That the petition submitted by Birmingham Friends of the Earth and considered by the committee on 6 January be noted; 2. That a change to the project relating to tree removal and its associated interaction with the petition report be noted and 3. That a final decision to proceed with the project would be retained by Birmingham City Council as Local Highway Authority by the Cabinet Member for Transport and the Environment through a Cabinet report be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
1.4Since the January TDC report, officers have continued to review the project to finalise a full business case (FBC) pursuant to submission to Birmingham City Council’s Cabinet Member for Transport and Environment who will make the final decision on the project.
1.5In developing the FBC, continuous review of the project design has taken place to both take on board the continued engagement with the local community and stakeholders but also to refine the technical design.
Tree Impact
1.6TDC will recall the scheme consulted upon included the removal of six mature trees through Balsall Heath. Following consultation and further design review, it was considered possible to retain three trees meaning that only three trees would require removal. The TDC report included a visual tree plan (shown in annex 1 of this update) showing the trees that 4, 5 and 6 could be retained.
1.7TDC was also advised that, following detailed site investigations to identify tree pit locations, it will be possible to replant 16 trees through Balsall Heath local centre (as well as further tree planting along Highgate Middleway) to mitigate the impact of tree loss. This would be complemented by further soft landscaping features incorporating greenery as part of the wider public realm scheme.
1.8On this basis, TDC accepted the recommendation of the officer petition panel that ‘the proposed reduction in tree removal and replacement tree strategy would, in principle, address the issues set out within the petition around tree impact. This would be subject to final confirmation of the tree/landscaping scheme to be taken to, and considered by, Transport for West Midlands (TfWM) Key Network Board and the BCC Cabinet Member for Transport and Environment as part of the FBC’.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.