DEMOLITION OF FLAT BLOCKS IN BLYTHEWOOD & BANKSBARN TO FACILITATE PHASE 2 OF DIGMOOR REVIVAL SCHEME

Approved Committee 3 papers

Council approved this item on Wednesday 28 February 2024. Below is the council's own wording, with the papers it was decided on.

Item82

Resolved

A. That having regard to the decision of Cabinet, the development, as outlined in the report be approved and the proposal be funded from the £9m budget which has previously been set aside for this purpose. B. That the Head of Housing be given delegated authority to take all steps necessary to implement the development outlined within the report , to include, but not be limited to instructing TVD Ltd, obtaining planning permission, entering into grant funding arrangements with Homes England, contracts with design and build businesses, demolition of existing properties, relocation of tenants and repurchase of leaseholds. C. That the Head of Housing, following discussion with the relevant Portfolio Holder, be given delegated authority to, as a last resort, use the power of compulsory purchase. D. That the Head of Housing be given delegated authority to make ongoing adjustments to the delivery of the scheme, following discussions with the relevant Portfolio Holder .
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Purpose of the report

1.1To seek approval to proceed with the development of Digmoor area of Skelmersdale in accordance with the Digmoor Revival Scheme. Approval is sought to demolish the existing blocks of flats in Blythewood and Banksbarn, shown in the current site plan attached at Appendix 1 and thereafter take all steps necessary to develop the site. This demolition will facilitate the development of 45 new Council homes for affordable/social rent. In order to facilitate this development, approval is required from both Council and Cabinet on various aspects of the proposal.

1.2The report is being brought forward to this meeting to avoid any delay in the project. The impact of a delay would be the loss of significant funding from Homes England if the project is not completed by the end of the current Homes England Affordable Housing Programme, in March 2026.

2.0RECOMMENDATIONS TO CABINET

2.1That the proposed development, details of which are contained within this report,(including the demolition of the flat blocks in Blythewood and Banksbarn) be approved subject to Council approval where appropriate.

2.2That the Head of Housing following discussion with the relevant Portfolio Holder be given delegated authority to take all steps necessary (subject to Council approval where necessary) to implement the development outlined within this report. This will include, but not be limited to, instructing TVD, obtaining planning permission, entering into grant funding arrangements with Homes England, contracts with design and build businesses, demolition of existing properties, relocation of tenants and repurchase of leaseholds.

2.3That the Head of Housing, following discussion with the relevant Portfolio Holder, be given delegated authority to, as a last resort, use the power of compulsory purchase.

2.4That the Head of Housing be given delegated authority to make on going adjustments to the delivery of the scheme following discussions with the relevant Portfolio Holder.

2.5In respect of matters reserved to Council the report be noted and any agreed comments be referred to Council for consideration.

3.0RECOMMENDATIONS TO COUNCIL

3.1That having regard to the comments from Cabinet the development as outlined in this report be approved. The proposal to be funded from the £9m budget which has previously been set aside for this purpose.

3.2That the Head of Housing be given delegated authority to take all steps necessary to implement the development outlined within this report. This will include, but not be limited to instructing TVD Ltd, obtaining planning permission, entering into grant funding arrangements with Homes England, contracts with design and build businesses, demolition of existing properties, relocation of tenants and repurchase of leaseholds.

3.3That the Head of Housing, following discussion with the relevant Portfolio Holder, be given delegated authority to, as a last resort, use the power of compulsory purchase.

3.4That the Head of Housing be given delegated authority to make on going adjustments to the delivery of the scheme following discussions with the relevant Portfolio Holder.

Background

4.1Due to the age and condition of the flat blocks on Blythewood and Banksbarn, officers have been working closely with TVD to consider their long-term future.

4.2The existing properties are approximately 50 years old and are constructed using the REEMA Conclad concrete panel system. As such they are difficult to improve, poorly insulated, and prone to defects. The flats have outdated electric heating systems, poor layouts, and the communal areas are in need of refurbishment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Digmoor Revival DemolitionAppendix 2 133 KB Download
PDF
DEMOLITION OF FLAT BLOCKS IN BLYTHEWOOD & BANKSBARN TO FACILITATE PHASE 2 OF DIGMOOR REVIVAL SCHEMEReport 2 MB DownloadRead as text
PDF
Flat Blocks Cabinet MinReport 61 KB Download

At this meeting

Whole meeting

Who was there

41 of 78 attended
MN
Councillor Maureen NixonMayor, present
JA
Councillor Julian Antoni FinchDeputy Mayor, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
DD
Councillor Darren DanielsCommittee Member, present
TD
Councillor Terence DevineCommittee Member, apologies
GD
Councillor Gareth DowlingCommittee Member, present

All 78 on the meeting page

On this subject at West Lancashire

Search all
  1. DEMOLITION OF FLAT BLOCKS IN BLYTHEWOOD & BANKSBARN TO FACILITATE PHASE 2 OF DIGMOOR REVIVAL SCHEMEThis decision
  2. Demolition of flat blocks in blythewood & banksbarn to facilitate phase 2 of digmoor revival schemeApproved

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open