.900m to cover an insulation overspend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedForecast outturn and virements approved
Money£84.702m forecast, £101.702m budgetForecast outturn of £84.702m against current budget
What happens nextRephase £16.439m into 2026/27Move budget into next financial year
Who it affectsCouncil capital programmeGeneral Fund and Housing Revenue Account schemes

What was decided

Cabinet noted the capital forecast outturn position, showing a £17.000m variance to budget partly offset by £16.439m of rephasing. Report P4, P18

Cabinet noted the forecast position as of 30 September 2025 for funding of the capital programme and reserves balances. Report P5

Cabinet approved virements including £0.425m from AHP New Schemes to AHP Open Market Purchases, and £2.236m from Major Repairs plus £0.664m from Heating Replacement to fund the Insulation Improvements overspend. Report P5

Why

The Insulation Improvements project is forecast to overspend by £2.900m because more damp and mould works are needed, and funding is being moved from underspends in related maintenance budgets.

Two properties have been bought for affordable housing under the AHP Open Market Purchases scheme at a cost of £0.425m, and budget is being transferred from the AHP New Schemes line.

Several large schemes including Howard House, AHP Burfield, and AHP Howlands House will not spend their full budget this year, and a budget correction removes £0.073m, £0.200m and £0.053m wrongly rolled forward from 2024/25.

What happens next

A detailed Cabinet report is being prepared on options for reallocating the £5.720m AHP Burfield budget, and another on the proposed disposal of the Hazel Grove site.

Signing of the Howard House redevelopment contract is expected in autumn 2025, with £8.726m rephased into 2026/27.

Section 106 funded Angerland Football and Rugby Improvement Schemes will continue to be reviewed for suitable projects, with budgets rephased into 2026/27 in the meantime.

The money

  • £101.702m Current approved capital budget for 2025/26 Report P4, P11
  • £84.702m Forecast outturn for 2025/26 Report P4, P18
  • £16.439m Total budget to be rephased into 2026/27 Report 3.5, P20
  • £2.900m Forecast overspend on Insulation Improvements project
  • £0.425m Virement from AHP New Schemes to AHP Open Market Purchases
  • £2.236m Virement from Major Repairs to Insulation Improvements
  • £0.664m Virement from Heating Replacement Programme to Insulation Improvements
  • £15.700m Additional budget for the Gatehouse purchase Report P9

Options considered

  • Chosen: Vire £0.425m from AHP New Schemes to AHP Open Market Purchases. To fund the purchase of two properties for affordable housing
  • Chosen: Vire £2.236m from Major Repairs and £0.664m from Heating Replacement Programme to Insulation Improvements. To cover a £2.900m overspend driven by extra damp and mould works
  • Chosen: Remove £0.073m, £0.200m and £0.053m rolled forward in error from 2024/25. Late accrual correction at year end 2024/25
  • Chosen: Rephase AHP Burfield £5.720m into 2026/27 and prepare a Cabinet report on reallocation. The Burfield redevelopment is no longer planned to go ahead

Implications

  • Legal: No direct legal implications, though individual projects will need legal input on procurement and contracts. Report P27
  • Risk: No risk management implications identified directly from the report. Report P29
  • Other: No equality impact assessment carried out as the report does not directly change services. Report P35

Who and where

  • Council tenants receiving insulation, damp and mould works
  • Households placed in the two properties bought under AHP Open Market Purchases
  • Howard House residents awaiting the redevelopment contract signing
  • Users of football and rugby facilities in the Angerland area
  • Affordable housing prospects in Welwyn Garden City through the Gatehouse purchase

Timeline

  • 30 September 2025: Forecast position date for capital programme and reserves Report P5
  • 4 November 2025: Cabinet decision date Report P1, P2
  • Autumn 2025: Expected signing of the Howard House redevelopment contract
  • 2026/27: Rephased budgets to be spent, including £1.000m General Fund and £15.439m HRA Report 3.5, P20

Plain English for the jargon

  • Virement: Moving budget from one spending line to another within the same overall budget.
  • Rephasing: Shifting planned spending from one financial year into a later one.
  • AHP: Affordable Housing Programme, a council scheme for new affordable homes.
  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spending.
  • Section 106 funding: Money paid by developers to mitigate the impact of their developments, earmarked for specific local facilities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item497

Resolved

Cabinet: 1. Noted the capital forecast outturn position. 2. Noted the forecast position as of 30 th September 2025 for funding of the capital programme and reserves balances. 3. Approved the virements set out in the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr Astrid Scott All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 4 NOVEMBER 2025 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)

QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2025-26

1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 2 (September 2025). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £101.702m (which includes the approved re- phasing of budgets from 2024/25) and the forecast outturn is £84.702m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.

2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 30 September 2025 for funding of the capital programme and reserve balances as reflected in Table 2. 2.3 That Cabinet approve the virements set out in Section 3.2.

3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).

£ Original Budget £55.990m

Re-phasing from 2024/25 £29.199m

Additional budget for Gatehouse purchase £15.700m

Additional budget for Outdoor Energy Gym £0.020m

Additional budget for Food Waste Recycling project £0.793m Current Budget £101.702m 3.2 It is recommended that the following virements be approved: • That £0.425m from the AHP – New Schemes budget (App A ref. 50) be vired to the AHP – Open Market Purchases budget (App A ref. 39) to fund the purchase of two properties which are to be used for affordable housing. • That £2.236m from the Major Repairs budget (App A ref. 49) and £0.664m from the Heating Replacement Programme (App A ref. 53) be vired to fund the forecasted overspend on the Insulation Improvements project (App A ref. 51). This overspend has arisen due to increased damp and mould works required. 3.3 In addition to the virements above, a budget correction is required. Due to a late accrual at the end of 2024/25, budgets were rolled forward that should not have been. It is therefore proposed to remove these budgets in 2025/26. These budgets are £0.073m from the Hatfield Town Centre Public Realm budget (App A ref. 8), £0.200m from the Play Area Replacement Scheme budget (App A ref. 12), and £0.053m from the Hatfield Town Centre Marketplace budget (App A ref. 17). 3.4 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2025/26 by Fund and Directorate

Re- Variance phasing (Under)/ Budget Outturn to of Over 2025/26 2025/26 Budget Capital Budget Schemes

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 229 229 0 0 0

Executive Director (Place) 18,978 17,782 (1,196) 1,000 (196) Executive Director (Resident Services and Climate Change) 2,820 2,855 35 0 35

General Fund Total 22,027 20,866 (1,161) 1,000 (161) Housing Revenue Account

Executive Director (Place) 17,690 10,127 (7,563) 7,163 (400) Executive Director (Res Services and Climate Change) 61,985 53,709 (8,276) 8,276 0 Housing Revenue Account Total 79,675 63,836 (15,839) 15,439 (400)

Grand TOTAL 101,702 84,702 (17,000) 16,439 (561)

3.5There is currently a requirement to rephase £16.439m split between funds as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 2 Capital Monitor 2025-26Appendix A 182 KB Download
PDF
CAPITAL BUDGET MONITORING REPORT Q2Report 236 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
AS
Councillor Astrid ScottCommittee Member, present
BC
Bernice ComptonSecretary, expected
RM
Roxanne MisirSecretary, expected
SB
Councillor Sandreni BonfanteCommittee Member, present
MH
Councillor Max HollowayCommittee Member, apologies
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, in attendance
CC
Clare CadeSecretary, in attendance

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. CAPITAL BUDGET MONITORING REPORT Q2This decision
  2. Q3 capital budget monitoring report 2025/26Noted
  3. Quarter 1 Capital Budget Monitoring ReportNoted
  4. Quarter 3 capital budget monitoring report 2024-25Noted
  5. Capital Budget Monitoring Report Q2Noted
  6. Period 3 capital budget monitoring report 2024-25Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies