Date 11 June 2018 Report title Metro Operations Business Report Accountable Director Phil Hewitt, Metro Programme Director
Email: [email removed] Tel: 0121 214 7254 Accountable Sophie Allison, Metro Operations Manager Employee Email: [email removed] Tel: 0121 214 7347
Report to be/has been Councillor Roger Horton – Lead Member Rail and Metro considered by
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended to note the report:
1.0Purpose
1.1To report on matters relating to the performance, operation and delivery of Metro services in the West Midlands.
Page 1 of 8 [PUBLIC]
This report includes:
Section A Operational Performance 2.0 2.1 Patronage 2.2 Weekend Patronage Growth 2.3 Punctuality 2.4 Reliability 2.5 Customer Service Representative Coverage
Section B Partnership Update 3.0 3.1 Metro Passenger Panel 3.2 Future Events and Planned Works
Section C Tram Passenger Survey - Satisfaction Results 4.0 4.1 Tram Passenger Survey
Section D Operator Business Updates 5.0 6.1 NXMM update
Section E Financial Comments 6.0
Page 2 of 8 [PUBLIC]
2.0Section A – Operational Performance.
2.1Metro Patronage
2.1A Chart 1 shows the monthly patronage from May 2017 to April 2018. Patronage has recovered as anticipated following Bilston Road closure and was just 2% lower in April 2018 when compared with April 2017. This is a significant improvement on March 2018 where patronage was 12% lower against March 2017. It was expected that it would take approximately 3 months for patronage to recover from Bilston Rd closure and this has been achieved.
Chart 1
2.2Weekend Patronage Growth
2.2A Chart 2 shows patronage on Midland Metro at weekends. When comparing the period May 2017 to April 2018 with the equivalent period a year prior, patronage on average has shown a decrease of 15% on Saturday and 13% on Sunday. When comparing the month of April 2018 with April 2017, the change has been a decrease on Saturday of 23% and on Sunday a decrease of 11%.
Page 3 of 8 [PUBLIC]
Chart 2
2.3Punctuality
2.3A This measure details how many journeys have been operated in accordance with the published timetable at the departure and termination points. Chart 3 shows monthly punctuality performance from May 2017 to April 2018. Please note that incidents which affected service and are outside of the operator’s control have not been removed from the figures presented, thus the figures demonstrate the real passenger experience.
2.3B Punctuality started to decline during November and December 2017 but has since improved to 93% in April 2018, closer to the target 98%. From the 7% shortfall 1% is attributed to driver availability and 0.5% due to tram availability. The main shortfall therefore is due to general late running to timetable.
Chart 3
Page 4 of 8 [PUBLIC]
2.4Reliability
2.4A This measure shows the percentage of kilometres operated against the scheduled timetable. Chart 4 shows performance over the last 12 months. The target is 98% and due to staff and driver availability this has fallen slightly below this target.
Chart 4
2.5CSR Coverage
2.5A Chart 5 shows the number of journeys that were completed with a Customer Service Representative (CSR) on board over the last 12 month period. Where journeys have been completed without a CSR, this is largely attributed to staff absence due to short and long term sickness.
Page 5 of 8 [PUBLIC]
Chart 5
3.0Section B – Metro Partnership Update
3.1Metro Passenger Panel
3.1A Metro Passenger Panel last met on 15 March 2018 and items discussed included an operational update, on board energy storage system (OESS) including the programme of work to equip the current fleet following the completion of endurance and maximum range testing of tram 18 and a progress update for the extension projects.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Metro Operations Business Update ReportReport | 218 KB | DownloadRead as text |
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Feb 2023 | Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... | Decided | Open |
| 6 Feb 2023 | Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... | Noted | Open |
| 6 Feb 2023 | Minutes - 9 January 2023Agreed as a correct record. | Agreed | Open |
| 6 Feb 2023 | Matters ArisingThe committee noted matters arising from the minutes. | Noted | Open |
| 6 Feb 2023 | Forward PlanA plan of items to be reported to future meetings was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.