(1) The approval of £2.96m funding for the first three years of the West Midlands Innovation Programme operational costs (Phase 1) was confirmed. (2) The additional detail on the anticipated outputs/outcomes, structure and planned activity of the West Midlands Innovation Programme Phase 1 was approved. (3) The progress made in the planning and preparation phase since the Investment Board approval on 24 June 2019 in establishing the structure and initiating delivery of the West Midlands Innovation Programme Phase 1 was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Accountable Email: [email removed] Employee Tel 0121 214 7941
Report has been This programme was considered by the Investment Board (24th June considered by 2019) and was approved, subject to review by Investment Board before 10% of funds were spent. This review paper has been considered by the West Midlands Innovation Board, LIS Implementation Group, SED Board and the Senior Leadership Team.
Recommendation(s) for action or decision:
The Investment Board is recommended to:
1. Confirm the approval of £2.96m funding for the first three years of the West Midlands Innovation Programme (WMIP) operational costs (Phase 1). 2. Approve the additional detail on the anticipated outputs/ outcomes, structure and planned activity of WMIP Phase 1. 3. Note progress made in the planning and preparation phase since Investment Board Approval on 24th June 2019 in establishing the structure and initiating delivery of WMIP Phase 1.
1. Purpose 1.1 This report requests the confirmation of approval of £2.96m for operational innovation support and ecosystem development for the West Midlands Innovation Programme (WMIP) for its first three years (Phase 1), in the light of the additional information provided on structure, activities and outputs/ outcomes, and the progress towards delivery so far. Less than £200k of costs have been incurred since approval on 24 June 2019, well within the 10% limit of spend before coming back to the Investment Board for Review. 1.2 WMCA has an aspiration to ultimately deliver and/ or lever c.£36m of support (Phase 2) to new West Midlands innovation proposals over the eventual five-year life of the programme, subject to funding availability, which this initial investment will enable. 2. Context 2.1 On 24th June 2019 a paper was presented to the Investment Board on the West Midlands Innovation Programme Phase 1. They resolved (extract from minutes): 1. That the £2.96 million of funding for the first three years of the West Midlands Innovation Programme operational costs be approved subject to a formal review after 10% of the funding had been used; 2. That the proposed process for future funding drawdown, as detailed in the report be approved in principle but that it be noted that the source of such funding had yet to be identified; 3. That the aspiration to deliver ultimately circa £36 million of support to new innovation proposals over the five-year life of the programme be noted. 2.2 In the period since 24th June, there has been considerable activity to move to delivery of the Local Industrial Strategy, led by the WMCA Economy and Strategy Team, the LEPs and wide-ranging other stakeholders. The Innovation Alliance WM (supported by WMIP funding) has continued its work on developing WMIP, to align the plans for WMIP delivery with the emerging LIS delivery plans. This includes alignment with the Sector and Major Market Opportunity Action Plans, and with new structures emerging from these plans (eg Create Central and the emerging Life Sciences Cluster Body). 2.3 Appointment of a WMCA Innovation Lead in November (supported by WMIP funding) has further facilitated alignment with LIS delivery plans, with the Innovation Framework developed by the WM Innovation Board, and across wider WMCA Directorates. 2.4 This paper provides additional information on the WMIP Phase 1 programme structure, proposed activities and expected outputs/ outcomes, as well as setting out the progress towards delivery so far.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.