That the achievements since the March 2019 meeting of the Transport Delivery Committee be noted ; 2. That progress of deliverables and outturn of the 2018/19 Capital Programme be noted and 3. That the variations from the baseline which relate to TBT Platinum Route RTI equipment and Bradley Lane Park and Ride be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2018/19 Capital Programme was approved by WMCA Board as part of the wider Transport Plan on 9th February 2018.
2.2The ITB allocation for 2018/2019 has been fully utilised on continuing committed schemes and in attempting to manage the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment, in order to endeavour to maintain a steady state of asset condition across the estate.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
3.02018/19 Achievement Summary
3.1The following elements within the 2018/19 Capital Programme have been completed.
Transforming Bus Travel TBT Wolverhampton City Centre Shelters TBT Birmingham City Centre Shelter Design Optimisation Positively Reviewing Bus Lanes
4.1TBT Platinum Route RTI Equipment Upgrades – delay incurred due to manufacturer scaling back operation. New supplier appointed however there is a fourteen week lead in time.
4.2Bradley Lane Park & Ride – As a result of the contractor going into administration in March 2019 a new procurement strategy has had to be developed, in order to appoint a new
Page 2 of 9 [PUBLIC]
contractor to complete Phase 1 and undertake Phase 2 works. It is anticipated that there will be a 6 month delay from the baseline in completing the project.
Financial implications
5.1The detailed financial aspects of the TfWM 2018/2019 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the position in financial terms is, however, attached to this report as Appendix 2.
6.0Schemes in Development & Delivery
6.1The Capital Programme for 2018/19 has included a number of rolling programmes and longer term deliverables. These are set out below:
Transforming Bus Travel Digital Advertising Panel Rollout TBT Platinum Route RTI Equipment Upgrade Network Wide P&R Lighting Enhancements Transforming Bus Travel
Asset Management Network Wide Bus Station Refurbishment Phase 1
Project Delivery Bradley Lane Metro Park & Ride
Project Development Programme Cycle Counters Dudley Interchange Network Wide Park & Ride Expansion Developments, Sandwell & Dudley, Tipton Tamebridge Parkway, Whitlocks End & A34 Sprint Corridor. Perry Barr Station & Bus Interchange Snow Hill 3rd Access Network Wide Cycling Programme 3A (NWCP) Making the KRN (Key Route Network) Safer University Station West Midlands Bike Share Scheme
7.02019/20 Capital Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.