Resolved
AGREED: ( A) That the revised Capital Programme, including the budget adjustments contained within Appendix A of the report be noted. (B) That the progress against the Revised Capital Programme at Quarter 1 be noted.
Policy & Resources Committee agreed this item on Tuesday 24 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED: ( A) That the revised Capital Programme, including the budget adjustments contained within Appendix A of the report be noted. (B) That the progress against the Revised Capital Programme at Quarter 1 be noted.
1.1.1 To note the Revised General Revenue Account (GRA) Capital Programme for 2024/25 and provide an update on progress on capital schemes.
2.0RECOMMENDATIONS FOR P&R COMMITTEE
2.1That the revised Capital Programme, including the budget adjustments contained within Appendix A, be noted.
2.2That progress against the Revised Capital Programme at Quarter 1 be noted.
3.1The Capital Programme is set on a three-year rolling basis and the Programmes for 2024/2025, 2025/2026 and 2026/2027 were approved by Council in February 2024. 3.2 In accordance with best practice, the Capital Programme is subject to revision during the year to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.
3.3Members are kept informed of the financial position of the Capital Programme through monitoring reports. The Housing Public Sector programme is the subject of a separate report elsewhere on the agenda and will be also presented to this Policy and Resources Committee. This report concentrates on the GRA programme.
4.0REVISED CAPITAL PROGRAMME
4.1The original Capital Programme that was set for the 2024/2025 financial year together with underspends brought forward from the previous financial year totals £12.744m of which £931k has been spent to date as shown in Appendix A - 2024/2025 Revised Capital Programme Spend to Date Against Budget.
4.2The £160k for Resurfacing of Blaguegate Lane has now been returned to the Clinical Commissioning Group and has therefore been removed from the Capital Programme.
4.3The £47k grant that was expected for Play Strategy Improvements is unlikely to be received and has also therefore been removed from the Capital Programme.
5.0CAPITAL EXPENDITURE
5.1Generally, capital schemes are profiled with relatively low spending compared to budget in the early part of the financial year with increased spending as the year progresses. This reflects the fact that many new schemes have considerable lead in times. Other schemes are dependent on external partner funding and can only begin once their funding details have been finalised. Other related issues include contract retentions or contingencies that will only be spent some time after completion of the contract.
5.2For the current year, £58k (0.99%) of expenditure from borrowing has been incurred by the end of Quarter 1.
5.3It was agreed at Cabinet in November 2020 that the £247k for Affordable Housing that was originally agreed in 2011 be utilised by Tawd Valley Developments. This was because the arrangement with Regenda Housing was ended. 6.0 CAPITAL RESOURCES
6.1There are sufficient resources identified to fund the 2024/2025 Revised Capital Programme as shown in Appendix A.
6.2The target for useable capital receipts (including the affordable housing element) to be generated from Council House sales in the year is £0.960m from 60 sales. By the end of quarter 1, 11 sales had been completed with a sales value of £460.7k.
7.0SUSTAINABILITY IMPLICATIONS
7.1The Capital Programme includes schemes that the Council plans to implement to enhance service delivery and assets. The Capital Programme also achieves the objectives of the Prudential Code for Capital Finance in Local Authorities by ensuring capital investment plans are affordable, prudent, and sustainable. This report provides an updated position on project plans and shows progress against them.
8.0RISK ASSESSMENT
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2024-25 Q1 GRA Capital ReportReport | 184 KB | DownloadRead as text |
PDF |
Appendix A20242025RevisedCapitalProgrammeSpendtoDateAgainstBudgetAppendix A20242025RevisedCapitalProgrammeSpendtoDateAgainstBudget | 236 KB | Download |
Follow Policy & Resources Committee at West Lancashire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | MinutesThat the minutes of the meeting held on Wednesday, 25 March 2026 be received as a correct record and signed by the Ch... | Decided | Open |
| 25 Jun 2026 | Terms of ReferenceThat the Terms of Reference be noted. | Noted | Open |
| 25 Jun 2026 | Confirmation of Procedural MattersA. That the Working Groups for 2026/27 be noted. B. That Cllr Howard be appointed Vice-Chair of the Member Developmen... | Noted | Open |
| 25 Jun 2026 | Public SpeakingA request to speak in relation to the item, Community Infrastructure Levy (CIL) Funding Programme 2025 – Becconsall H... | Noted | Open |
| 25 Jun 2026 | Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewThat in accordance with Option 1 of the report, CIL funding is not allocated towards Becconsall Heritage Park. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.