Investment Programme Dashboard- Red Rated Projects Update

Noted Committee 1 paper

AI summaryWest Midlands Combined Authority Investment Board notes eight red-rated projects on the Investment Programme Dashboard, with several Change Requests pending approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard noted current position and recovery actions
MoneyNo new funding approvedReport does not seek financial decisions
What happens nextChange Requests require Board approvalSeveral extensions and funding changes pending
Who it affectsProject sponsors and delivery partnersIncludes Solihull and Warwickshire councils

What was decided

The Board noted the current position of the eight red-rated projects, the reasons for the ratings and the progress being made to resolve outstanding matters.

The Board noted the factors contributing to delivery challenges and the actions being taken to agree revised delivery positions and progress approvals.

Why

A Red rating is applied where there is a variance of six months or more against the approved completion date, or where an issue materially affects delivery. Report 2.2

Main themes across the projects are revised delivery approaches needing approval, outstanding Change Requests, delayed Business Cases, land and infrastructure dependencies, and construction or completion issues. Report 2.3, P4, P5

What happens next

Until revised positions are formally approved, projects will continue to be recorded against the last approved date and position. Report 2.5, 2.6

The Investment Programme Team will continue working with project sponsors to progress outstanding approvals, monitor delivery and report changes through the Dashboard. Report 2.61

Several Change Requests for the Solihull projects and the A46 Stoneleigh Junction will require Investment Board approval before revised timescales or funding can be adopted. Report 2.14, 2.41, 2.48, 2.53

The money

  • £2.82 million Approved allocation for Accelerated Housing Delivery, of which £2.68 million claimed Report 2.9
  • £0.424 million Proposed increase to the Accelerated Housing Delivery programme allocation Report 2.11
  • £3.049 million Overall reduction across the Accelerated Housing Delivery Programme Report 2.11
  • £340,169 Approved allocation for Playing Pitch Implementation Strategy, of which £132,664 claimed Report 2.17
  • £244,480 Approved allocation for Middlewood House, of which £230,323 claimed Report 2.24
  • £450,000 Proposed revised allocation for Middlewood House Report 2.26
  • £495,060 Approved allocation for Rowood Drive, of which £284,672 claimed Report 2.31
  • £3.434 million Approved allocation for Chelmsley Wood, of which £2.88 million claimed
  • £575,000 Approved allocation for Solihull Town Centre Public Realm, of which £568,533 claimed Report 2.44
  • £148,879 Additional Investment Programme funding sought through available underspend for the Public Realm scheme Report 2.45, 2.47
  • £6.6m Approved allocation for A46 Stoneleigh Junction, with the full allocation claimed Report 2.51
  • £103m Approved allocation for Metro Wednesbury to Brierley Hill, with £102.94m claimed Report 2.56

Options considered

  • Rejected: Produce a closure report for the Metro extension rather than a Change Request. Suggested in the report as a potentially prudent alternative given completion is expected in the calendar year and no budget increase is needed

Implications

  • Financial: No new financial decisions are sought in this report; any financial implications from individual projects will continue to be managed through the appropriate governance processes. Report P71
  • Legal: No new legal decisions are sought; any legal implications will continue to be managed through the appropriate governance arrangements. Report P72
  • Risk: Several projects have unresolved Change Requests, including a contractual dispute with the main contractor on the A46 Stoneleigh Junction. Report 2.52, 2.53
  • Other: The Public Realm scheme is being reshaped into a streamlined, phased approach because the funding landscape has changed since the project was commissioned in 2019. Report 2.46

Who and where

  • Solihull Metropolitan Borough Council, as project sponsor and landowner for several red-rated schemes Report 2.8, 2.10
  • Warwickshire County Council, as delivery partner and likely funder of any A46 cost overruns Report 2.50, 2.53
  • Residents in Solihull, including future housing occupants and playing pitch users Report 2.8, 2.16, 2.27, 2.33
  • Future passengers of the extended Midland Metro between Brierley Hill, Dudley, Wolverhampton and Birmingham Report 2.55, 2.57

Timeline

  • March 2023: Most recently approved completion date for the Accelerated Housing Delivery programme, now passed Report 2.7
  • April 2026: Revised Change Request for Accelerated Housing Delivery submitted Report 2.14
  • 14 May 2026: Amended planning application submitted for Middlewood House Report 2.27
  • July 2026: Change Request updated following WMCA stakeholder feedback Report 2.14
  • By the end of August 2026: Amended planning application scheduled for submission for Rowood Drive Report 2.33
  • August 2026: Revised Change Request expected for Rowood Drive Report 2.32
  • June 2027: Proposed revised delivery timescales for Middlewood House Report 2.26
  • September 2027: Proposed extension sought for A46 Stoneleigh Junction due to construction delays Report 2.52
  • Autumn 2026: Entry into Service expected for the Metro Wednesbury to Brierley Hill extension Report 2.57
  • April 2028: Proposed revised completion date for Rowood Drive Report 2.32
  • April 2029: First Outline Business Case for Playing Pitch Implementation Strategy anticipated to be submitted Report 2.20
  • April 2032: Proposed extension of delivery timescales for the Accelerated Housing Delivery programme Report 2.11

Plain English for the jargon

  • Red rating: A dashboard status applied where there is a variance of six months or more against the approved completion date, or where an issue materially affects delivery.
  • Change Request: A formal proposal to update an approved project's timescales, funding or delivery approach, processed under the Single Assurance Framework.
  • OBC: Outline Business Case, a stage in the business case approval process before a Full Business Case.
  • SOC: Strategic Outline Case, the earliest stage in the business case approval process.
  • PPIS: Playing Pitch Implementation Strategy, a Solihull strategy being incorporated into the Accelerated Housing Delivery programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Resolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, including the reasons for the current ratings and progress being made to resolve outstanding matters be noted. 2. The factors contributing to delivery challenges and the actions being undertaken to agree revised delivery positions, progress approvals and address outstanding issues be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

2.1The information used to update the Dashboard is based on quarterly monitoring information provided by project sponsors and reviewed by the Investment Programme Team. This includes progress against approved outputs, financial position, milestones and issues impacting on delivery.

2.2Project delivery status is assessed against the approved programme position. A Red rating is applied where there is a variance of 6 months or more against the approved completion date, or where an issue has been identified that materially affects the delivery of the scheme.

2.3The current Red ratings reflect a range of project-specific circumstances. The main themes are: • revised delivery approaches requiring approval;

• outstanding Change Requests; • delays in progressing Business Cases; • land, technical and infrastructure dependencies; • construction and completion issues.

Current Position

2.4Currently eight projects are reported as Red on the Investment Programme Dashboard. Several projects require formal Change Requests to update approved timescales, funding arrangements or delivery approaches. These are being developed and assessed with project sponsors before being progressed through the relevant governance process.

2.5Until revised positions are formally approved, projects will continue to be recorded with the date based upon the last approval.

2.6The appraisal of Change Requests and Business Cases is important in establishing whether the allocated budget, proposed revised timescales, outputs, outcomes and benefits are realistic and achievable. Projects will therefore continue to report against their existing approved position until any changes have been formally agreed.

Project Summaries

A) Accelerated Housing Delivery – Utilising Solihull Assets

2.7The programme remains Red because the most recently approved completion date of March 2023 has passed and the revised Change Request requires approval.

2.8The programme supports housing delivery through the use of SMBC land interests and by addressing barriers to development, including site constraints, infrastructure requirements and land assembly issues.

2.9The original completion date of December 2022 was extended to March 2023. The approved allocation is £2.82 million, of which £2.68 million has been claimed.

2.10As part of the programme, a number of viable housing sites have been identified, including Middlewood House and Rowood Drive. Outline Business Cases (OBCs) will be prepared for each individual housing project and submitted to WMCA for consideration.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Investment Programme Dashboard- Red Rated Projects UpdateReport 167 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
SS
Councillor Stephen SimkinsChair, present
SC
Councillor Steve ClarkVice-Chair, present
CG
Councillor Chris GarghanCommittee Member - Voting, present
LK
Councillor Lynnette KellyCommittee Member - Voting, present
RN
Councillor Ray NockCommittee Member - Voting, present
DP
Councillor Dave PinwellCommittee Member - Voting, present
EW
Councillor Elaine WilliamsCommittee Member - Voting, present

On this subject at West Midlands Combined Authority

Search all
  1. Investment Programme Dashboard- Red Rated Projects UpdateThis decision
  2. Investment Programme UpdateApproved
  3. Investment Programme UpdateApproved
  4. Investment Programme UpdateApproved
  5. Investment Programme UpdateApproved
  6. Investment Programme UpdateApproved

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open
17 Aug 2026 Residential Investment Fund DashboardResolved that: The report be noted. Noted Open