Investment Portfolio Governance Audit Update 2018

Noted Finance 1 paper

Audit, Risk & Assurance Committee noted this item on Monday 14 January 2019. Below is the council's own wording, with the papers it was decided on.

Item128

Resolved

(1) That the progress made to date against the original actions in the Internal Audit Report be noted. (2) That the timescales for implementation of the enhanced Governance & Assurance Framework be noted. (3) That an update be provided to committee on the amber actions and accountability in June 2019.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Audit, Risk & Assurance Committee

Audit, Risk & Assurance Committee Date 14 January 2019

Report title Investment Portfolio Governance Audit Update 2018 Accountable Chief Deborah Cadman, OBE Executive Chief Executive of the WMCA Email: [email removed] Tel: (0121) 214 7200 Accountable Julia Goldsworthy Employee Director of Strategy Email: [email removed] Tel: (0121) 214 7941 Report to be Audit, Risk & Assurance Committee considered by

Recommendation(s) for action or decision:

Audit, Risk and Assurance Committee is recommended to:

(1) Note the progress made to date against the original actions in the Internal Audit Report [section 3].

(2) Note timescales for implementation of the enhanced Governance & Assurance Framework [section 2.4].

Page 1 of 10 1. Purpose of Report

1.1This report has been produced to provide in flight assurance to the Audit, Risk & Assurance Committee that progress has been made against the original recommendations in the Internal Audit review of Investment Portfolio Governance Arrangements for Programme Approval & Appraisal.

2. Update of Governance and Assurance Framework Review and Timeframes

2.1The development of actions to address key audit findings as well as the internal process to strengthen assurance on the Investment Programme has been supported by the commissioning of Arcadis to support development of the Governance and Assurance Framework.

2.2Engagement with internal and external stakeholders, has identified WMCA’s requirement to provide a greater focus on portfolio delivery and benefits realisation with processes and systems that make sure there is:

 Smooth facilitation of Delivery Organisation (Local Authorities, LEPs, TFWM etc.) projects as they progress through the governance and assurance process  Clarity on business case development and how these progress through approval boards  A clear and consistent evidence based evaluation and approvals process  A supportive portfolio management office and performance management system  Increased efficiency through the process  Robust governance and assurance on approvals and delivery  Early visibility of progress, issues and problems.

2.3Since the internal audit and the review and recommendations provided by Arcadis, WMCA PMO have developed a robust plan for an enhanced approach and methodology for governance and assurance of the Investment Portfolio. These enhancements build and expand on the existing assurance framework with the intention of demonstrating that the benefits and outcomes of investments are planned, managed, monitored and realised, and evidenced to the UK government.

2.4The WMCA PMO plan to develop and implement an enhanced Governance and Assurance Framework was endorsed by the Investment Board on 10th December 2018. The enhanced framework will require approval at Investment Board level before being presented to MHCLG for final sign off in August 2019.

2.5The tables provided in Section 3 of this report provide a summary of progress against the Internal Audit actions in February 2018.

Page 2 of 10 3. Summary of Progress against Internal Audit Actions

Quick Wins

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Investment Portfolio Governance Audit Update 2018Report 176 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 25 attended
DL
David LaneChair, present
AA
Councillor Adam AstonCommittee Member, present
TB
Councillor Tom Baker-PriceCommittee Member, present
RB
Councillor Richard BrownCommittee Member, present
KC
Councillor Kerrie CarmichaelCommittee Member, apologies, sent representative
CC
Councillor Craig CollingswoodCommittee Member, present
SF
Sean FarnellCommittee Member, present
MG
Councillor Michael GoughCommittee Member, apologies
JK
Councillor John KraujalisCommittee Member, expected
JO
Councillor John O'SheaCommittee Member, present
AP
Councillor Alexander PhillipsCommittee Member, present
JT
Councillor June TandyCommittee Member, present

All 25 on the meeting page

More from West Midlands Combined Authority Audit, Risk & Assurance Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Terms of Reference - To NoteResolved that: The Terms of Reference be noted. Noted Open
14 Jul 2026 West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Resolved that: The update be noted. Noted Open
14 Jul 2026 Annual Review Letter 2025/26Resolved that: The Local Government and Social Care Ombudsman’s annual review letter for 2025/26 be noted. Noted Open
14 Jul 2026 Business Continuity Programme Update(1) That a reduction in overall programme risk and that Business Continuity Resilience, Response and Recovery (BCRRR)... Noted Open
14 Jul 2026 Consideration of Private Internal Audit Reports(1) The contents of the latest Internal Audit Update Report and progress against delivery of the 2025/26 Internal Aud... Noted Open