That the achievements since the November 2018 meeting of the Transport Delivery Committee be noted; 2. That progress of deliverables under 2018/19 Capital Programme be noted and 3. That the variation to the baseline programme in respect of Snow Hill Third Access which has incurred delays to the programme due to contractual arrangements being formalise be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2018/2019 Capital Programme was approved by WMCA Board as part of the wider Transport Plan on 9th February 2018
2.2The ITB allocation for 2018/2019 has been fully utilised on continuing committed schemes and in attempting to manage the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment, in order to endeavour to maintain a steady state of asset condition across the estate.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the October 2018 TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
3.0Achievements
3.1The following elements within the 2018/19 Capital Programme have been completed during November and December 2018.
Dudley Interchange – outline planning permission submitted Snow Hill 3rd Access – non-intrusive survey work is complete West Midlands Bike Share Scheme – Contract signed with Next Bike
5.0Variations to Baseline Programme
5.1Snow Hill 3rd Access has incurred delays to the programme due to contractual arrangements being formalised.
Financial implications
6.1The detailed financial aspects of the TfWM 2018/2019 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the position in financial terms is, however, attached to this report as Appendix 3.
Legal implications
7.1There are no direct legal implications arising from the recommendations set out in this report. However, legal and procurement will support, as necessary, any deliverables that may arise throughout 2018/2019.
Page 2 of 8 8.0 Equalities implications
8.1There are no equality implications arising from the recommendations set out in this report. However, Anna Sirmoglou will support as project requires any deliverables within the 2018/2019 capital programme
8.0Inclusive Growth Implications
8.1The transport interventions sets out within this report form an integral part of an efficient and resilient transport system which support inclusive growth objectives by:
Enabling wider labour markets, Providing access to skills, education and training Supporting regeneration and place making initiatives
9.0Geographical Area of Report’s Implications
9.1The report deals with schemes to be funded through the Transforming Cities Fund which are located within the Metropolitan Area, but will serve to improve connectivity across the wider WMCA through improved links on key corridors.
10.0Other Implications
10.1No implications
Appendices
11.1APPENDIX 1 – Progress of Deliverables against 2018/19 Baseline Programme 11.2 APPENDIX 2 – Financial Summary
12.0Glossary of Terms
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.