(1) The current draft Internal Audit Plan for 2019/20 be noted. (2) The final draft Internal Audit Plan be submitted for approval at committee on the 15 April 2019. (3) A clear timescale for completion of the internal audits to be included within the plan for 2019/20. (4) Internal audits completed summary in advance of committee be circulated to members.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1Internal audit is a statutory requirement for all Local Authorities. The audit service provided to the WMCA is in accordance with the Local Government Act (1972), the Accounts and Audit Regulations Act and the Public Sector Internal Audit Standards.
3. Wider WMCA Implications
3.1There are no implications.
Financial implications
4.1There are no implications.
Legal implications
5.1There are no implications.
Page 2 of 17 This report is PUBLIC [NOT PROTECTIVELY MARKED]
Equalities implications
6.1There are no implications.
7. Other Implications
7.1There are no implications.
8. Schedule of Background Papers
8.1None.
Appendices
9.1None
Page 3 of 17 This report is PUBLIC [NOT PROTECTIVELY MARKED]
Draft Internal Audit Plan – 2019-2020
Page 4 of 17 This report is PUBLIC [NOT PROTECTIVELY MARKED]
Delivered by City of Wolverhampton Council - Audit Services
Index
A quick guide to the audit and assurance planning process Glossary of Terms Introduction Assessing the effectiveness of risk management and governance Assessing the effectiveness of the system of control The assessment of assurance needs methodology The assessment of assurance needs Developing an internal audit plan Considerations required of the Audit, Risk and Assurance Committee and senior WMCA management How the internal audit service will be delivered The internal audit plan
Page 5 of 17 This report is PUBLIC [NOT PROTECTIVELY MARKED]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Risk & Assurance Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.