CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
West Lancashire Borough Council
Policy & Resources Committee, Thursday 25 June 2026 at 7.00pm

GRA Outturn 2025/26

Noted Committee 1 paper

AI summaryWest Lancashire's Policy and Resources Committee noted the draft 2025/26 General Revenue Account outturn. Only £80k of the £865k budgeted use of reserves was needed, with the GRA remaining in balance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedComments invited before Council on 15 July 2026
MoneyNot stated
What happens nextCouncil on 15 July 2026Comments to Chair beforehand
Who it affectsWest Lancashire residents and servicesCouncil-wide revenue budget 2025/26

What was decided

The Committee noted the draft 2025/26 General Revenue Account outturn position and invited comments to be sent to the Chair before Council on 15 July 2026. Report 2.1

Members noted that only £80k of the £865k budgeted use of reserves was required, with any further changes during audit to be absorbed by reserves so the GRA stays in balance. Report 3.2, 3.3

Why

In March 2025 Council set a balanced 2025/26 budget using £0.865m of revenue reserves, after including substantial in-year savings and efficiency assumptions.

Officers reported around £993k of ongoing pressures alongside about £931k of potential ongoing savings, and several large one-off variances, leaving the GRA in balance overall. Report 5.1, P14, P15, P16, P17

The Medium Term Financial Forecast approved in March 2025 identified further gaps of £1.315m for 2026/27 and £0.687m for 2027/28, and a February 2026 update showed a £3.791m gap across the three years to March 2029. Report 4.2, 4.3

What happens next

Comments on the draft outturn are to be sent to the Chair of Policy and Resources Committee before Council meets on 15 July 2026. Report 2.1

Council will be asked to note the draft 2025/26 GRA revenue outturn position. Report 3.1

If audit changes the outturn, the amount drawn from reserves will be flexed so the GRA remains in balance. Report 3.3

The money

  • £0.865m Revenue reserves approved to balance the 2025/26 GRA in March 2025
  • £1.315m Forecast budget gap for 2026/27 identified in March 2025 Report 4.2
  • £0.687m Forecast budget gap for 2027/28 identified in March 2025 Report 4.2
  • £3.791m Medium term gap across the three years to March 2029, per February 2026 update Report 4.3
  • £1,664k Centrally held corporate vacancy factor budget for 2025/26 Report 5.2
  • £1,798k Pay budgets vired to the corporate vacancy factor at outturn, 108% of target Report 5.2
  • £993k Estimated ongoing service pressures carried into future years Report 5.1, P14
  • £931k Estimated ongoing savings opportunities identified Report 5.1, P14
  • £785k Net one-off, not ongoing, outturn pressure across services Report 5.1, P15, P17
  • £80k Actual draw from reserves needed, against a £865k budget Report 3.2, P83, P84

Options considered

  • Chosen: Note the draft 2025/26 GRA outturn position. Recommended by the Director of Finance and Corporate Resources; report is for information Report 2.1, 3.1, 8.1
  • Rejected: Do not note the report or refer it elsewhere Report 2.1

Implications

  • Financial: Only £80k of the £865k budgeted use of reserves is needed, but a £1.315m gap remains for 2026/27 and a £3.791m medium term gap to March 2029. Report 3.2, 4.2, 4.3
  • Financial: Around £993k of ongoing pressures are flagged for future years, against about £931k of identified ongoing savings opportunities. Report 5.1, P14
  • Staffing: The £1,664k corporate vacancy factor was exceeded, with £1,798k vired in; agency staff overspent in Environmental Services by £223k after EPR funding, mainly in waste collection and recycling. Report 5.2, P29
  • Risk: Environmental Services faces ongoing fleet hire pressure of £162k and wear and tear pressure of £89k, with a further £192k lease pressure expected in 2027/28. Report P31
  • Equalities: No Equality Impact Assessment required; decision has no direct impact on members of the public, employees, elected members or stakeholders. Report P99
  • Climate: No significant sustainability impacts identified. Report 6.1
  • Other: No health and wellbeing implications arise from this report. Report 9.1

Who and where

  • West Lancashire Borough Council as a whole, through its General Revenue Account Report 1.1, 2.1
  • Environmental Services, facing ongoing fleet, agency and pest or green waste income pressures Report 5.5, P29, P31, P32
  • Housing Services, with software licence and NNDR pressures, and tenants using the GRA furnishing service Report 5.7, P47
  • Wellbeing and Leisure services, including leisure centre users and Beacon café users Report 5.10, P75
  • Planning applicants, since planning income volatility affects the outturn Report P60, P61
  • Council taxpayers, given ongoing budget gaps identified in the Medium Term Financial Forecast Report 4.2, 4.3

Timeline

  • March 2025: Council approved 2025/26 budget using £0.865m of revenue reserves and the original Medium Term Financial Forecast Report 4.2
  • October 2025: Council approved delegated authority for officers to vire pay budgets into the corporate vacancy factor Report 4.4
  • February 2026: Updated Medium Term Financial Forecast showed a £3.791m gap to March 2029 Report 4.3
  • 25 June 2026: Policy and Resources Committee noted the draft 2025/26 GRA outturn Report 2.1
  • 15 July 2026: Council scheduled to consider the draft 2025/26 revenue outturn Report 2.1, 3.1

Plain English for the jargon

  • GRA: General Revenue Account, the council's day to day spending budget funded mainly by council tax, business rates and grants
  • Outturn: The final, actual spending and income position at the end of the financial year, compared with the budget
  • MTFF: Medium Term Financial Forecast, the council's multi-year projection of income, spending and budget gaps
  • Vacancy factor: A centrally held saving budget that assumes a percentage of staff posts will be unfilled during the year
  • Virement: Movement of budget from one budget heading to another, approved by members or under delegated authority
  • EPR: Extended Producer Responsibility, a grant regime that funds recycling and waste work carried out by councils on behalf of packaging producers
  • NNDR: National Non Domestic Rates, the business rates paid on commercial properties such as council offices
  • CIL: Community Infrastructure Levy, a charge on certain new developments, partly used to fund administration
  • ASG: Asylum Seekers Grant, central government funding for work with people seeking asylum
  • LGR: Local Government Reorganisation, structural changes to how councils are arranged
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item170

Resolved

That the draft financial outturn position of the 2025/26 GRA be noted and any comments forwarded to the Chairperson of Policy and Resources Committee in advance of Council on 15th July 2026.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Policy & Resources Committee

Wards affected

Purpose of the report

1.1To provide a summary of the draft General Revenue Account (GRA) for the 2025/26 financial year.

2.0RECOMMENDATIONS TO POLICY & RESOURCES COMMITTEE

2.1That the draft financial outturn position of the 2025/26 GRA be noted and any comments forwarded to the Chair of Policy and Resources Committee in advance of Council on 15th July 2026.

3.0RECOMMENDATIONS TO COUNCIL

3.1That the draft revenue outturn position of the 2025/26 GRA be noted.

3.2To note that only £80k of the £865k budgeted use of reserves is required.

3.3To note that outturn is not expected to change but if it does during audit, the amount drawn from reserves will be flexed so that the GRA remains in balance.

4.0BACKGROUND 4.1 In order to set a balanced budget for the 2025/26 GRA, Council approved in March 2025 the use of £0.865m of revenue reserves, this is after including substantial savings and efficiency assumptions that needed to be delivered in-year.

4.2The Medium-Term Financial Forecast (MTFF), which was also approved by Council in March 2025, identified a further gap of £1.315m for 2026/27 and £0.687m in 2027/28 without the use of revenue reserves.

4.3The MTFF approved in February 2026 showed an improved position for 2026/27 but a continuing medium-term gap of £3.791m for the three years to March 2029.

4.4In October 2025 Council approved delegated authority for officers to make budget virements between salary budgets and the centrally held corporate vacancy factor. Since approval a number of virements have taken place accordingly.

5.0GRA DRAFT REVENUE OUTTURN

5.1The table below summarises the analyses further down in the report in regard to ongoing pressures and savings opportunities. It shows that there is around £993k of pressure likely to continue and around £931k of potential savings opportunities.

£000's CCS ES F&CR HS LDS PRS WPS Other Res. Total Ongoing 0 580 0 357 0 0 56 0 993 pressures Ongoing savings (100) (100) (25) (52) (50) 0 (318) (286) (931)

One-off/not ongoing 0 0 0 119 363 406 225 104 785 2,002 pressures

One-off/not (428) (264) (296) (199) (299) (295) (323) (121) (2,225) ongoing savings

Other unders & (14) (54) (25) 133 (14) (60) 195 0 161 overs Outturn (542) 162 (346) 358 0 51 (165) (303) 785 0 variance

New pressures 192 tbc tbc

5.2Council approved a centrally held corporate vacancy factor budget of £1,664k in 2025/26 and then in October 2025, delegated authority to vire vacant pay budget to the vacancy factor budget. At outturn the vacancy factor target was surpassed with a total of £1,798k of pay budgets vired to the vacancy factor. The table below shows the respective contributions from each Directorate. It is worth noting that all but one Directorate still show a neutral or favourable variance on budgeted staff costs, though some services did also rely on agency staff beyond the budgeted amount. This will be captured in the overall variances further down in this report. Service Vacancy % original Revised Remaining Factor pay 2025/26 pay outturn pay vired budget budget £000's var £000's £000's Corporate & Customer Services (622) 13% 4,354 (152) Legal & Democratic Services (203) 12% 1,507 (130) Environmental Services (145) 2% 6,212 (120) Finance & Corporate Resources (192) 9% 1,959 (106) Housing Services (144) 10% 1,333 (70) Planning & Regulatory (389) 13% 2,609 (257) Wellbeing & Place (50) 1% 3,395 340 Chief Officers (53) 15% 307 0 Corporate vacancy factor 1,798 108% 134 (134) Total Pay Budget 0 21,810 (629)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GRA Outturn 2025/26Report 280 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 38 attended
DW
Councillor David WhittingtonChairperson, present
AO
Councillor Adrian OwensVice-Chairperson, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, apologies
AB
Councillor Aaron BodyCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
TD
Councillor Thomas de FreitasCommittee Member, apologies
PD
Councillor Paul David HeskethCommittee Member, present
RL
Councillor Richard LeeCommittee Member, present
MS
Councillor Melissa S ParlourCommittee Member, present
IR
Councillor Ian RigbyCommittee Member, present
JH
Councillor John HowardCommittee Member, in attendance, virtual

All 38 on the meeting page

On this subject at West Lancashire

Search all
  1. GRA Outturn 2025/26This decision
  2. GRA Outturn 2025/26Noted
  3. 2025/26 GRA Capital OutturnNoted
  4. 2025/26 GRA Capital OutturnNoted
  5. GRA Draft Revenue Outturn 2024/25Noted
  6. 2024/25 GRA Capital OutturnNoted

More from West Lancashire Policy & Resources Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 MinutesThat the minutes of the meeting held on Wednesday, 25 March 2026 be received as a correct record and signed by the Ch... Decided Open
25 Jun 2026 Terms of ReferenceThat the Terms of Reference be noted. Noted Open
25 Jun 2026 Confirmation of Procedural MattersA. That the Working Groups for 2026/27 be noted. B. That Cllr Howard be appointed Vice-Chair of the Member Developmen... Noted Open
25 Jun 2026 Public SpeakingA request to speak in relation to the item, Community Infrastructure Levy (CIL) Funding Programme 2025 – Becconsall H... Noted Open
25 Jun 2026 Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewThat in accordance with Option 1 of the report, CIL funding is not allocated towards Becconsall Heritage Park. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies