Resolved
(1) The achievements since 8 May 2017 meeting of the Transport Delivery Committee be noted; (2) Progress of deliverables under the 2017-18 Capital Programme be noted; and (3) Variations from the baseline programme where indicated be noted.
Transport Delivery Committee noted this item on Monday 10 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The achievements since 8 May 2017 meeting of the Transport Delivery Committee be noted; (2) Progress of deliverables under the 2017-18 Capital Programme be noted; and (3) Variations from the baseline programme where indicated be noted.
2.1The 2017/2018 Capital Programme was approved by WMCA Board as part of the wider Transport Plan on 17th March 2017.
2.2The ITB allocation for 2017/2018 is fully utilised on continuing current (2016/2017) committed schemes and in attempting to manage the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment, in order to endeavour to maintain a steady state of asset condition across the estate.
2.3The Capital Programme in 2017/2018 will be a one year transition period by bringing existing schemes to a conclusion and will allow TfWM to re-focus subsequent programmes towards supporting Asset Management, Network Resilience and Capacity Enhancement projects from April 2018, or sooner should funding become available.
2.4Attached to this report (Appendix 1) is the detailed monitoring report for the 2017/2018 TfWM Capital programme outlining these deliverables, indicating the baseline date (endorsed through March report) with an indication of the current forecast date with a RAG indicator.
3.0Achievements
3.1The following elements within the 2017/18 Capital Programme have been completed during May and June 2017:
Cradley Heath Interchange – The contractor completed the resurfacing works at the interchange, with successful handover to the bus station management team. 2016/2017 Managing Shorter Trips (MST) – Supported LSTF/Black Country Consortium in reporting completion of deliverables by Canal River Trust, Dudley and Walsall MBCs. As a result of the successful project management, TfWM has been asked to continue a second package of MST works totalling £4.25 million across 2017/2018 and 2018/2019 (pending funding approval). Infilling works to Walsall Cutting – The project is now complete. Network Wide Cycling Facilities at Rail Stations - Cycle facilities now installed at Tile Hill, Sutton, Widney Manor and Smethwick Galton Bridge Rail Stations. This concludes the implementation of this scheme.
Page 2 of 8 [PUBLIC]
4.0Variations to Baseline Programme
4.1The following schemes have had variations to their established baseline programmes:
Strategic Economic Plan Schemes:
Birmingham City Centre One Station – project currently on hold while consideration is given to wider connectivity improvements that are being developed for Curzon Street and Moor St as part of HS2. Discussions are ongoing with Birmingham City Council and HS2 Ltd.
Wolverhampton City Centre Shelters – implementation will follow once City of Wolverhampton Council complete their pedestrianisation works. The expected date for installation of the shelters is March 2018.
5.1The detailed financial aspects of the TfWM 2017/2018 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the final year position in financial terms is, however, attached to this report as Appendix 2.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Delivery Monitoring ReportReport | 171 KB | DownloadRead as text |
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Feb 2023 | Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... | Decided | Open |
| 6 Feb 2023 | Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... | Noted | Open |
| 6 Feb 2023 | Minutes - 9 January 2023Agreed as a correct record. | Agreed | Open |
| 6 Feb 2023 | Matters ArisingThe committee noted matters arising from the minutes. | Noted | Open |
| 6 Feb 2023 | Forward PlanA plan of items to be reported to future meetings was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.