Transport Capital Investment Programme

Approved Committee 1 paper

AI summaryWMCA Board approves framework for £2.4bn Transport for City Regions capital programme, including £200m over-programming and £85m for Metro lifecycle costs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRosewell Review endorsed, over-programming approved
Money£2.4bn TCR allocationOver 2027/28 to 2031/32, including £2.2bn new capital
What happens nextFurther paper to January 2026 BoardConsolidates Rosewell Review outcomes and final allocations
Who it affectsWest Midlands transport projects and councilsImpacts highways, Metro, bus and rail schemes region-wide

What was decided

The Board endorsed the Rosewell Review approach for independently assessing the West Midlands capital infrastructure programme. Report P1

The Board approved a recommended approach to building a project pipeline linked to the West Midlands Growth Plan and Local Transport Plan, and approved principles allowing 10% capital-to-revenue transfer and use of TCR funds for Metro lifecycle costs. Report P4, P5

The Board approved over-programming the TCR resources by £200m, a marginal reduction on the previous CRSTS over-programming value, subject to risk monitoring. Report P8, 7.4

Why

The Integrated Settlement allows Mayoral Strategic Authorities to switch up to 10% of capital to revenue, and using this would help protect the Transport function's operating position. Report 2.29, 7.5

Funding Metro lifecycle maintenance from TCR avoids creating an upwards pressure on the Transport Levy, with provisional five-year costs assessed at £85m. Report 2.30, 7.5

Over-programming mirrors the approach taken under CRSTS to avoid curtailing delivery, where £227m of CRSTS resources were over-programmed. Report 2.28, 7.4

What happens next

A further paper will come to the WMCA Board on 16 January 2026 consolidating Rosewell Review outcomes, including highways maintenance, LNIPs, deferred CRSTS projects and short and long term TCR priorities. Report P9

A new Outline Business Case and updated designs for Witton and Aston stations will go through appropriate governance in June 2026. Report 2.40

Public consultation on the Area Based Implementation Plans is proposed for summer 2026 ahead of WMLTP5 adoption. Report 2.25

The money

  • £2.4bn West Midlands TCR allocation over 2027/28 to 2031/32, including £80m revenue Report 2.11, 7.1
  • £2.2bn New capital within the TCR allocation Report 2.11, 7.1
  • £200m Approved over-programming of TCR resources Report P8, 7.4
  • £227m Over-programming previously undertaken during the CRSTS period Report 2.28, 7.4
  • £85m Provisional Metro lifecycle maintenance costs over the five-year TCR period Report 2.30, 7.5
  • £50m Allocation for Arden Cross, subject to business case Report P56, 2.27
  • £44.2m Birmingham Eastside Metro commitment Report P57, 2.27
  • £56.8m Bus Depot Acquisition envelope Report P58, 2.27
  • £400m TCR funding ringfenced for transport improvements linked to Birmingham Sports Quarter Report 2.34
  • £25m Budget envelope sought for Witton and Aston station improvements Report 2.36
  • £263m Total value of deferred CRSTS projects to be considered for inclusion in TCR Report 2.33
  • £262.2m Schemes deferred in July 2024 and May 2025 with in-principle agreement for TCR consideration Report 2.41
  • £159m Projected growth in carriageway backlog over next 5 years at current funding Report 2.31
  • £24m Current annual highways maintenance allocation baseline Report 2.31
  • £19.5m Current annual Local Network Improvement Plan allocation Report 2.32
  • £15.6 billion Total TCR funding confirmed in Spending Review 2025 for 9 Mayoral Strategic Authorities Report 2.11

Options considered

  • Rejected: Do nothing: continue developing capital programme in isolation from wider strategic drivers. Lacks alignment with Growth Plan, Rosewell Review outputs and Local Transport Functional Strategy Report 3.1, 4.1
  • Chosen: Develop programme against West Midlands Growth Plan, Rosewell Review approach and Local Transport Functional Strategy. Provides evidence-based approach enabling wider objectives and Integrated Settlement Outcomes Framework alignment Report 3.1, 4.1, 4.2
  • Chosen: Use full 10% capital-to-revenue transfer to support transport operating position. Helps protect operating position of the Transport function, with requirement to evidence need annually Report 2.29, 7.5
  • Chosen: Charge Metro Lifecycle Maintenance costs to the TCR programme. Avoids creating an upwards Transport Levy pressure Report 2.30, 7.5

Implications

  • Financial: Over-programming of £200m carries risk requiring monitoring throughout the TCR period; influenced by certainty about transport capital resources beyond 2032. Report P8, 7.4
  • Legal: Schemes over £200m or requiring integration with the strategic national transport network will need Department for Transport agreement; those meeting criteria must join the Government Major Projects Portfolio. Report 2.16
  • Equalities: Individual projects will be subject to equality assessments in line with WMCA policy; a Health and Equity Impacts Assessment will follow completion of the Rosewell Review. Report 9.3
  • Climate: Interventions can reduce emissions by supporting shift to cleaner zero emission vehicles and travel behaviour change; capital schemes themselves may create carbon emissions requiring management strategies. Report P87
  • Financial: Highways maintenance proposed to increase by 100% and LNIPs by 30% annually, subject to Rosewell Review validation and engagement with Highway Authorities and Local Authorities. Report 2.31, 2.32, P66
  • Risk: No significant new risks are introduced by the approach set out in the report; risks are managed in accordance with WMCA and Local Authority processes. Report 10.1
  • Other: Up to 10% of total TCR allocation may be used for local highway capacity schemes unless exceptional Ministerial approval is granted; this cap excludes renewal and safety schemes. Report 2.15

Who and where

  • West Midlands residents and businesses benefiting from transport investment Report 2.1, P85
  • Constituent local authorities as highway and planning authorities Report P89, 11.1
  • Aston Villa Football Club and visitors to Villa Park, including UEFA Euro 2028 attendees Report 2.35, 2.36, 2.38
  • Knighthead Capital Management and Birmingham Sports Quarter development area Report 2.34
  • Transport for West Midlands (TfWM) operating the Metro and other services Report 2.30, P89
  • Highway Authorities receiving uplifted maintenance and LNIP allocations Report 2.31, 2.32
  • Network Rail, Great British Railways and National Highways as infrastructure partners Report P89

Timeline

  • 2025/26: TCR funding to be managed under Integrated Settlement rules from April 2026 Report 7.2
  • November 2025: Rosewell Review outputs on existing capital investments and TCR allocation recommendations expected Report P20, P21
  • January 2026: Rosewell Review systems and processes review expected; further paper to WMCA Board on 16 January 2026 Report P22, P9
  • June 2026: Outline Business Case and updated designs for Witton and Aston stations to be taken through governance Report 2.40
  • Summer 2026: Proposed public consultation on Area Based Implementation Plans Report 2.25
  • 2028: UEFA European Football Championships hosted with Aston Villa hosting 4 matches Report 2.38, P73
  • 2032: End of TCR funding period (March 2032) Report 2.33, 2.11
  • March 2027: CRSTS funding must be fully committed Report 2.18
  • 2027/28 to 2031/32: TCR funding period Report 2.11

Plain English for the jargon

  • TCR: Transport for City Regions, the funding settlement replacing CRSTS, covering 2027/28 to 2031/32
  • CRSTS: City Region Sustainable Transport Settlement, the predecessor capital funding programme
  • MSA: Mayoral Strategic Authority, one of nine bodies eligible for TCR funding
  • WMLTP5: West Midlands Local Transport Plan 5
  • LNIP: Local Network Improvement Plan, a minor works funding programme for local authorities
  • MTFP: Medium Term Financial Plan
  • AVFC: Aston Villa Football Club
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

(1) The approach adopted as part of the ‘Rosewell Review’ for undertaking an independent review of the West Midlands capital infrastructure programme was endorsed. (2) The Transport for City Regions allocation for the West Midlands and its associated guidance was noted. (3) The commitments made by the WMCA Board to date which affected the available Transport for City Regions resources were noted. (4) The recommended approach to developing a project pipeline which built on the West Midlands Growth Plan and the Local Transport Plan Core Strategy was approved. (5) The principles relating to use of the Transport for City Regions resources required to safeguard the sustainability of the transport function over the Medium Term Financial Plan period relating to capital to revenue transfers and the funding of metro lifecycle costs were approved. (6) Whilst each scheme featuring in the Transport for City Regions programme would do so on merit, it was noted that the following types of schemes would be initially evaluated for inclusion: (a) schemes where significant development activity had been funded by the City Region Sustainable Transport Settlement. (b) schemes deferred from the City Region Sustainable Transport Settlement programme to the Transport for City Regions period. (7) The intention to increase allocations for highways maintenance and the Local Network Improvement Plan, subject to the independent validation currently underway, was noted. (8) The decision to over-programme the Transport for City Regions resources by £200m (a marginal reduction on the City Region Sustainable Transport Settlement value) was approved, subject to the risks associated with this being carefully monitored and reported during the Transport for City Regions period. (9) It was noted that a further paper would be considered by the WMCA Board at its meeting on 16 January 2026 which consolidated the outcomes of the ‘Rosewell Review’, taking into account engagement with local authorities on an agreed way forward for highways maintenance, Local Network Improvement Plans, City Region Sustainable Transport Settlement-deferred projects, Transport for City Regions short term priorities and its medium to long term approach.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to WMCA Board

Recommendations

(1) Endorse the approach adopted as part of the Rosewell Review for undertaking an independent review of the West Midlands capital infrastructure programme.

(2) Note the Transport for City Regions (TCR) allocation for the West Midlands and its associated guidance.

(3) Note the commitments made by WMCA Board to date which affect the available TCR resources.

(4) Approve the recommended approach to developing a project pipeline which builds on West Midlands Growth Plan and the Local Transport Plan Core Strategy.

(5) Approve the principles relating to use of TCR required to safeguard the sustainability of the Transport function over the Medium-Term Financial Plan (MTFP) period relating to capital to revenue transfers and the funding of Metro lifecycle costs.

(6) Note that whilst each scheme featuring in the TCR programme will do so on merit, the following types of schemes will be initially evaluated for inclusion:

a. Schemes where significant development activity has been funded by CRSTS. b. Schemes deferred from the CRSTS programme to the TCR period. (7) Note the intention to increase allocations for Highways Maintenance and Local Network Improvement Plan, subject to the independent validation currently underway.

(8) Approve the decision to over-programme the TCR resources by £200m (a marginal reduction on the CRSTS value) subject to the risks associated with this being carefully monitored and reported during the TCR period.

(9) Note that a further paper will be presented to WMCA Board in January which consolidates the outcomes of the Rosewell Review. This will take into account engagement with Local Authorities on an agreed way forward for Highways Maintenance, Local Network Improvement Plans, CRSTS deferred projects, TCR short term priorities and medium to long term approach.

Voting Requirements The Mayor, and separately, at least two-thirds of the members appointed by the constituent councils, in attendance in the meeting room and indicating their preference are required to vote in favour of any recommendation/proposition for it to become decision of the board [‘Requirement B’ as specified in paragraph 18.9(b) of the constitution].

Executive summary

1.1This report sets out the approach for developing a future West Midlands transport capital programme as part of Transport for City Regions (TCR) funding which supports the West Midlands Growth Plan and West Midlands Local Transport Plan 5 (WMLTP5).

1.2Agreement is sought from WMCA Board on the approach adopted through the Rosewell Review, the principles of prioritisation for the TCR funding and the commitments for projects, highways maintenance and Local Network Improvement Plans (LNIPs).

2. Matters for Consideration

Background

2.1The West Midlands is on the cusp of a significant economic resurgence. It has the foundations for success: a young, diverse population; it’s connectivity, not least with London; it’s scale with the second biggest city in the UK – Birmingham; and with a burgeoning innovation ecosystem driven by high-performing universities, catapults and cutting-edge businesses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Capital Investment ProgrammeReport 298 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 29 attended
RP
Richard ParkerChair, expected
ST
Councillor Sharon ThompsonVice-Chair, expected
AA
Councillor Adrian AndrewCommittee Member, expected
MB
Councillor Mike BirdCommittee Member, expected
PB
Councillor Paul BradleyCommittee Member, expected
KC
Councillor Kerrie CarmichaelCommittee Member, expected
LC
Councillor Lee CarterNon-Constituent Member, expected
JC
Councillor John CottonCommittee Member, expected
IC
Councillor Ian CourtsCommittee Member, expected
ID
Councillor Ian DavisonNon-Constituent Member, expected
CD
Councillor Carol DeanNon-Constituent Member, expected
GD
Councillor George DugginsCommittee Member, expected

All 29 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Transport Capital Investment ProgrammeThis decision
  2. Transport Capital Delivery ProgrammesAgreed
  3. Transport for West Midlands Capital Spending Pressures and Programme UpdateApproved
  4. Transport Programme Capital Governance Review (TfWM)Noted
  5. Transport for West Midlands Capital PressuresNoted
  6. Transport for West Midlands Capital PressuresNoted

More from West Midlands Combined Authority WMCA Board

All decisions
MeetingDecisionOutcome
17 Jul 2026 Apologies for AbsenceCecilie Booth (Audit, Risk & Assurance Committee), Councillor Paul Bradley (Dudley), Councillor George Duggins (Coven... Decided Open
17 Jul 2026 Chair's RemarksThe Chair provided a summary of the recent delivery and activity that he had been involved in. Decided Open
17 Jul 2026 Minutes - 12 June 2026Agreed as a correct record. Agreed Open
17 Jul 2026 Constitution Review(1) The proposed amendments to parts A and B of the constitution, as amended, were approved. (2) Authority was delega... Approved Open
17 Jul 2026 Rosewell Review Phase 2 / Transport for City Regions(1) The work undertaken as part of phase 2 of the Rosewell Review, including its proposals regarding how the Transpor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies