GRA Outturn 2025/26

Noted Committee 1 paper

AI summaryWest Lancashire Borough Council noted a 2025/26 revenue outturn needing only £80k from reserves, against a budgeted £865k draw, with a £3.791m medium-term gap still forecast to March 2029.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNet variance against budget is zero
Money£80k of £865k reservesMuch less than budgeted draw needed
What happens nextCouncil to note figuresReserve draw may flex during audit
Who it affectsCouncil budget positionBetter than set for 2025/26

What was decided

Council noted the draft revenue outturn for the 2025/26 General Revenue Account, with a balanced position against budget. Report 3.1, 5.1

Council noted that only £80k of the £865k budgeted use of reserves was actually required for 2025/26. Report 3.2, P84

Council noted that the amount drawn from reserves would be flexed during the audit if needed, to keep the General Revenue Account in balance. Report 3.3

Why

Council set a balanced 2025/26 budget in March 2025 using £0.865m of reserves, alongside savings and efficiency assumptions to be delivered in year.

A central corporate vacancy factor of £1,664k was exceeded, with £1,798k of salary budgets vired in, contributing to the favourable position. Report 5.2

What happens next

Draft outturn was already considered by Policy and Resources Committee before Council on 15 July 2026. Report 2.0, 2.1

Outturn figures may be adjusted during the external audit, with reserve draw flexed to keep the General Revenue Account in balance. Report 3.3, 8.0

A Medium-Term Financial Forecast approved in February 2026 still shows a £3.791m gap over the three years to March 2029. Report 4.3

The money

  • £865k Budgeted use of revenue reserves in 2025/26, approved by Council in March 2025 Report 3.2
  • £80k Actual use of reserves needed at outturn Report 3.2, P84
  • £993k Likely ongoing pressures continuing into 2026/27 Report 5.1, P14
  • £931k Potential ongoing savings opportunities Report 5.1, P14
  • £785k One-off or non-ongoing pressures in 2025/26 Report P15
  • £1,664k Approved corporate vacancy factor budget for 2025/26 Report 5.2
  • £1,798k Actual salary budgets vired to the vacancy factor at outturn Report 5.2
  • £3.791m Forecast medium-term gap to March 2029 in the February 2026 MTFF Report 4.3
  • £1.315m Identified gap for 2026/27 in the March 2025 MTFF Report 4.2
  • £0.687m Identified gap for 2027/28 in the March 2025 MTFF Report 4.2
  • £358k Adverse outturn variance for Housing Services Report 5.7, P49
  • £363k One-off pressure on the insurance fund in Legal and Democratic Services Report P54
  • £221k Planning income above budget in Planning and Regulatory Services Report P60
  • £190k Adverse variance for car parking in 2025/26 Report P76
  • £288k Favourable variance across the three leisure centres in 2025/26 Report P72
  • £998k Total cost of leisure provision to the Council in 2025/26 Report P72

Options considered

  • Chosen: Note the draft 2025/26 revenue outturn position. Standard reporting of actual income and expenditure against budget Report 3.1
  • Chosen: Use only £80k of reserves instead of the £865k budgeted. Better than expected in-year position reduces the need to draw on reserves Report 3.2, P84
  • Chosen: Flex reserve draw during audit if outturn changes. To keep the General Revenue Account in balance Report 3.3

Implications

  • Financial: Reserves are preserved: only £80k of a budgeted £865k draw is needed, strengthening the Council's reserves position. Report 3.2, P84
  • Financial: Around £993k of pressures are likely to continue into 2026/27, partly offset by £931k of potential ongoing savings, leaving a structural gap to address. Report 5.1, P14
  • Financial: Environmental Services faces continuing fleet and agency pressures, with a further £192k lease pressure expected in 2027/28. Report P31
  • Financial: Housing Services has ongoing software licence pressure of £200k and NNDR pressure of £157k that are not expected to ease in 2026/27. Report 5.7
  • Financial: Car parking income is £190k below budget, with a new model expected to address this, although timing delays may extend the pressure into 2026/27. Report P76
  • Staffing: The corporate vacancy factor was over-delivered at £1,798k against a £1,664k target, but several Directorates used agency staff above budget to maintain services. Report 5.2, P29
  • Risk: No formal risk assessment was required as the item is for information only, though ongoing pressures and a £3.791m medium-term gap remain unaddressed. Report 4.3, 8.1

Who and where

  • West Lancashire Borough Council as a whole, through the General Revenue Account Report 3.0, 5.0
  • Environmental Services directorate, with a £162k adverse outturn variance Report P37, P38
  • Finance and Corporate Resources directorate, with a £346k favourable variance Report P41, P42
  • Housing Services directorate, with a £358k adverse variance Report P48, P49
  • Planning and Regulatory Services directorate, with a £51k adverse variance Report P65, P66
  • Wellbeing and Place Services directorate, with a £165k favourable variance Report P77, P78
  • Council tax and NNDR payers, via general funding pressure of £104k Report P83

Timeline

  • March 2025: Council approved a balanced 2025/26 budget using £0.865m of reserves and the original MTFF showing further gaps in 2026/27 and 2027/28 Report 4.2
  • October 2025: Council delegated authority to officers to vire salary budgets to the corporate vacancy factor Report 4.4
  • February 2026: Updated MTFF approved showing a £3.791m medium-term gap to March 2029 Report 4.3
  • 15 July 2026: Council noted the draft revenue outturn and the reduced £80k reserve draw Report 2.1
  • After 15 July 2026: External audit of the accounts, with reserve draw flexed if needed to keep GRA in balance Report 3.3

Plain English for the jargon

  • GRA: General Revenue Account, the Council's main fund for day-to-day income and spending
  • Outturn: The actual income and expenditure for the year, compared with the budget
  • MTFF: Medium-Term Financial Forecast, a multi-year projection of the Council's finances
  • Vacancy factor: A central budget assuming some staff posts are unfilled, with salary budgets vired into it as posts become vacant
  • Virement: A transfer of budget from one budget line to another, here between salary budgets and the vacancy factor
  • EPR grant: Extended Producer Responsibility grant, paid to councils to cover costs of recycling packaging waste
  • LERG: Lancashire Economic Recovery Grant, awarded by Lancashire County Council
  • CIL: Community Infrastructure Levy, a charge on new development in the area
  • NNDR: National Non-Domestic Rates, business rates collected by the Council
  • ASG: Asylum Seekers Grant, central government funding for supporting asylum seekers
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27

Resolved

A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £865k budgeted use of reserves is required. C. That it be noted that outturn is not expected to change but if it does during audit, the amount drawn from reserves will be flexed so that the GRA remains in balance.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Wards affected

Purpose of the report

1.1To provide a summary of the draft General Revenue Account (GRA) for the 2025/26 financial year.

2.0RECOMMENDATIONS TO POLICY & RESOURCES COMMITTEE

2.1That the draft financial outturn position of the 2025/26 GRA be noted and any comments forwarded to the Chair of Policy and Resources Committee in advance of Council on 15th July 2026.

3.0RECOMMENDATIONS TO COUNCIL

3.1That the draft revenue outturn position of the 2025/26 GRA be noted.

3.2To note that only £80k of the £865k budgeted use of reserves is required.

3.3To note that outturn is not expected to change but if it does during audit, the amount drawn from reserves will be flexed so that the GRA remains in balance.

4.0BACKGROUND 4.1 In order to set a balanced budget for the 2025/26 GRA, Council approved in March 2025 the use of £0.865m of revenue reserves, this is after including substantial savings and efficiency assumptions that needed to be delivered in-year.

4.2The Medium-Term Financial Forecast (MTFF), which was also approved by Council in March 2025, identified a further gap of £1.315m for 2026/27 and £0.687m in 2027/28 without the use of revenue reserves.

4.3The MTFF approved in February 2026 showed an improved position for 2026/27 but a continuing medium-term gap of £3.791m for the three years to March 2029.

4.4In October 2025 Council approved delegated authority for officers to make budget virements between salary budgets and the centrally held corporate vacancy factor. Since approval a number of virements have taken place accordingly.

5.0GRA DRAFT REVENUE OUTTURN

5.1The table below summarises the analyses further down in the report in regard to ongoing pressures and savings opportunities. It shows that there is around £993k of pressure likely to continue and around £931k of potential savings opportunities.

£000's CCS ES F&CR HS LDS PRS WPS Other Res. Total Ongoing 0 580 0 357 0 0 56 0 993 pressures Ongoing savings (100) (100) (25) (52) (50) 0 (318) (286) (931)

One-off/not ongoing 0 0 0 119 363 406 225 104 785 2,002 pressures

One-off/not (428) (264) (296) (199) (299) (295) (323) (121) (2,225) ongoing savings

Other unders & (14) (54) (25) 133 (14) (60) 195 0 161 overs Outturn (542) 162 (346) 358 0 51 (165) (303) 785 0 variance

New pressures 192 tbc tbc

5.2Council approved a centrally held corporate vacancy factor budget of £1,664k in 2025/26 and then in October 2025, delegated authority to vire vacant pay budget to the vacancy factor budget. At outturn the vacancy factor target was surpassed with a total of £1,798k of pay budgets vired to the vacancy factor. The table below shows the respective contributions from each Directorate. It is worth noting that all but one Directorate still show a neutral or favourable variance on budgeted staff costs, though some services did also rely on agency staff beyond the budgeted amount. This will be captured in the overall variances further down in this report. Service Vacancy % original Revised Remaining Factor pay 2025/26 pay outturn pay vired budget budget £000's var £000's £000's Corporate & Customer Services (622) 13% 4,354 (152) Legal & Democratic Services (203) 12% 1,507 (130) Environmental Services (145) 2% 6,212 (120) Finance & Corporate Resources (192) 9% 1,959 (106) Housing Services (144) 10% 1,333 (70) Planning & Regulatory (389) 13% 2,609 (257) Wellbeing & Place (50) 1% 3,395 340 Chief Officers (53) 15% 307 0 Corporate vacancy factor 1,798 108% 134 (134) Total Pay Budget 0 21,810 (629)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GRA Outturn 2025/26Report 280 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

41 of 56 attended
JI
Councillor Janet IngmanMayor, present
JH
Councillor John HowardDeputy Mayor, present
JA
Councillor Judy AbbottCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
CR
Councillor Charles Robert BerryCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
AB
Councillor Aaron BodyCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
MJ
Councillor Michael John CromptonCommittee Member, present

All 56 on the meeting page

On this subject at West Lancashire

Search all
  1. GRA Outturn 2025/26This decision
  2. 2025/26 GRA Capital OutturnNoted
  3. GRA Outturn 2025/26Noted
  4. 2025/26 GRA Capital OutturnNoted
  5. GRA Draft Revenue Outturn 2024/25Noted
  6. 2024/25 GRA Capital OutturnNoted

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open
15 Jul 2026 HRA Outturn 2025/26 - Revenue & CapitalA. That the draft financial outturn position of the 2025/26 HRA and Housing Capital Programme be noted. B. That the a... Noted Open