Welwyn Hatfield Borough Council
Cabinet, Tuesday 11 August 2026 at 6.30pm

QUARTER 1 CAPITAL MONITORING REPORT 2026/27

Noted Executive 2 papers

AI summaryCabinet noted a capital forecast outturn of £77.526m against a £87.356m budget for 2026/27, with £8.720m re-phased into 2027/28 and a £0.478m virement approved for the Warm Homes grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedForecast outturn and funding position noted, Warm Homes virement approved
MoneyNot stated
What happens next£8.720m re-phased to 2027/28HRA schemes to be re-phased into next financial year
Who it affectsHRA housing and town centre projectsSeveral Affordable Housing Programme schemes and town centre regeneration

What was decided

Cabinet noted the capital forecast outturn of £77.526m shown in Table 1 of the report. Report P6, 1.2

Cabinet noted the forecast funding position and reserve balance as at 30 June 2026 in Table 2. Report P7

Cabinet approved a virement of £0.478m to create income and expenditure budgets for the Warm Homes Local Government grant. Report P8, P16, 2.2

Why

The report presents capital expenditure and funding at the end of Quarter 1, showing changes to the original capital programme from programme commitments and project delivery. Report 1.1, 1.2

Several HRA Affordable Housing Programme schemes are being re-phased or showing underspends, including Howlands House (£2.000m), Burfield (£5.720m), Haseldine Meadows (£0.418m), Lockley Crescent (£0.800m) and Peartree (£1.000m). Report P43, P46, P48, P50, P52

What happens next

HRA capital budget of £8.720m to be re-phased into 2027/28, as detailed in Section 2.3 of the report. Report 2.3, P27, P29

AHP Haseldine Meadows and AHP Lockley Crescent to merge into the AHP Phase 3 Garage Sites project, expected to commence on site in late summer. Report P48, P50

The money

  • £87.356m Current approved capital budget for 2026/27 (including re-phasing from 2025/26) Report 1.2, P14, P27
  • £77.526m Forecast capital outturn for 2026/27 Report 1.2, P27
  • £8.720m HRA budget to be re-phased into 2027/28 Report P27, P29
  • £0.478m Virement to create income and expenditure budgets for Warm Homes Local Government grant Report P16, 2.2
  • £2.000m Rephasing for AHP Howlands House Redevelopment and Additional Units Report P43, P44
  • £5.720m Rephasing for AHP Burfield (budget reallocated to other AHP schemes) Report P45, P46
  • £0.418m Favourable variance (underspend) for AHP Haseldine Meadows Report P47, P48
  • £0.800m Favourable variance (underspend) for AHP Lockley Crescent Report P49, P50
  • £1.000m Rephasing for AHP Peartree Report P51, P52

Options considered

  • Chosen: Approve virement of £0.478m for Warm Homes Local Government grant. To create income and expenditure budgets reflecting the grant Report P8, P16, 2.2
  • Chosen: Note the capital forecast outturn in Table 1. Required to review the Quarter 1 position Report P6
  • Chosen: Note the funding and reserve position in Table 2. Required to review the Quarter 1 position Report P7

Implications

  • Financial: General Fund capital expenditure is forecast to be slightly higher than budgeted; ongoing management fees on finished projects will be funded by borrowing. Report P75
  • Financial: HRA borrowing requirement for the year is reduced by £2.017m to reflect re-phasing of Affordable Housing Programme schemes. Report P72, P78
  • Equalities: No Equality Impact Assessment carried out as there is no direct impact on services from the recommendations. Report P87
  • Legal: No direct legal implications, though individual projects will require legal input into procurement and contractual documentation. Report P85
  • Risk: No direct risk management implications arising from the report. Report P83
  • Other: Report supports corporate priorities including housing, economy, climate change and effective council operations. Report P80, P82

Who and where

  • Housing Revenue Account tenants (Affordable Housing Programme schemes including Howlands House, Burfield, Haseldine Meadows, Lockley Crescent, Peartree) Report P43, P46, P48, P50, P52
  • Town centre regeneration projects in Hatfield and Welwyn Garden City (small overspends funded by borrowing) Report P36, P37, P38, P39, P40
  • Council tenants benefiting from Major Repairs (£20.000m), Insulation Improvements (£6.422m), Decarbonisation HRA (£6.910m) and Heating Replacement (£3.000m) Report P56, P57, P59, P60, P61, P62, P65, P66

Timeline

  • 30 June 2026: Forecast funding position and reserve balance as at end of Quarter 1 Report P7
  • Late summer 2026: AHP Phase 3 Garage Sites project (merging Haseldine Meadows and Lockley Crescent) expected to commence on site Report P48, P50
  • 2027/28: £8.720m of HRA capital budget to be re-phased into this year Report P27, P29

Plain English for the jargon

  • Virement: An authorised transfer of budget between headings within the capital programme.
  • HRA: Housing Revenue Account, the ring-fenced account that funds council housing.
  • Re-phasing: Moving budgeted capital spending from one financial year to a later one.
  • MRP: Minimum Revenue Provision, the amount the council must set aside to repay debt.
  • AHP: Affordable Housing Programme, the council's development programme for new affordable homes.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67

Resolved

RESOLVED Cabinet resolved to: a) Note the capital forecast outturn as shown in Table 1 of the report. b) Note the forecast position as at 30 June 2026 for funding of the capital programme and reserve balance as reflected at Table 2 of the report c) Approve the virements set out in Section 2.2 of the report.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report presents the capital expenditure and associated capital funding as at the end of Quarter 1 (June 2026). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery.

1.2The current approved capital budget is £87.356m (which includes the approved re-phasing of budgets from 2025/26) and the forecast outturn position is £77.526m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 2.4.

1.3A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5.

1.4A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.

Recommendations

It is recommended that Cabinet:

a. Note the capital forecast outturn position as shown in Table 1.

b. Note the forecast position as at 30 June 2026 for funding of the capital programme and reserve balances as reflected in Table 2.

c. Approve the virements set out in Section 2.2.

2. Capital Programme – Expenditure Forecasts Capital Budgets 11 August 2026 Agenda Item No. 7e

2.1The following table tracks approved changes to the original budget during the year (excluding fully funded virements).

£

Original Budget £57.266m

Re-phasing from 2025/26 £30.090m

Current Budget £87.356m

2.2It is recommended that the following virements be approved:

• To create income and expenditure budgets of £0.478m for the Warm Homes Local Government grant.

2.3The capital outturn position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies.

Table 1: Capital Outturn 2026/27 By Fund and Directorate

Re- Forecast Variance phasing (Under)/ Budget Outturn to of Over 2026/27 2026/27 Budget Capital Budget Schemes

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 548 548 0 0 0

Executive Director (Place) 2,702 2,781 80 0 80

Executive Director (Resident Services and Climate Change) 5,553 5,581 28 0 28

General Fund Total 8,803 8,910 108 0 108 Housing Revenue Account

Executive Director (Place) 19,162 9,224 (9,938) 8,720 (1,218) 11 August 2026 Agenda Item No. 7e

Executive Director (Res Services and Climate Change) 59,391 59,391 0 0 0 Housing Revenue Account Total 78,553 68,615 (9,938) 8,720 (1,218)

Grand TOTAL 87,356 77,526 (9,830) 8,720 (1,110)

2.3There is currently a requirement to re-phase £8.720m into 2027/28, split between funds as follows:

HRA £8.720m – re-phase budget into 2027/28 Total re-phasing - £8.720m

2.4Key forecast variances are outlined below:

General Fund:

2.4.1 There are no key forecast variances to report as at Quarter 1.

2.4.2 Overspends

There are a number of projects with small overspends which are listed below. All of these overspends will be funded by borrowing.

• Highview Shops (App A ref. 9) £0.014m adverse forecast variance

• Hatfield Town Centre Fees for Redevelopment (App A ref. 10) £0.004m adverse forecast variance

• Redevelopment of 1 and 3-9 Town Centre Hatfield (App A ref. 11) £0.008m adverse forecast variance

• Welwyn Garden City Town Centre North (App A ref. 12) £0.025m adverse forecast variance

• Link Drive Redevelopment (App A ref. 16) £0.023m adverse forecast variance

• Hatfield Town Centre Market Place (App A ref. 17) £0.006m adverse forecast variance

• Warm Homes LG (App A ref. 41) £0.0028m adverse forecast variance

Housing Revenue Account:

2.4.3 £2.000m rephasing – AHP Howlands House Redevelopment and Additional Units (App A ref. no 55)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 3 Appendix A: Quarter 1 Capital Monitor 2026-27Appendix 181 KB Download
PDF
QUARTER 1 CAPITAL MONITORING REPORT 2026/27Report 231 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AS
Councillor Astrid ScottCommittee Member, present
SB
Councillor Sandreni BonfanteVice-Chairman, present
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, expected
RB
Richard BakerOfficer, expected
HO
Helen O'KeeffeOfficer, expected
JH
Jenny HowellOfficer, expected
MS
Michael SherryCouncil Staff, expected
CC
Clare CadeSecretary, expected
RG
Councillor Rose GrewalChair, present
GM
Councillor Gemma MooreCommittee Member, present

All 15 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. QUARTER 1 CAPITAL MONITORING REPORT 2026/27This decision
  2. Quarter 1 Capital Budget Monitoring ReportNoted
  3. Quarter 3 capital budget monitoring report 2024-25Noted
  4. Quarter 3 Capital Budget Monitoring Report 2023-24Noted
  5. Capital budget monitoring report - quarter 2Decided
  6. Capital monitoring report 2022-23 - quarter 3Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies