(1) The achievements since the September 2021 meeting of the Transport Delivery Committee be noted. (2) The progress of deliverables and outturn of the 2021/2022 Capital Programme be noted. (3) Where indicated, any variations from the baseline programme be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The 2021/22 Integrated Transport Block (ITB) Capital Programme allocation was approved by WMCA Board as part of the wider transport budget in February 2021.
2.2As with recent years, the ITB allocation for 2021/2022 has been fully utilised on continuing committed schemes and managing the existing asset base with respect to replacement and or renewal of life expired/obsolete equipment. Through this approach, a steady state of asset condition across the estate can be maintained.
2.3Attached to this report (Appendix 1) is the detailed monitoring report for the TfWM Capital programme outlining deliverables, indicating the baseline date with an indication of the current forecast date with a RAG indicator.
3.0Achievements
3.1The following elements within the 2021/22 Capital Programme have been completed during September and October:
Dudley Interchange - Works to procure contractor through open tender exercise are now complete with activities being completed to award contract
University – Two major milestones were delivered;
1) The Canal Footbridge and Rail Link Bridge were successfully installed 2) Legal agreements for canal footbridge are complete
Perry Barr Rail Station and Bus Interchange – positive progress in construction, with all major steelwork, lift shafts and stairs now installed. Works commenced on the bus interchange north entrance
West Midlands Cycle Hire – Scheme now rolled out across all 7 Local Authorities, with 1,216 (as of 1st October 2021) bikes currently out on street
Digital Panel Rollout - Clear Channel contract negotiations are now complete and include an additional 110 digital panels across the TfWM estate over the remainder of the contract 4.0 Variations to Baseline Programme
4.1The following are variations to the baseline programme:
Network wide Park & Ride Expansion Developments – Phase 2 – Programme on hold due to postponing the majority of development works for Park & Ride expansion subsequent to the impacts Covid-19 has had on the demand for Park & Ride
University – The scheme has been re-baselined which shows an improvement in the opening date
Financial implications
5.1The detailed financial aspects of the TfWM 2021/2022 Capital Programme are reported separately under the Financial Monitoring Report to this Committee. A summary of the position in financial terms is, however, attached to this report as Appendix 2
Legal implications
6.1There are no direct legal implications arising from the recommendations set out in this report. However, legal and procurement will support, as necessary, any deliverables that may arise throughout 2021/2022.
Equalities implications
7.1There are no equality implications arising from the recommendations set out in this report. The Equalities & Diversity Manager will support as project required any deliverables within the 2021/2022 capital programme.
8.0Inclusive Growth Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Delivery Committee at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.