West Lancashire Borough Council
Council, Thursday 26 February 2026 at 7.30pm

* Capital Strategy & Programme 2026-29

Agreed Committee 4 papers

AI summaryWest Lancashire Borough Council agrees the Capital Strategy and Programme for 2026/27, with £1.858m of recurring and continuation schemes, £3.711m of slippage, and £25.972m of new general fund investment to 2028/29.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedfor the 2026/27 financial year
Money£25.972m new investment to 2028/29plus £1.858m recurring and £3.711m slippage in 2026/27
What happens nextReviewed and updated annuallyto reflect challenges facing the council and residents
Who it affectsCouncil capital investment and residentsincluding housing, environment and place services

What was decided

The Council agreed the Capital Strategy and Programme for 2026/27. Report 3.1

The Policy and Resources Committee had been asked to note the same strategy, with this report revised since that meeting. Report 2.1, 2.0

Why

The Prudential Code for Capital Finance in Local Authorities requires councils to prepare a Capital Strategy, and this document has been produced in accordance with the latest guidance.

The strategy provides the framework for capital financing and treasury management, and links to the Medium-Term Financial Strategy, Treasury Management Strategy and Investment Strategy. Report 1.1

Key priorities supported include greener energy initiatives, cycleways and waste management measures to address fly tipping.

What happens next

The Strategy will be reviewed annually and updated to take account of challenges facing the Council and residents of West Lancashire.

Preliminary discussions with Lancashire County Council suggest a further £400k may be required for Local Government Reorganisation transformation, in addition to the £600k already allocated. Report P14

The money

  • £25.972m Total new general fund capital expenditure to 2028/29 Report 7.1
  • £1.858m Recurring and continuation of schemes in 2026/27
  • £3.711m Slippage rephased from 2025/26 into 2026/27
  • £5.502m Business Unit Scheme at Junction 4, 2025/26 new general fund spend Report P11, 7.1
  • £94.0m Forecast increase in Capital Financing Requirement over next 3 years Report P15
  • £27.1m Capital resources available at end of 2024/25 Report P14
  • £13.0m Total commitments against those capital resources Report P14
  • £885k Capital receipts reallocated by Council on 15 October 2025 Report P14

Implications

  • Financial: Consideration should be given to the affordability of borrowing due to the significant increase in capital budget compared to previous years. Report 11.3
  • Financial: Section 106, CIL and other grant funding have terms and conditions which must be met before these resources can be applied to alternative schemes. Report 11.2
  • Financial: A £94.0m increase in the Capital Financing Requirement over the next 3 years will increase borrowing, with higher interest charges and minimum revenue provision once assets are finalised. Report P15
  • Risk: All potential risks are logged on the Ideagen risk platform, with mitigations put in place and monitored as part of the capital programme. Report 8.0
  • Risk: Schemes reliant on external contributions are not started until funding is secured, and the capital receipts position is scrutinised regularly. Report 12.1
  • Staffing: The Capital and Treasury Programmes are managed by professionally qualified accountants, including a Chartered Public Financial Accountant as Investment Project Manager. Report 9.1
  • Equalities: The decision does not have any direct impact on members of the public, employees, elected members or stakeholders, so no Equality Impact Assessment is required. Report P30
  • Climate: The programme supports greener energy initiatives, cycleways and waste management measures to deter and address fly tipping, with further green energy initiatives in development.

Who and where

  • Residents of West Lancashire Report 13.1
  • Council service areas including Housing Services, Environmental Services and Wellbeing and Place Report P8
  • Council partners

Timeline

  • February 2024: HRA 30-year capital budget approved by Members Report 7.4
  • April 2025: Skelmersdale Town Centre Masterplan approved at Council Report P14
  • 15 October 2025: Council approved reallocation of capital resources, releasing £885k Report P14
  • 2025/26: Forecast capital programme year including £5.502m of new general fund spend Report 7.1
  • 2026/27: Capital Strategy and Programme year now agreed Report 3.1
  • 2026/27 to 2028/29: Forecast minimum revenue provision of £0.5m, £0.9m and £0.9m for general fund Report P15
  • Annually: Strategy will be reviewed and updated

Plain English for the jargon

  • GRA: General Fund, the main council fund for non-housing services
  • HRA: Housing Revenue Account, ring-fenced account for council housing
  • MTFS: Medium-Term Financial Strategy
  • CIL: Community Infrastructure Levy, a charge on new development
  • S106: Section 106 planning obligation contributions from developers
  • PWLB: Public Works Loan Board, a government lender to local authorities
  • CFR: Capital Financing Requirement, the council's underlying borrowing need
  • LGR: Local Government Reorganisation
  • FUCR: Flexible Use of Capital Receipts, allowing receipts to fund transformation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item109

Resolved

That the Capital Strategy and Programme for 2026/27 be agreed.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Purpose of report

1.1To set the framework for capital financing and treasury management operations for the next financial year.

2.0RECOMMENDATION FOR POLICY AND RESOURCES COMMITTEE

2.1That the Capital Strategy and Programme for 2026/27 be noted.

3.0RECOMMENDATION FOR COUNCIL

3.1That the Capital Strategy and Programme for 2026/27 be agreed. 4.0 INTRODUCTION 4.1 The Prudential Code for Capital Finance in Local Authorities (updated December 2021) sets out the requirement for councils to prepare a Capital Strategy, and this document has been produced in accordance with the latest guidance. 4.2 This strategy updates the capital strategy for both the general fund (GRA programme) and for the HRA and sets out the direction for the Council’s capital programme management and investment decisions in support of our outcomes. It sets out the principles for prioritising our capital investments, the governance, scrutiny and assurance process. It also provides an overview of the asset management process and approach to risk management. 4.3 The effective management of capital resources is an integral aspect in the delivery of the Council’s corporate objectives. The Capital Strategy provides the framework for this delivery and ensures there is a focused approach to our capital investment. The Strategy maintains a strong link to its key strategy documents notably the Medium-Term Financial Strategy (MTFS), Treasury Management Strategy and the Investment strategy. The Strategy will be reviewed annually and updated to take account of the challenges facing the Council and the residents of West Lancashire.

5.0BACKGROUND 5.1 The Council formulates its capital investment programme as part of its annual budget setting process. The aim is to ensure that the programme is affordable, deliverable and in line with the Council's priorities for expenditure. 5.2 The key priorities continue to be supported by our capital investment programme, for instance through our greener energy initiatives and the development of cycleways. We are working towards a cleaner environment with waste management initiatives to deter and address fly tipping. 5.3 Although not currently in the strategy, there is work underway to look at the long- term leisure service needs and further green energy initiatives.

6.0OBJECTIVES 6.1 To support the MTFS by ensuring that capital investment decisions are not taken in isolation from revenue spending with specific emphasis on delivering future savings and income streams capable of supporting the revenue budget. 6.2 To ensure that the right capital assets are available and are fit for purpose for the Council and partners to support the Council's priorities. 7.0 CAPITAL PROGRAMME The programme in 2026/27 includes £1.858m recurring and continuation of schemes (details are included in appendix 1). In addition to this, £3.711m has been identified as slippage, being expenditure originally expected to be incurred in 2025/26 but now rephased into the 2026/27 programme. This is mainly due to delays in implementation of a number of schemes across Environmental Services and Wellbeing and Place, funded primarily from grant and external contributions, together with resources earmarked for the implementation and transitional costs associated with the Local Government Review.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
* Capital Strategy & Programme 2026-29Report 174 KB DownloadRead as text
PDF
Amdt CAPITAL STRATEGY AND PROGRAMME 2026Report 52 KB Download
PDF
for Capital Strategy & Programme 2026-29Appendix 1 81 KB Download
PDF
GRA Capital Minute of the Policy and resourcesReport 50 KB Download

At this meeting

Whole meeting

Who was there

44 of 57 attended
AM
Councillor Anne Mary FennellMayor, present
SP
Councillor Suresh PatelDeputy Mayor, present
JA
Councillor Judy AbbottCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
TD
Councillor Terence DevineCommittee Member, present
GD
Councillor Gareth DowlingCommittee Member, present

All 57 on the meeting page

On this subject at West Lancashire

Search all
  1. * Capital Strategy & Programme 2026-29This decision
  2. Capital Strategy & Programme 2026-29Noted
  3. GRA Capital Strategy & Programme 2025/26 to 2027/28Agreed
  4. Capital Finance & Treasury Management Strategy 25-26Noted
  5. Capital Strategy & Programme 2025-28Agreed
  6. Capital Finance & Treasury Management Strategy 25-26Noted

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open