That the recent progress with developing the West Midlands Stations Alliance concept between Network Rail, West Midlands Railway and the West Midlands Rail partnership of local authorities be noted; 2. That progress with the pilot stations master planning work which has been undertaken at local stations on the Stour Valley and Chase Lines be noted and 3. That the proposed next steps of the West Midlands Stations Alliance and Station Master Planning workstreams be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report Title West Midlands Stations Alliance Update
Accountable Director Malcolm Holmes, Director of Rail
Accountable employee(s) Toby Rackliff, Strategic Lead, Rail Policy (West Midlands Rail) Report has been reviewed Councillor Roger Horton – Lead Member Rail and Metro by
Recommendation(s) for action or decision:
The Transport Delivery Committee is recommended:
1. To note the recent progress with developing the West Midlands Stations Alliance concept between Network Rail, West Midlands Railway and the West Midlands Rail partnership of local authorities;
2. To note the progress with the Pilot Stations master Planning work which has been undertan at local stations on the Stour Valley and Chase Lines.;
3. To note the proposed next steps for the West Midlands Stations Alliance and Station Master Planning workstream;
1.0Purpose
1.1The purpose of this report is to provide an update regarding recent progress with developing the West Midlands Stations Alliance concept between Network Rail, West Midlands Railway and the West Midlands Rail partnership of local authorities (which includes WMCA and its constituent authroities).
2.0Background: What are the issues we are trying address
2.1The West Midlands Stations Alliance (WMSA) concept seeks to address issues of:
lack of co-ordination between the various parties responsible for station assets insufficient incentives to invest in significant station enhancements
Page 1 of 4 2.2 With a couple of exceptions Network Rail own all stations in the West Midlands and are funded by Government to maintain these station assets in their 2004 condition.
2.3Similarly, as the Station Facility Owner, the operator is only contractually obliged to maintain the status quo. Whilst there is a “Residual Value” mechanism in place which seeks to incentivise the train operator to invest in longer term station improvements, the application of this mechanism has arguably been driven by largely commercial considerations.
2.4This asset management approach does not generally consider the passenger experience nor recognise the full potential role that stations could play as community assets.
2.5Transport for West Midlands, which, uniquely, is responsible for the majority of station car parks in the metropolitan area, has consistently invested heavily in these assets over recent decades. However, such investment has not generally been co-ordinated with station maintenance and renewal work undertaken by either Network Rail or the Train Operator.
2.6It has therefore become clear that the current asset management processes do not facilitate a coherent long term plan to enhance stations (or even undertake maintenance on a co-ordinated basis) as the incentives are fractured and unclear.
2.7Any substantial enhancements to station facilities are therefore generally only progressed on a case by case basis and require wholly separate funding and approvals processes from that of asset maintenance.
3.0Why we have adopted the West Midlands Stations Alliance (WMSA) Concept
3.1Prior to deciding on a “Stations Alliance” approach the West Midlands Rail (WMR) partnership had considered around 20 other different models of station ownership and management.
3.2However, it was eventually concluded that it would be possible to achieve WMR’s objectives for stations, within the current station asset management and financial arrangements, alongside the establishment of a formal tri-partite agreement between WMR, Network Rail and the Train Operator.
Page 2 of 4 3.3 This Alliance approach, crucially, leaves the operational responsibilities and risks of station asset management with Network Rail and the train operator.
3.4TfWM and individual WMCA authroities are not a formal members of WMSA, but have close involvement with the alliance through WMR’s membership.
4.0WMSA Vision, Objectives and Governance
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.