Tawd Valley Park Project

Approved Executive 2 papers

Cabinet approved this item on Tuesday 10 January 2017. Below is the council's own wording, with the papers it was decided on.

Item73

Resolved

RESOLVED (A) That the allocation of up to £25,000 be approved to undertake the master plan process for the . (B) That delegated authority be given to the Director of Leisure and Wellbeing to take all steps necessary to engage consultants to deliver the Tawd Valley Park master plan.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To request funding to engage consultants to deliver a detailed master plan for the Council to progress the development of a programme of environmental and recreational improvements in Tawd Valley Park, Skelmersdale.

2.0RECOMMENDATIONS TO CABINET

2.1That the allocation of up to £25,000 be approved to undertake the master plan process for the Tawd Valley Park Project.

2.2That delegated authority be given to the Director of Leisure and Wellbeing to take all steps necessary to engage consultants to deliver the Tawd Valley Park master plan.

Background

3.1Tawd Valley Park is an area of public open space running along the line of the River Tawd from Skelmersdale Town Centre in a northerly direction for 2 km to the edge of the town at Ashurst. The park consists of open greenspace, woodlands, and meadows and is within easy access of most of the residential areas of Skelmersdale.

3.2The park offers the potential to be a valuable recreational and environmental asset to the local community, however, realising this potential will require careful and co-ordinated planning and investigation to establish environmental improvements that are required to improve the health of the park, and recreational facilities that are beneficial to the local community and are what local people want.

3.3In the previous park development project at Coronation Park in Ormskirk, the process used was to initially develop a master plan for the park, created from an extensive consultation and planning process. This process proved to be very successful and the results for Coronation Park have been excellent. It is felt therefore that taking the same approach for Tawd Valley Park would be the best way to take the project forward.

4.0CURRENT POSITION

4.1In November 2016 an officer working group was established consisting of West Lancashire Borough Council, Environment Agency, Groundwork CLM, Douglas Valley Catchment Programme and Lancashire County Council. This group will initially oversee a master plan process which will create clear and justified proposals for the project, will give an idea of the level of resources required to implement the scheme, and where these resources could be realised.

4.2The master plan would include:-

 Scoping Exercise - to establish facilities existing on and around the park.  Environmental Appraisal – identifying where environmental improvements/protection are required.  Options Appraisal – liaison with stakeholders to establish core improvements required.  Public Consultation – extensive programme to consult on core improvements and others proposals from the community.  Establishing Consensus – gathering all views and proposals and propose options for master plan.  Draft Master plan – compilation of consensus proposals into overall plan for further consultation.  Final Master plan – adoption of Master plan.  Design Proposals – detail designs for all elements of improvement works.  Costings – indicative prices for all improvement works.  Sources of Funding – identify feasible and available sources of funding.

4.3In addition to the master plan, and further into the process, the officer working group will seek funding required and will oversee the implementation of the project. It will also assist with developing the sustainability of the project through creating a means of on-going management of the park.

5.0PROPOSALS

5.1It is proposed that the Tawd Valley Park Working Group develop specifications for the Master plan contract and that the Council make revenue funds of up to £25,000 available to cover the cost of this contract. 6.0 SUSTAINABILITY IMPLICATIONS/COMMUNITY STRATEGY

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendixAppendix 303 KB Download
PDF
Tawd Valley Park ProjectReport 153 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 17 attended
IM
Councillor Ian MoranCommittee Member, present
YG
Councillor Yvonne GagenCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
JH
Councillor John HodsonCommittee Member, present
JP
Councillor Jenny PattersonCommittee Member, present
KW
Councillor Kevin WilkieCommittee Member, present
KW
Councillor Kevin WrightCommittee Member, present
CW
Councillor Chris WynnCommittee Member, present
SG
Sue GriffithsSecretary, present
KW
Kim WebberOfficer, present
TB
Terry BroderickOfficer, present
MT
Marc TaylorOfficer, present

All 17 on the meeting page

On this subject at West Lancashire

Search all
  1. Tawd Valley Park ProjectThis decision
  2. Future Direction for Tawd Valley Developments LtdApproved
  3. Independent Review of Tawd Valley Developments LtdAgreed
  4. Independent Review of Tawd Valley Developments LtdApproved
  5. 2019/1164/wl3 - tawd valley allotments, manfield, skelmersdaleApproved
  6. Tawd valley developments limited - officer director appointmentsAgreed

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open