Resolved
RESOLVED Cabinet resolved to: Make a direct contract award to Falcon Structural Repairs, Watford to complete the repairs to the embankment.
AI summaryWelwyn Hatfield Cabinet awards a direct contract to Falcon Structural Repairs of Watford for embankment repairs at Stanborough Lakes.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED Cabinet resolved to: Make a direct contract award to Falcon Structural Repairs, Watford to complete the repairs to the embankment.
11 August 2026 Agenda Item No. 7b
Committee: Cabinet
Report title: Direct Award of Contract for Embankment work at Stanborough Lakes
Forward Plan number: FP2262
Report author: John Beare, Senior Building Surveyor
Responsible Officer: Executive Director (Residents Services and Climate Change)
Cabinet Member(s) responsible: Gemma Moore, Executive Member for Housing
Part 1 or 2: Part 1
Executive Summary: This report seeks Cabinet approval to directly award a contract to Falcon Structural Repairs to undertake embankment repair works at Stanborough Lakes at a cost of £44k. The embankment and adjacent footpath have deteriorated over time due to erosion and sustained high river levels, resulting in uneven surfacing, missing paving, reduced path width and increased complaints from park users. The proposed direct award is considered the most appropriate route because the works are specialist and complex, and previous market engagement identified limited suitable contractors with the necessary experience. Falcon’s proposal provides a structured method for completing the embankment repairs and reinstating the block paving, reducing delivery and cost risks when compared with the alternative proposal received. Failure to progress the works is likely to result in continued erosion, further deterioration of the footpath and an increased risk of trips and falls, particularly for vulnerable users and those using mobility aids. The condition of the route has already affected public use of the area, including organised events that would normally use the underpass path. A capital allocation of £50,000 has been approved under CapProg reference C0985, with the works expected to be completed in Q3 2026/27. The recommendation supports the Council’s priorities to enable an economy that delivers for everyone and to run an effective council by maintaining safe, accessible public infrastructure and reducing the likelihood of further service disruption or additional remedial costs. Recommendations:
It is recommended that Cabinet:
a) make a direct contract award to Falcon Structural Repairs, Empire House, Bermer Road, Off Imperial Way, Watford, WD24 4YX to complete the repairs to the embankment. 11 August 2026 Agenda Item No. 7b
2. Background and key issues
2.1The condition of the embankment of the river Lea as it passes through Stanborough Park has slowly been deteriorating over the years. Numerous repairs have been undertaken to the paving.
2.2Works will be completed in Q3 to limit disruption to users of Splashlands.
2.3The continued erosion of the bank of the river is narrowing the path as it runs under the road dividing the north and south side of the park.
2.4The number of complaints of the area is increasing.
3. Corporate Priorities
This reports supports the council in meeting the corporate priority/priorities of:
• Enable an economy that delivers for everyone • Run an effective council
4. Risk Management Implications 4.1 The alternative proposal is not considered feasible by the structural engineers as the risk to not dam the river would be too high leading to complications and delays.
4.2The alternative proposal did not include a feasibility statement for their proposal. Undertaking works without a dam would be a risk and costs of dams and pumps could significantly add to the cost of the project
4.3The path may require closing off should this work be left unattended.
5. Financial Implications 5.1 The proposal to complete the work by Falcon provides a structured approach to repairing the embankment and relaying the block paving. This method reduces the risk of overspending.
5.2The proposal to complete the work with alternative supplier is provided by a sub- contractor. The aqua blocks that they have specified can only be installed at low water levels, but should the water levels be higher than those noted at the time of survey then a dam and pumping will require costing. They do not include the footpath repairs in their quote.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FP2262 DIRECT AWARD OF CONTRACT FOR EMBANKMENT WORK AT STANBOROUGH LAKESReport | 160 KB | DownloadRead as text |
PDF |
Part 1 Apendix 1 Stan_Lakes_photographs 1Report | 389 KB | Download |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.