Financial Monitoring Report 2022 / 23

Noted Committee 1 paper

Transport Delivery Committee noted this item on Monday 10 October 2022. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

(1) The year to date position as at the end of August 2022 against the Transport for West Midlands revenue budget, showing an overall favourable variance of £1.4m, was noted. (2) The Transport for West Midlands capital programme expenditure as at the end of August 2022, totalling £102.1m, which was £38.3m below budget, was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Transport Delivery Committee

Transport Delivery Committee Date 10 October 2022

Report title Financial Monitoring Report

Accountable Director Linda Horne, Executive Director of Finance and Business Hub, West Midlands Combined Authority Email: [email removed] Tel: (0121) 214 7508

Accountable Kate Taylor, Head of Finance Business Partnering Employee and Strategic Planning, West Midlands Combined Authority Email: [email removed]

Report has been Councillor Pervez Akhtar considered by

Recommendation(s) for action or decision:

The Transport Delivery Committee is recommended to:

1. Note the year to date position as at the end of August 2022 against the TfWM Revenue Budget shows an overall favourable variance of £1.4m, as detailed in Section A.

2. Note the TfWM Capital Programme expenditure as at the end of August 2022 totals £102.1m, which is £38.3m below budget, as detailed in Section B. 1. Purpose

1.1This report sets out the financial position as at 31 August 2022. The content relates to the financial position of the Combined Authority’s Transport Delivery Revenue and Capital Budgets and consists of the following Sections:

SECTION A

2.0Section A - Summary Revenue Position

2.1The year to date position on the Transport revenue budget as at the end of August 2022 shows an overall favourable variance of £1.4m against budget.

August 2022 Year to Date Full Year Actual Budget Variance Forecast Budget Variance £'000 £'000 £'000 £'000 £'000 £'000 Net TfWM Surplus / (Deficit) before reserves 2,244 (2,423) 4,667 (8,898) (9,078) 180 Use of Reserves 485 3,776 (3,291) 9,333 9,078 255

Net TfWM Surplus / (Deficit) 2,729 1,353 1,376 435 0 435

2.2The most notable variance at this early stage of the year relates to Concessions where there is lower than budgeted patronage and fare levels.

These savings have been partly offset by lower than budgeted drawdown of reserves to support the overall budget as they have not yet been required.

2.3As noted in the previous report, the key movements within the full year position reflects an increase in the MML operating costs of £4.2m to reflect ongoing cost pressures and revenue lost during the service shutdown. This increase has been offset by additional Local Transport Fund (LTF) grant of £1.8m and non-pay savings of £2.5m.

2.4Further details of net spending are set out in Appendix 1.

SECTION B

3.0Summary Position TfWM Capital Budget

3.1Overall, TfWM Capital Programme expenditure totalled £102.1m which was £38.3m below the August year to date budget of £140.4m, with the variance primarily contained within the Investment Programme portfolio (£19.2m). YEAR TO DATE - AUGUST 22 FULL YEAR TRANSPORT PROGRAMME ACTUAL BUDGET VARIANCE FORECAST BUDGET VARIANCE £000 £000 £000 £000 £000 £000

Investment Programme 58,700 77,912 19,212 197,535 205,285 7,750

CWG Programme 34,317 48,536 14,219 61,285 61,535 250

Other Major Programmes 5,162 8,309 3,147 35,399 38,878 3,479 Minor Work Programme 997 1,971 974 8,243 8,565 322 Grants to Local Authorities 2,438 2,790 352 17,086 36,757 19,671 CRSTS 477 864 387 58,808 90,343 31,535

TOTAL 102,091 140,382 38,291 378,356 441,363 63,007 3.2 The TfWM delivered Investment Programme portfolio comprises the largest of the five Programmes within the Transport Programme, containing the schemes which feature in the WMCA Devolution Deal Investment Programme to be delivered by TfWM. These schemes are all, to some extent, funded from the West Midlands Combined Authority Devolution Deal funding arrangements.

3.3The Transport Programme has been categorised into six sub programmes. The largest of these is the Investment Programme with a budget to August of £77.9m, including Rail, Sprint & Metro Extension Schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring Report 2022 / 23Report 392 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
RW
Councillor Richard WorrallChair, present
TH
Councillor Timothy HuxtableVice-Chair, present
ML
Councillor Mary LockeVice-Chair, present
PA
Councillor Pervez AkhtarCommittee Member, present
RA
Councillor Robert AldenCommittee Member, apologies
LB
Councillor Linda BighamCommittee Member, apologies
ZC
Councillor Zaker ChoudhryCommittee Member, expected
BG
Councillor Bill GavanCommittee Member, apologies
RG
Councillor Robert GrinsellCommittee Member, present
SH
Councillor Shabrana HussainCommittee Member, present
CH
Councillor Carol HyattCommittee Member, present
NK
Councillor Narinder Kaur Kooner OBECommittee Member, present

All 19 on the meeting page

On this subject at West Midlands Combined Authority

Search all
  1. Financial Monitoring Report 2022 / 23This decision
  2. West Midlands Combined Authority (WMCA) Financial Monitoring Outturn 2025/26Noted
  3. 2025/26 Quarter 3 Update and Financial Monitoring ReportNoted
  4. 2026/27 Budget Update and 2025/26 Financial MonitoringNoted
  5. 2026/27 Budget Update and 2025/26 Financial MonitoringNoted
  6. 2026/27 Budget Update and 2025/26 Financial MonitoringNoted

More from West Midlands Combined Authority Transport Delivery Committee

All decisions
MeetingDecisionOutcome
6 Feb 2023 Apologies for AbsenceCouncillor Bill Gavan (Sandwell), Councillor Anne Millward (Dudley), Councillor Clare Simm (Wolverhampton) and Counci... Decided Open
6 Feb 2023 Chair's RemarksThe Chair noted the recent death of William Whiting, Chair of the Stourbridge Line Users Group and former Chair of We... Noted Open
6 Feb 2023 Minutes - 9 January 2023Agreed as a correct record. Agreed Open
6 Feb 2023 Matters ArisingThe committee noted matters arising from the minutes. Noted Open
6 Feb 2023 Forward PlanA plan of items to be reported to future meetings was noted. Noted Open