2022/23 Quarter 2 GRA Capital Monitoring

Noted Committee 6 papers

Council noted this item on Wednesday 14 December 2022. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

A. That the revised Capital Programme for 2022/23 of £12.113m, be noted. B. That the re-profiling, virements and budget adjustments contained within the revised Appendix A, be approved. C. That the 2022/23 budget additions of £1.766m to the 2022/23 budget and £60k 2023/24 budget, to existing schemes within the approved programme, contained in the revised Appendix A, be approved. D. That the progress against the Revised Capital Programme at Quarter 2, be noted.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Purpose of report

1.1To provide the Revised General Revenue Account (GRA) Capital Programme for 2022/23 and an update on the progress of capital schemes at quarter 2.

2.0RECOMMENDATIONS TO BUDGET/COUNCIL PLAN COMMITTEE

2.1That the report be considered and any comments submitted to the Finance Portfolio Holder in advance of the Council meeting on 14 December 2022.

3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW & SCRUTINY COMMITTEE

3.1That the report be considered and any comments submitted to the Finance Portfolio Holder in advance of the Council meeting on 14 December 2022.

4.0RECOMMENDATIONS TO CABINET

4.1Note and endorse the revised Capital Programme for 2022/23 of £12.147m, including the re-profiling, virements and budget adjustments contained within Appendix A. 4.2 Note and endorse the 2022/23 budget additions of £1.800m to the 2022/23 budget and £296k 2023/24 budget, to existing schemes within the approved programme, contained in Appendix A for approval by Council in December 2022.

4.3Note the progress against the Revised Capital Programme at Quarter 2.

5.0RECOMMENDATIONS TO COUNCIL

5.1Note the revised Capital Programme for 2022/23 of £12.147m,

5.2Approve the re-profiling, virements and budget adjustments contained within Appendix A.

5.3Approve the 2022/23 budget additions of £1.800m to the 2022/23 budget and £296k 2023/24 budget, to existing schemes within the approved programme, contained in Appendix A.

5.4Note the progress against the Revised Capital Programme at Quarter 2.

Background

6.1The Capital Programme is set on a three-year rolling basis and the programme for 2022/2023 to 2024/2025 was approved by Council in February 2022.

6.2In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.

6.3Members are kept informed of the financial position of the Capital Programme through monitoring reports. The Housing Revenue Account programme is subject to a separate report, this report concentrates on the GRA Capital Programme.

7.0REVISED CAPITAL PROGRAMME

7.1The original 2022/23 Capital Programme of £6.033m was set at February 2022 Council, the re-profiling of £9.262m from 2021/22 into 2022/23 was further approved at July 2022 Council, so that the total Capital Programme for 2022/23 at quarter 1 totals £15.295m.

7.2The 2022/23 budget will increase by £1.800m due to the following schemes:  Disabled Facilities Grant of £1.444m  Moor Street Phase 2 has overspent by £84k at the end of Quarter 2 and is expected to spend another £136k which will be funded partly by HAZ (Heritage Asset Zone) and Lancashire County Council.  Cycle Trail funding has increased to £442k, the original funding was for £257k but an extra £185k has been secured via a grant.  Safer Streets will reduce to £39k which is funded by a grant.  Emergency works totalling £32k to be undertaken at the Chapel Gallery

The revised GRA Capital Programme at quarter 2 totals £17.095m of which £4.755m is funded by Capital Receipts following these changes.

7.3Heads of Service have undertaken a review of their respective schemes and are proposing changes and re-profiling into future years of the Capital Programme to match the anticipated timing of spending, that are a result of more up to date information becoming available.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2022-23 GRA Capital Q2 Monitoring Report AddendumAddendum 310 KB Download
PDF
2022-23 GRA Capital Q2 Monitoring Report App A REVISEDAppendix 534 KB Download
PDF
2022/23 Quarter 2 GRA Capital MonitoringReport 74 KB DownloadRead as text
PDF
Exec Min GRA CapitalReport 193 KB Download
PDF
GRA Capital Cabinet MinReport 182 KB Download
PDF
Minute of the Budget CP Cttee GRA CapReport 180 KB Download

At this meeting

Whole meeting

Who was there

53 of 84 attended
AL
Alan LeicesterOfficer, expected
AS
Adam SpicerCouncil Staff, expected
TB
Terry BonnerCouncil Staff, expected
JS
Julie StamperOfficer, expected
SP
Simon PeetCouncil Staff, expected
MM
Councillor Mrs Marilyn WestleyMayor, present
KM
Councillor Kate MitchellDeputy Mayor, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
MM
Councillor Mrs May BlakeCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present

All 84 on the meeting page

On this subject at West Lancashire

Search all
  1. 2022/23 Quarter 2 GRA Capital MonitoringThis decision
  2. 2022/23 Quarter 2 GRA Revenue MonitoringNoted
  3. 2022/23 Quarter 2 GRA Revenue MonitoringNoted
  4. 2022/23 Quarter 2 GRA Capital MonitoringNoted
  5. 22/23 Quarter 2 GRA Revenue MonitoringNoted
  6. 22/23 Quarter 2 GRA Capital MonitoringNoted

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open