A. That the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A to the report, be approved , subject to the reference to the "Playgrounds Improvements" scheme being amended to "Leisure Facilities" . B. That progress against the Revised Capital Programme at the mid-year point be noted.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To agree a Revised General Revenue Account (GRA) Capital Programme for 2019/2020 and provide an update on progress on capital schemes.
Recommendations
2.1That the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A, be approved.
2.2That progress against the Revised Capital Programme at the mid-year point be noted.
Background
3.1The Capital Programme is set on a three-year rolling basis and the Programmes for 2019/2020, 2020/2021 and 2021/2022 were approved by Council in February 2019. It is also standard practice for unused funding from the previous year to be slipped into the current year.
3.2In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.
3.3Members are kept informed of the financial position of the Capital Programme through monitoring reports. The Housing Public Sector programme is the subject of a separate report elsewhere on the agenda and has also been presented to Cabinet on the 5th November. This report concentrates on the GRA programme.
4.0REVISED CAPITAL PROGRAMME
4.1The original budget that was set for the 2019/20 financial year together with slippage from the previous financial year totals £4.749m. Taken together with the £0.783m of funding agreed at July 2019 Council means that the current budget total is £5.532m
4.2Heads of Service have reviewed their respective schemes and are now proposing that changes are made as a result of more up to date information that has become available. This review process has incorporated a number of considerations including: Re-profiling of schemes to match the anticipated timing of spending. Increasing expenditure budgets to reflect new and / or additional external funding Amending budgets to reflect anticipated levels of demand or new issues
4.3The proposed changes to the 2019/2020 Programme are analysed in Appendix A. This shows a net decrease of £614k largely due to Tawd Valley £155k, CCTV works £240k, and Burscough Sports Centre £386K being re-profiled into the next financial year and the inclusion of the approval for the purchase of Land at New Court Way in Ormskirk. The revised GRA Capital Programme totals £4.918m for 2019/2020 following these changes. The overall programme is analysed by service in Appendix B along with a summary of the revised capital resources available.
5.0CAPITAL EXPENDITURE
5.1Generally, capital schemes are profiled with relatively low spending compared to budget in the early part of the financial year with increased spending as the year progresses. This reflects the fact that many new schemes have considerable lead in times, for example, because of the need to undertake the tendering process and other factors. Other schemes are dependent on external partner funding and can only begin once their funding details have been finalised. Other related issues include contract retentions or contingencies that will only be spent some time after completion of the contract. 5.2 For the current year, £0.998m (20%) of expenditure has been incurred by the midyear. This is lower than 2018/19, mainly due to the Westec Site Development being undertaken last year. Comparisons to previous years’ programmes are shown in Table 1.
Table 1: GRA Capital Expenditure against Budgets Year Expenditure Budget % spend £m £m against Budget
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.