That the achievements since the 9 September meeting of the Transport Delivery Committee be noted; 2. That progress of deliverables and the outturn of the 2019/20 Capital Programme be noted and 3. That the variation to the baseline programme with regards to Longbridge Connectivity Project in Appendix 1 of the report be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2019/20 Capital Programme was approved by WMCA Board as part of the wider Transport Plan in February 2019.
2.2The ITB allocation for 2019/2020 has been fully utilised on continuing committed schemes and in attempting to manage the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment, in order to endeavour to maintain a steady state of asset condition across the estate.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
3.0Achievements
3.1The following elements within the 2019/20 Capital Programme have been completed during September and October 2019:
Longbridge Connectivity Package – below ground construction activities are complete, thereby minimising risks to project delivery as the scheme moves into winter working. New bike stands installed into Coventry Pool Meadow and Wolverhampton Bus Stations Planning Application submitted for University Station and Perry Barr Station. West Midlands Bike Share is out to tender (Competitive Dialogue)
4.0Variations to Baseline Programme
4.1We have included the Longbridge Connectivity Project in Appendix 1.
Financial implications
5.1The detailed financial aspects of the TfWM 2019/2020 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the position in financial terms is, however, attached to this report as Appendix 2.
Page 2 of 8 [PUBLIC]
Legal implications
6.1There are no direct legal implications arising from the recommendations set out in this report. However, legal and procurement will support, as necessary, any deliverables that may arise throughout 2019/20.
Equalities implications
7.1There are no equality implications arising from the recommendations set out in this report. However, Anna Sirmoglou will support as project requires any deliverables within the 2019/2020 capital programme.
8.0Inclusive Growth Implications
8.1The transport interventions sets out within this report form an integral part of an efficient and resilient transport system which support inclusive growth objectives by:
Enabling wider labour markets, Providing access to skills, education and training Supporting regeneration and place making initiatives
9.0Geographical Area of Report’s Implications
9.1The report deals with schemes to be funded through the Integrated Transport Block which are located within the Metropolitan Area, but will serve to improve connectivity across the wider WMCA.
10.0Other Implications
10.1No implications
Appendices
11.1APPENDIX 1 – Progress of Deliverables against 2018/19 Baseline Programme 11.2 APPENDIX 2 – Financial Summary
12.0Glossary of Terms
BCC = Birmingham City Council BCCI = Birmingham City Centre Interchange CA = Combined Authority CC = City Council CCTV = Closed Circuit Television DfT = Department for Transport
Page 3 of 8 [PUBLIC]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.