(1) The achievements since the June meeting of the Transport Delivery Committee be noted. (2) The progress of deliverables and outturn of the 2021/22 Capital Programme be noted. (3) Where indicated, any variations from the baseline programme be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2021/22 Integrated Transport Block (ITB) Capital Programme allocation was approved by WMCA Board as part of the wider transport budget in February 2021.
2.2As with recent years, the ITB allocation for 2021/2022 has been fully utilised on continuing committed schemes and managing the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment. Through this approach, a steady state of asset condition across the estate can be maintained.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
3.0Achievements
3.1The following elements within the 2021/22 Capital Programme have been completed during July and August:
Longbridge Connectivity Project – The multi storey car park opened on Monday 16th August 2021
Perry Barr Rail Station and Bus Interchange – Planning permission for the bus interchange was secured on 22nd July 2021
University Station - The pre-cast concrete elements for the buildings at University were successfully and safely installed in June and July
Network Wide Cycling Programme 3A (NWCP) – The 2020/21 programme has been completed with installation of cycle parking at Coventry, Wolverhampton, Solihull and Birmingham New Street
West Midlands Cycle Hire – Approval obtained to install a further 24 docking stations
4.0Variations to Baseline Programme
4.1The following are variations to the baseline programme:
Network wide Park & Ride Expansion Developments – Phase 2 – Programme on hold due to postponing the majority of development works for Park & Ride expansion subsequent to the impacts Covid-19 has had on the demand for Park & Ride 5.0 Financial Implications
5.1The detailed financial aspects of the TfWM 2021/2022 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the position in financial terms is, however, attached to this report as Appendix 2
Legal implications
6.1There are no direct legal implications arising from the recommendations set out in this report. However, legal and procurement will support, as necessary, any deliverables that may arise throughout 2021/2022.
Equalities implications
7.1There are no equality implications arising from the recommendations set out in this report. The Equalities & Diversity Manager will support as project required any deliverables within the 2021/2022 capital programme.
8.0Inclusive Growth Implications
8.1The transport interventions set out within this report form an integral part of an efficient and resilient transport system which support inclusive growth objectives by:
Enabling wider labour markets, Providing access to skills, education and training Supporting regeneration and place making initiatives
9.0Geographical Area of Report’s Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.